0% found this document useful (0 votes)
32 views20 pages

Kishor Dadmal Sfcs

Download as ppt, pdf, or txt
Download as ppt, pdf, or txt
Download as ppt, pdf, or txt
You are on page 1/ 20

SHOP FLOOR CONTROL

SYSTEM

Presented by:-
KISHOR L. DADMAL
Roll no. 20,
Marathwada Institute of Technology,
Aurangabad.
Shop Floor Control System
 Introduction:-
Production management systems are
concerned with two related objectives;
planning and control of the manufacturing
operations. The functions of production
planning, development of the master schedule,
capacity planning and MRP all deal with
planning objective. System that accomplished
this objective termed as ‘Shop floor control ‘.
Major Functions
1. Assigning priority of each shop order

2. Maintaining work-in-process quantity


information

3. Conveying shop-order status information to


the office
Major Functions
4. Providing actual output data for capacity control
purposes

5. Providing quantity by location by shop order for


WIP inventory and accounting purposes

6. Providing measurement of efficiency, utilization,


and productivity of manpower and machines
Shop floor control system
 The shop floor control system consists of three
steps.

1.Order release.

2.Order scheduling

3.Order progress.
Order Release
 The purpose of order release is to provide the
necessary documentation that accompanies an
order as it is processed through the shop.
 The shop packet for an order consists of :

1.Route sheet.
2.Material requisitions.
3.Job cards.
4.Move ticket.
5.Parts list.
Order Scheduling
 The purpose is to make assignment of the order to
the various machines in the factory.

 It is the function of priority control to schedule


the order for production according to their
priorities.

 The basic document prepared by the order


scheduling module is dispatch list.
Order Progress
 The purpose of the order progress module is to
accomplish the remaining three function of
shop floor control;

 To provide data relative to work in progress.

 Shop order status.

 Capacity control.
Order Scheduling
 It reports the job that should be done at each work
center and certain details about the routing of the part.

 The dispatch list is generated each day or each shift

 In an effective shop floor control system, documents


represents to the foreman or production supervisor
the best way for accomplishing the master schedule
Dispatch List
WORK LOT PRIOR NEXT START DUE REMAIN
ORDER QUANTI WORK WORK DATE DATE ING
TY CENTER CENTER HOURS
1573 25 370 400 1-14 1-25 27.6

1688 300 370 400 1-14 1-28 40.5

1692 107 265 375 1-17 1-31 13.6

1693 14 370 342 1-17 2-4 12.0

2053 27 240 375 1-20 1-28 16.2


Operations Scheduling
 The nature and importance of job shops

 Job-shop scheduling (n jobs on one machine)

 Shop-floor control

 Issues in scheduling service personnel


Principles of Scheduling
1. There is a direct equivalence between work
flow and cash flow.

2. The effectiveness of any job shop should be


measured by speed of flow through the shop.

3. Schedule jobs as a string, with process steps


back to back.

4. A job once started should not be interrupted.


Principles of Scheduling
5. Speed of flow is most efficiently achieved by
focusing on bottleneck work centers and jobs.

6. Reschedule every day.

7. Obtain feedback each day on jobs that are not


completed at each work center.

8. Match work center input information to what


the worker can actually do.
Principles of Scheduling
9. When seeking improvement in output, look
for incompatibility between engineering
design and process execution.

10. Certainty of standards, routings, and so forth


is not possible in a job shop, but always work
towards achieving it.
Priority Rules for Job
Sequencing
1. First-come, first-served (FCFS)

2. Shortest operating time

3. Earliest due date first

4. Earliest start date first (due date-lead time)

5. Least slack time remaining first


Priority Rules for Job
Sequencing
6. Least slack time remaining (per operation as opposed to
per job) first
7. Smallest critical ratio first
(due date-current date)/(number of days remaining)

8. Smallest queue ratio first


(slack time remaining in schedule)/(planned remaining queue time)

9. Last come, first served


10. Random order
Job Sequencing Example
First-Come First-Served
Jobs (in order Processing Due Date
of arrival) Time (days) (days hence) Orders submitted
A 4 5 at beginning of week
B 7 10
C 3 6
D 1 4
n-jobs on one machine

FCFS Schedule
Jobs (in order Processing Due Date Flow Time
of arrival) Time (days) (days hence) (days)
A 4 5 4 Late?
B 7 10 11
C 3 6 14
On-Time?
D 1 4 15
Job Sequencing Example
Last-Come First-Served
Jobs (in order Processing Due Date
of arrival) Time (days) (days hence) Orders submitted
A 4 5 at beginning of week
B 7 10
C 3 6
D 1 4
n-jobs on one machine

Last-Come First-Served Schedule


Jobs (in order Processing Due Date Flow Time
of arrival) Time (days) (days hence) (days)
D 1 4 1 Late?
C 3 6 4 On-Time?
B 7 10 11
A 4 5 15
Job Sequencing Example
Shortest Operating Time
Jobs (in order Processing Due Date
of arrival) Time (days) (days hence) Orders submitted
A 4 5 at beginning of week
B 7 10
C 3 6
D 1 4
n-jobs on one machine

Shortest Operating Time Schedule


Jobs (in order Processing Due Date Flow Time
of arrival) Time (days) (days hence) (days)
D 1 4 1
Late?
C 3 6 4 On-Time?
A 4 5 8
B 7 10 15
Job Sequencing Example
Earliest Due Date First
Jobs (in order Processing Due Date
of arrival) Time (days) (days hence) Orders submitted
A 4 5 at beginning of week
B 7 10
C 3 6
D 1 4
n-jobs on one machine

Earliest Due Date First


Jobs (in order Processing Due Date Flow Time
of arrival) Time (days) (days hence) (days)
D 1 4 1 Late?
A 4 5 5 On-Time?
C 3 6 8
B 7 10 15

You might also like