Production Systems: Colegio de San Juan de Letran Calamba

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

Colegio de San Juan de Letran Calamba

City of Calamba, Laguna, Philippines 4027 www.letran-calamba.edu.ph +63(049) 545-5453loc2030

School of Engineering and Architecture

Production Systems
Production (Shop Floor) Scheduling & Management
PART 2

Work Center Defined


• A work center is an area in a business in which productive
resources are organized and work is completed.

• May be a single machine, a group of machines, or an area where a


particular type of work is done.

IE Department © 2019 Letran – Calamba 2


Scheduling Techniques
• Infinite scheduling
– An approach to scheduling that initially
assumes infinite capacity and then
manually “levels the load” of resources
that have exceeded capacity. (Ex: MRP)

• Finite loading
– An approach to scheduling that loads
jobs in priority order and delays to
those jobs for which current capacity is
exceeded.

IE Department © 2019 Letran – Calamba 3

Scheduling Techniques
• Forward scheduling
– starts processing when a job is received

• Backward scheduling
– begin scheduling the job’s last activity so that the job is finished on due date

IE Department © 2019 Letran – Calamba 4


Typical Scheduling and Control Functions
• Allocating orders, equipment, and personnel.

• Determining the sequence of order performance.

• Initiating performance of the scheduled work.

• Shop-floor control
– Scheduling and monitoring day-to-day production in a job shop. It is also
known as production control or production activity control.

IE Department © 2019 Letran – Calamba 5

Work-Center Scheduling Objectives


• Meet due dates

• Minimize lead time

• Minimize setup time or cost

• Minimize work-in-process inventory

• Maximize machine utilization

IE Department © 2019 Letran – Calamba 6


Sequencing
– The process of assigning priorities to jobs so that they are processed
in particular order

Priority Rules for Job Sequencing


1. First come, first served (FCFS)
2. Last come, first served (LCFS)
3. Earliest due date (EDD)
4. Shortest processing time (SPT)
5. Longest processing time (LPT)
6. Slack
(Due date – today’s date) – processing time
7. Critical ratio (CR):
(Due Date – Today’s Date)
Processing Time

IE Department © 2019 Letran – Calamba 7

Schedule Performance Measures


• Meeting due dates of customers or downstream operations.

• Minimizing the flow time (the time a job spends in the process).

• Minimizing work-in-process inventory.

• Minimizing idle time of machines or workers.

IE Department © 2019 Letran – Calamba 8


Example of Job Sequencing: First-Come First-Served

Jobs (in order Processing Due Date


of arrival) Time (days) (days hence)
A 4 5
B 7 10
C 3 6
D 1 4
Assume: Today is day 1 of the planning cycle.

Completion
Jobs
Jobs StartingStarting time Completion
Processing time Due Time
time Processing time Due Time
(in order of
(in order of arrival) (days) (days) (days) Time Time Tardiness
Tardiness
(days) (days)(days)
arrival) (days) (days)
D 0 1 1 4 0
A 0 4 4 5 0
A 1 4 5 5 0
B 4 7 11 10 1
C
C 11
5 3
3 14
8 6
6 8
2
D B 14 8 1 7 15 15 4 10 115
Total
Total 44 29 207
Average
Average 11 7.25 1.75
5

IE Department © 2019 Letran – Calamba 9

Example of Job Sequencing: Last-Come First-Served

Jobs (in order Processing Due Date


of arrival) Time (days) (days hence)
A 4 5
B 7 10
C 3 6
D 1 4
Assume: Today is day 1 of the planning cycle.

Jobs Completion
Completion
Jobs StartingStarting
time time Processing
Processing time time Due Time
Due Time
(in order of Time Time Tardiness
Tardiness
(in order of arrival) (days) (days) (days) (days) (days)(days)
arrival) (days) (days)
D 0 1 1 4 0
D 0 1 1 4 0
C A 1 1 3 4 4 5 6 5 00
B C 4 5 7 3 11 8 10 6 12
A B 11 8 4 7 15 15 5 10 105
Total
Total 31 29 117
Average
Average 7.75 7.25 2.75
1.75

IE Department © 2019 Letran – Calamba 10


Example of Job Sequencing: Earliest Due Date First

Jobs (in order Processing Due Date


of arrival) Time (days) (days hence)
A 4 5
B 7 10
C 3 6
D 1 4
Assume: Today is day 1 of the planning cycle.

Jobs Completion
Completion
Jobs StartingStarting
time time Processing
Processing time time Due Time
Due Time
(in order of Time Time Tardiness
Tardiness
(in order of arrival) (days) (days) (days) (days) (days)(days)
arrival) (days) (days)
D 0 1 1 4 0
D 0 1 1 4 0
A A 1 1 4 4 5 5 5 5 00
C C 5 5 3 3 8 8 6 6 22
B B 8 8 7 7 15 15 10 10 55
Total
Total 29 29 77
Average
Average 7.25 7.25 1.75
1.75

IE Department © 2019 Letran – Calamba 11

Example of Job Sequencing: Shortest Processing Time

Jobs (in order Processing Due Date


of arrival) Time (days) (days hence)
A 4 5
B 7 10
C 3 6
D 1 4
Assume: Today is day 1 of the planning cycle.

