Lecture Schedulling
Lecture Schedulling
Lecture Schedulling
• Frequently results in
buildup of work-in-
process inventory
Due
Now Date
Forward and Backward Scheduling
• Backward scheduling begins with the due date and schedules the
final operation first
• Schedule is produced by working backwards though the processes
Due
Often these approaches are combined to develop a Now Date
trade-off between capacity constraints and customer
expectations
Finite and Infinite Loading
Assigning jobs to workstations
Finite loading assigns work up to the capacity of the
workstation
• All work gets done
• Due dates may be pushed out
Infinite loading does not consider capacity
• All due dates are met
• Capacities may have to be adjusted
Scheduling Criteria
Average
Average Number of Average
Completion Utilization Jobs in Lateness
Rule Time (Days) Metric (%) System (Days)
FCFS 15.4 36.4 2.75 2.2
Average
Average Number of Average
Completion Utilization Jobs in Lateness
Rule Time (Days) Metric (%) System (Days)
FCFS 15.4 36.4 2.75 2.2
With CR < 1, Job B is late. Job C is just on schedule and Job A has
some slack time.
Critical Ratio (CR) Technique
Time 0 3 10 20 28 33
WC
1 B E D C A
Idle
WC
2
Job
completed
Johnson’s Rule
Johnson’s Rule Example
Example
WORK CENTER 1 WORK CENTER
JOB (DRILL PRESS) 2 (LATHE)
A 5 2
B 3 6
C 8 4 B E D C A
D 10 7
E 7 12
Time 0 3 10 20 28 33
WC
1 B E D C A
Idle
WC
2 B E D C A
Job
Timeè 0 1 3 5 7 9 10 11 12 13 17 19 21 22 23 25 27 29 31 33 35 completed
B E D C A