Detailed Estimate of DLRB

sl.no Description Nos Length Breadth Depth Qty


1 Earthwork excavation for foundations of
structures as per drawing and technical
specification including setting out, construction of
shoring and bracing, removal of stumps and other
deleterious matter, dressing sides of bottom and
back filling with approved material as per
specifications.

for abutments (L/s & R/s)(+ 375.490 - 371.240) 2 10.100 4.55 4.250 390.62
for wing walls (L/s & R/s)(+ 375.490 - 371.240) 4 2.600 3.80 4.250 167.96
Total qty 558.58
cum
2 Providing and laying insitu vibrated CC M-20 ( 28
days cube compressive strength not less than10
N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded
aggregates for foundation filling including cost
of all materials, machinery, labour,
formwork,cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc.,

CC M20 40MSA for Levelling


course&abutments&wing walls foundation CC
under abutments (L/s & R/s) 2 9.800 3.95 0.500 38.71
under wing walls (L/s & R/s) 4 2.000 3.20 0.500 12.80
Total qty 51.51
cum
3 Providing and laying insitu vibrated CC M-20 ( 28
days cube compressive strength not less than20
N / sq mm) grade cement concrete using 40 mm
down size approved, clean, hard, graded
aggregates for sub-structure / super- structure
works including cost of
allmaterials,machinery,labour,formwork,scaffolding,
cleaning,batching,mixing,placing in position,
leveling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. for Sub
/super structure for Abutments & Returns

for Abutments (+ 371.74 to + 374.390) 2 9.450 (2.95+0.76)/2 2.650 105.18

Providing and laying insitu vibrated CC M-15 ( 28


days cube compressive strength not less than20
N / sq mm) grade cement concrete using 40 mm
down size approved, clean, hard, graded
aggregates for sub-structure / super- structure
works including cost of
4 allmaterials,machinery,labour,formwork,scaffolding,
cleaning,batching,mixing,placing in position,
leveling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. for Sub
/super structure for Abutments & Returns

for Wing walls (+375.490 to + 371.740) 4 2.000 (2.5+0.5)/2 3.750 45.00


Total qty in cum 150.18
sl.no Description Nos Length Breadth Depth Qty

Providing and laying insitu vibrated M-25 ( 28 days


cube compressive strength not less than 20 N / sq
mm ) grade cement concrete using 20 mm down
size approved, clean, hard, graded aggregates for
deck slab & kerb including cost of all
materials,machinery, labour, formwork, scaffolding,
5 cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement
content: 330 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)

RCC M25 20MSA for bedblock,Deckslab&Dirtwall


bed block on abutments horizontal phase 2 9.450 0.38 0.300 2.15
bed block on abutments vertical phase 2 9.450 0.38 1.000
Deckslab 1 7.740 8.35 0.700 45.24
Kerb walls 2 7.740 0.475 0.275 2.02
parapet walls 2 7.740 0.200 0.825 10.22
Total qty 59.63
cum
6 Providing and laying insitu vibrated RCC M-30 ( 28 days cube
compressive strength not less than 30 N / sq mm) grade cement
concrete using 20 mm down size approved, clean, hard, graded
aggregates for Approach slab works including cost of all
materials,machinery, labour, formwork, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.

Approach slabs 2 3.500 8.35 0.150 8.77


Total qty 8.77
7 Providing and laying insitu vibrated CC M-25 ( 28 days cube
compressive strength not less than 30 N / sq mm) grade cement
concrete using 20 mm down size approved, clean, hard, graded
aggregates for Wearing coat including cost of all
materials,machinery, labour, formwork, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.

on deckslab(1spans) 1 7.74 8.35 0.100 6.46


On Approach Slabs 2 3.50 7.50 0.100 5.25
Total qty in cum 11.71
8 Providing, fabricating and placing in position reinforcement steel
bars for RCC works including cleaning, straightening, cutting,
bending, hooking, lapping, welding wherever required,tying
with1.25 mm dia soft annealed steel wire, including cost of all
materials, machinery, labour etc., complete with initial lead upto 50
and all lifts.