Completion
Jobs
Jobs StartingStarting time Completion
Processing time Due Time
time Processing time Due Time
(inorder
(in orderofofarrival) (days) (days) Time Time Tardiness
Tardiness
(days) (days) (days)(days)
arrival) (days) (days)
D 0 1 1 4 0
D 0 1 1 4 0
A 1 4 5 5 0
C 1 3 4 6 0
A
C 4
5 4
3 8
8 5
6 3
2
B B 8 8 7 7 15 15 10 10 55
Total
Total 28 29 87
Average
Average 7 7.25 1.75
2

IE Department © 2019 Letran – Calamba 12


Example of Job Sequencing: Minimum Slack (SLACK)

Jobs (in order Processing Due Date Slack = (due date – today’s date) – processing time
of arrival) Time (days) (days hence)
A 4 5 A= 5−1 −4=0
B 7 10 B= 10 − 1 − 7 = 2
C 3 6 C= 6−1 −3=2
D 1 4
D= 4−1 −1=2
Assume: Today is day 1 of the planning cycle.

Jobs Completion
Completion
Jobs StartingStarting
time time Processing
Processing time time Due Time
Due Time
(in order of Time Time Tardiness
Tardiness
(in order of arrival) (days) (days) (days) (days) (days)(days)
arrival) (days) (days)
D 0 1 1 4 0
A 0 4 4 5 0
D A 4 1 7 4 11 5 10 5 10
C C 11 5 3 3 14 8 6 6 82
B B 14 8 1 7 15 15 4 10 115
Total
Total 44 29 207
Average
Average 11 7.25 5
1.75

IE Department © 2019 Letran – Calamba 13

Example of Job Sequencing: Critical Ratio Method


(DueDate – Today’s Date)
Critical Ratio =
Processing Time
Jobs (in order Processing Due Date
(5−1)
of arrival) Time (days) (days hence) A= =1
4
A 4 5 (10−1)
B= = 1.29
B 7 10 7
(6−1)
C 3 6 C= = 1.67
3
D 1 4 (4−1)
D= =3
1
Assume: Today is day 1 of the planning cycle. Arrange smallest to highest 

Jobs Completion
Completion
Jobs StartingStarting
time time Processing
Processing time time Due Time
Due Time
(in order of Time Time Tardiness
Tardiness
(in order of arrival) (days) (days) (days) (days) (days)(days)
arrival) (days) (days)
D 0 1 1 4 0
A 0 4 4 5 0
B A 4 1 1 4 5 5 10 5 00
C C 5 5 3 3 8 8 6 6 22
D B 8 8 7 7 15 15 4 10 115
Total
Total 32 29 137
Average
Average 8 7.25 3.25
1.75

IE Department © 2019 Letran – Calamba 14


Sequencing Jobs through Two Serial Processes:
Johnson’s Rule/ Procedure

The smallest processing time is 1 hour, occurs at Time in Hours


stage 1 for job D, since it is on stage 1 we place job
D to the beginning of the sequence. Jobs Stage 1 Stage 2

D A 1.50 1.25
B 2.00 3.00
The next smallest is 1.25 hours. It occurs at stage
2 for job A, so we place it to the end of the C 2.50 2.00
sequence. D 1.00 2.00
D A
Sequence 1 2 3 4
The next smallest time is 2 hours. It occurs at stage
1 for job B and at stage 2 for job C. Thus, we place Job
job B as near to the beginning of the sequence and
job C as near to the end.

D B C A

IE Department © 2019 Letran – Calamba 17

Shop-Floor Control: Major Functions


1. Assigning priority of each shop order.

2. Maintaining work-in-process quantity information.

3. Conveying shop-order status information to the office.

4. Providing actual output data for capacity control purposes.

5. Providing quantity by location by shop order for WIP inventory


and accounting purposes.

6. Providing measurement of efficiency, utilization, and


productivity of manpower and machines.

IE Department © 2019 Letran – Calamba 18


Input/Output Control

Work
Input Output
Center

• I/O control is a capacity-control technique used to monitor work


flow at individual work centers

• Planned input should never exceed planned output.

• Focuses attention on bottleneck work centers.

IE Department © 2019 Letran – Calamba 19

Principles of Work Center Scheduling


1. There is a direct equivalence between work flow and cash flow.

2. The effectiveness of any job shop should be measured by speed


of flow through the shop.

3. Schedule jobs as a string, with process steps back-to-back.

4. A job once started should not be interrupted.

5. Speed of flow is most efficiently achieved by focusing on


bottleneck work centers and jobs.

6. Reschedule every day.

IE Department © 2019 Letran – Calamba 20


Principles of Job Shop Scheduling (Continued)
7. Obtain feedback each day on jobs that are not completed at each
work center.

8. Match work center input information to what the worker can


actually do.

9. When seeking improvement in output, look for incompatibility


between engineering design and process execution.

10. Certainty of standards, routings, and so forth is not possible in a


job shop, but always work towards achieving it.

IE Department © 2019 Letran – Calamba 21

Personnel Scheduling in Services


• Scheduling consecutive days off

• Scheduling daily work times

• Scheduling hourly work times

IE Department © 2019 Letran – Calamba 22