A-Complete Building-Estimation-Sample by WWW
A-Complete Building-Estimation-Sample by WWW
A-Complete Building-Estimation-Sample by WWW
Construction of Flats
LEAD C H A R T (SSR 2008-09)
Initial
cost as Machine Conve- Deduct Seignora-
Sl. Source of Lead in Blasting GRAND
Description of Material Unit per SSR Curshing yance stacking age
No. supply Kms Charges Total
excluding charges charges charges charges
stacking
1 2 3 5 4 5 6 7 8 9 10 11
1 Cement 1 M.T. 4500.00 4500.00
2 Steel (HYSD Bars) 1 M.T. 45000.00 45000.00
3 Steel Mild steelBars 1 M.T. 44800.00 44800.00
4 Flyash Lime Solid Blocks-Size
290X225X140MM(50Kg/Sqcm)(P.8) 23 cm th. Walls 1000 Nos 13000.00 13000.00
5 Flyash Lime Solid Blocks-Size 290X
112/100X140MM(50kg/SQcm) (P-8) 10 cm th. Walls 1000 Nos 6000.00 6000.00
6 Sand for Mortor (179) KM21/0+2 1 Cum. 250 175.00 - - 1216.00 -5.50 36.00 1421.50
7 Sand for filling (180) Local 1 Cum. 250 60.00 - - 1216.00 -5.50 36.00 1306.50
SS-5 Metal
8
6 mm Hard Granite Metal (113) Crusher @ KM 6/4+0.2 1
KMCum.
MR 31 421.30 70.00 105.33 297.00 -8.70 45.00
929.93
9 10 mm Hard Granite Metal (114) do 1 Cum. 31 551.30 70.00 137.83 297.00 -8.70 45.00 1092.43
10 12 mm - do - (115) do 1 Cum. 31 681.30 70.00 170.33 297.00 -8.70 45.00 1254.93
11 20 mm - do - (116) do 1 Cum. 31 836.30 70.00 209.08 297.00 -8.70 45.00 1448.68
12 40 mm - do - (118) do 1 Cum. 31 491.30 70.00 122.83 297.00 -8.70 45.00 1017.43
13 65mm - do - (121) do 1 Cum. 31 316.30 70.00 - 297.00 -8.70 45.00 719.60
14 CRSMasonry (101) do 1 Cum. 31 209.30 69.00 - 297.00 -8.70 45.00 611.60
15 Rough Stone (HBG) (100) do 1 Cum. 31 146.30 67.00 - 297.00 -8.70 45.00 546.60
Rough Stone 225mm thick for Dry
- 297.00 -8.70
16 packing (HBG) (96) do 1 Cum. 31 108.30 45.00 441.60
17 Gravel (177) Local 1 Cum. 32 50.50 - 273.60 -5.50 20.00 338.60
Polished Shabad stones (Tandur blue
10 Sqm 1291.00 - - - 60.00 1351.00
18 variety) 15 to 18mm thick
Certificates
I Certified that the above leads are correct to the best of my knowledge and belief.
ii Certified that the above work is located with in the radius of Muncipality/Municipal Corporation Limits.
iii Certified that the labour available locally is not adequate, hence the importation of labour is incorporated.
Certified that the above rates in respect of cost of the materials, stacking charges, blasting charges, machine crushing charges, conveyance charges and
iv seignorage charges are being incorporated as per the SSR 2008 - 09.
MORTAR CHART
2 Cement Mortar ( 1:1.5 ) 1 Cum. 960 4320.00 1421.50 28.00 14.84 5784.34
3 Cement Mortar ( 1:2 ) 1 Cum. 720 3240.00 1421.50 28.00 14.84 4704.34
4 Cement Mortar ( 1:3 ) 1 Cum. 480 2160.00 1421.50 28.00 14.84 3624.34
5 Cement Mortar ( 1:4 ) 1 Cum. 360 1620.00 1421.50 28.00 14.84 3084.34
6 Cement Mortar ( 1:5 ) 1 Cum. 288 1296.00 1421.50 28.00 14.84 2760.34
7 Cement Mortar ( 1:6 ) 1 Cum. 240 1080.00 1421.50 28.00 14.84 2544.34
8 Cement Mortar ( 1:8 ) 1 Cum. 180 810.00 1421.50 28.00 14.84 2274.34
Scaffolding charges
a) For Superstructure in GF over foundation 982 40.00 1 Cum
b) for SF over the rate of FF 983 48.00 1 cum
c) for TF over the rate of SF 984 65.00 1 cum
d) for every addl. Floor over TF 985 29.00 1 cum
42 Centering Charges
Centering, shuttering, scaffolding with props and steel plate as per the approved shuttering
plan and other accessories as per the norms and stability calculations
43 Lift Charges
A For RCC
a) Between 1st - 2nd 1024 55.00 1 Cum
b) Between 2nd - 3rd 1025 137.00 1 Cum
c) Between 3rd - 4th 1026 254.00 1 Cum
d) Between 4th -5th 1027 400.00 1 Cum
e) Between 5th -6th 1028 436.00 1 Cum
f) Between 6th -7th 1029 545.00 1 Cum
Sl. S.No in
Items Rate per
No SSR
g) Between 7th -8th 1030 635.00 1 Cum
h) Between 8th -9th 1031 708.00 1 Cum
i) Between 9th -10th 1032 817.00 1 Cum
j) For every additional floor above 10th floor 109.00 1 Cum
D For Plastering
a) Between 1st - 2nd 1041 11.00 10 .Sqm
b) Between 2nd - 3rd 1042 19.00 10 .Sqm
c) Between 3rd -4th 1043 29.00 10 .Sqm
d) Add for every additional floor above 4th floor 1044 13.00 10 .Sqm
DATAS ( As per SSR-2008-09)
Add for MA & LALI @ 53% 0.53
Part-A Sub-Structure 'A' Civil work
S.No Qty Particulars Rate unit Amount
1 Earth work excavation and depositing on bank with an initial lead of 10 meters and lift of 2 meters in
mixture of gravel and soft disintegrated rock like shales, ordinary gravel stoney earth and earth mixed with
fair sized boulders which does not require blasting including shoring, shuttering and bailing out water for
foundations.
