Week 9 OpScheduling
Week 9 OpScheduling
Week 9 OpScheduling
Operations Scheduling
Operations Scheduling
• Time to use equipment & time to perform activities
• The order/sequence for processing jobs
• Can yield Cost Savings & increase Productivity
Scheduling Context
• Scheduling constrained by
higher level decisions:
‒ plant capacity
‒ equipment selection
‒ the PP&C Cycle
• aggregate plan, master
schedule & material
requirements plan
In order to do this schedule the CR’s have be calculated for each job:
CR(A)=(5/4)=1.25
CR(B)=(10/7)=1.43 This is a Static application of CR
CR(C)=(6/3)=2.00 rule; see basic text (page 708)
CR(D)=(4/1)=4.00 for Dynamic application version
No, Jobs B, C and D
The CR schedule is A-B-C-D (same as the FCFS schedule) are going to be late.
6 7 11 10 6 0 1 5 4
2
Jobs
3 5 7 6 3 0 2 4 3
3
5 10 12 9 5 0 5 7 4
4
0 1 0 2
Column Min
0 0 5 2 0 1 5 4
2
Jobs
0 1 4 1 0 2 4 3
3
0 4 7 2 0 5 7 4
4
0 1 0 2
Column Min
0 0 5 2
2
Jobs
0 1 4 1
3
4 0 4 7 2
1 0 5 2
2
Jobs
0 0 3 0
3
4 0 3 6 1
1 0 5 2
2
Jobs
0 0 3 0
3
4 0 3 6 1
1-to-1
assignments
Assignment 1-C 2-B 3-D 4-A
at minimum
Cost $2 $7 $6 $5 $20 Total cost