Detailed Estimate (DLRB NOW
Detailed Estimate (DLRB NOW
Detailed Estimate (DLRB NOW
for abutments (L/s & R/s)(+ 375.490 - 371.240) 2 10.100 4.55 4.250 390.62
for wing walls (L/s & R/s)(+ 375.490 - 371.240) 4 2.600 3.80 4.250 167.96
Total qty 558.58
cum
2 Providing and laying insitu vibrated CC M-20 ( 28
days cube compressive strength not less than10
N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded
aggregates for foundation filling including cost
of all materials, machinery, labour,
formwork,cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc.,
As per steel calculation sheet Total steel qty for DLRB in kgs 4246.36
13 Providing Weep holes with 75 mm dia AC pipe for concrete /
masonry walls including providing 20 x 20 x 20 cm size porous 1 :
4 proportion including 10 cm thick sand backing at the junction of
wall and soil back fill, cost of all materials, machinery, labour etc.,
complete with lead upto km and all lifts.
Backfilling
for abutments (L/s & R/s)(+ 371.24 - 374.39) 2 10.100 4.55 3.150 289.52
for Wing wall (L/s & R/s)(+ 371.24 - 375.49) 4 2.600 3.80 4.250 167.96
CC Qty deduction
under abutments (L/s & R/s) 2 9.800 3.95 0.500 -38.71
under Returns (L/s & R/s) 4 2.000 3.20 0.500 -12.80
for 1 slabs(2396.27
Approach slab
Main bars 12mm dia 150 c/c 12 150 2 24 7.2
Distribution bars 12 dia 150c/c 12 150 4 24 8.3