As per steel calculation sheet Total steel qty for DLRB in kgs 4246.36
13 Providing Weep holes with 75 mm dia AC pipe for concrete /
masonry walls including providing 20 x 20 x 20 cm size porous 1 :
4 proportion including 10 cm thick sand backing at the junction of
wall and soil back fill, cost of all materials, machinery, labour etc.,
complete with lead upto km and all lifts.

In Wing walls 4x2 0.6 4.80


In Abutments 2x6 2.10 21.00
sl.no Description Nos Length Breadth Depth Qty
Total Qty in RMT 25.80
14 Providing homogeneous embankment using soil
from approved borrow area in layers of 25 to 30 cm
before compaction including cost of all materials,
machinery, labour, all operations such as
excavation, sorting out, transportation, spreading
soil in layer of specified thickness, breaking clods,
sectioning,etc.,complete with initial lead upto 1 km
and all lifts.

Backfilling

for abutments (L/s & R/s)(+ 371.24 - 374.39) 2 10.100 4.55 3.150 289.52
for Wing wall (L/s & R/s)(+ 371.24 - 375.49) 4 2.600 3.80 4.250 167.96
CC Qty deduction
under abutments (L/s & R/s) 2 9.800 3.95 0.500 -38.71
under Returns (L/s & R/s) 4 2.000 3.20 0.500 -12.80

for Abutments (+ 259.800 to + 262.800) 2 9.450 (2.95+0.76)/2 2.650 -105.18

for reurns (+259.800 to + 263.965) 4 2.000 (2.5+0.5)/2 3.750 -39.00


Total qty 261.788
cum
15 Providing drainage spouts

on 4 slabs 1x4 4.00


Total Qty in No.s 4.00
17 Providing 20mm thick 790mm depth mastic pad

slab joints 2 8.35 16.70


Total Qty in Rmt 16.70
Bar
Bar dia Spacing in No. of Length in
SL. Bar description length shape mm mm Members bars M
Abutments
1 dirtwall on abutment main bars 10 2 6 9.45
2 dirt wall on abutment 2 legged stirrups 12 250 2 39 2.9
3 bed block on abutment main bars 12 2 6 9.45
4 bed block on abutment 2 legged stirrups 10 130 2 74 1.5

for 2 abutmnets (416.


Slab
Bottom steel
1 main bars dia p1 25mm@150mm c/c 25 150 1 48 7.74
2 main bars dia p3 25mm@140mm c/c 25 140 1 6 7.74
3 Distribution bars p2 10mm dia@110mm c/c 10 110 1 70 8.35
Top steel
1 main bars dia p6 10mm@230mm c/c 10 230 1 34 8.35
2 Distribution bars 10mm dia@300mm c/c 10 300 1 28 7.74
II Kerb walls
1 main bars 8mm dia 8 2 12 7.74
2 Distribution bars 10mm dia@300mm c/c 10 300 2 26 1.3

for 1 slabs(2396.27
Approach slab
Main bars 12mm dia 150 c/c 12 150 2 24 7.2
Distribution bars 12 dia 150c/c 12 150 4 24 8.3

for Approach slabs(239


Total steel Qty for DLRB
Total unit Total
length in weight weight in
M Kg/Rmt kgs

113.4 0.617 69.9678


226.2 0.89 201.318
9.45 0.89 8.4105
222 0.617 136.974
Quantity in kgs 416.6703
for 2 abutmnets (416.67x2) 833.3406

371.52 3.85 1430.352


46.44 3.85 178.794
584.5 0.62 362.39

283.9 0.62 176.018


216.72 0.62 134.3664

185.76 0.39 72.4464


67.6 0.62 41.912
Quantity in kgs 2396.2788
for 1 slabs(2396.27x1) 2396.2788

345.6 0.89 307.584


796.8 0.89 709.152
Quantity in kgs 1016.736
for Approach slabs(2396.27x1) 1016.736
Total steel Qty for DLRB 4246.3554