Unit - One Cum
1 Rate of Earth work as per SSR (P.24, Sl.No.246) 41.50 1 Cum 41.50
S.S-20B
0.75 Add 75% for foundations of buildings (as per 41.50 1 Cum 31.13
preamble of SSR, Page No.4)
0.53 Add for MA & LALI @ 53% 41.50 1 22.00
94.63
Sundries 0.07
Total Rate per 1 CUM 94.70
2 Earth work excavation and depositing on bank with an initial lead of 10 meters and one extra lift over
initial lift of 2 meters in mixture of gravel and soft disintegrated rock like shales, ordinary gravel stoney
earth and earth mixed with fair sized boulders which does not require blasting including shoring, shuttering
and bailing out water for foundations.
Unit - One Cum
1.00 Rate of Earth work as per SSR (P.24, Sl.No.246) 41.50 Cum 41.50
S.S-20B 1
0.75 Add 75% for foundations of buildings (as per 41.50 1 Cum 31.13
preamble of SSR, page No.4)
1 Add for one extra lift (P. No.24, Sl. No.258) 1.70 1 Cum 1.70
0.53 Add for MA & LALI @ 53% 41.50 1 22.00
96.33
Sundries 0.07
Total Rate per 1 CUM 96.40
3 Earth work excavation and depositing on bank with an initial lead of 10 meters and two extra lifts over
initial lift of 2 meters in mixture of gravel and soft disintegrated rock like shales, ordinary gravel stoney
earth and earth mixed with fair sized boulders which does not require blasting including shoring, shuttering
and bailing out water for foundations.
3 Add for three extra lifts (P. No.24, Sl. No.258) 1.70 1 Cum 5.10
0.53 Add for MA & LALI @ 53% 41.50 1 22.00
99.73
0.07
Total Rate per 1 CUM 99.80
5 Earth work excavation and depositing on bank with an initial lead of 10 meters and lift of 2 meters in
loamy and clayee sioils like B.C Soil , red earth and ordinary gravel including shoring, shuttering and bailing
out water etc., complete for Open foundations.
Unit - One Cum
1.00 Rate of earth work as per SSR (P.23, Sl.No.240) 37.50 1 Cum 37.50
S.S-20B
0.53 Add for MA & LALI @ 53% 37.50 1 19.88
57.38
Sundries 0.02
Total Rate per 1 CUM 57.40
6 Earth work excavation and depositing on bank with an initial lead of 10 meters and lift of 2 meters in
loamy and clayee sioils like B.C Soil , red earth and ordinary gravel including shoring, shuttering and bailing
out water etc., complete for foundations.
7 Earth work excavation and depositing on bank with an initial lead of 10 meters and one extra lift over
initial lift of 2 meters in loamy and clayee sioils like B.C Soil , red earth and ordinary gravel including
shoring, shuttering and bailing out water et complete for foundations.
9 Excavation and depositing on bank with all initial leads and lifts in hard rock and boulders more than 3
cum in size wherever quarrying is done by controlled blasting as per standard specifications and as
directed by Engineer in charge.
10 Excavation in rock by way of benching, chiseling, wedging and boring in rock in foundations, grade
levelling including all lead and lift charges and disposal of rock from the site as directed by the department
(Rs.180/- per cum will be recovered to the extent of entire stone quantity excavated.Site should be cleared
by the contractors at his own cost by disposing the excavated rock soon after excavation is done as
directed by the department.)
11 Disposal of excavated earth available at site (using machine) to a distance of 500 Mts. and filling in
Ditches, Lowlying area and road embankment in layers not exceeding 15cm thick, consolidating each
deposited layer by watering and ramming including all operational, incidental, labour charges, hire charges
of T&P etc., complete for finished item of work.
12 Disposal of excavated surplus rock available at site with a lead of 3 KM including transporting, loading
and unloading charges etc., complete as directed by the Engineer in charge.
Unit - One Cum
1 Conceyance charges as per SSR 132.00 1 cum 132.00
1 Deduct stacking charges -8.70 1 cum -8.70
123.30
sudries 0.00
Total Rate per 1 CUM 123.30
13 Earth work excavation using machinery in all soils upto soft disintegrated rock and stone matrix and
dumped within a radius of 5 mts. including all incidental charges, hire, charges of machinary and vehicles
etc., complete for finished item of work.
14 Earth work excavation using machinery in hard disintegrated rock-I & II and dumped within a radius of 5
mts. including all incidental charges, hire, charges of machinary and vehicles etc., complete for finished
item of work.
Unit - One Cum
Rate as per GO MS No.10 of Finance (Works & 19.50
1.00 Projects) Dept. dt.26.07.2005 19.50 1.00 Cum
Total Rate per 1 CUM 19.50
15 Refilling with useful excavated earth other than sand complying with standard specifications in layers of
150 mm thick including watering, tamping, consolidation as directed by Engineer in charge including all
operational charges, conveyance of water etc., to work site and all labour charges etc., complete as per
standard specifications and as directed by Engineer in charge for filling of basements and sides of
foundations.
16 Carting of useful excavated earth available at site(using machine) duly carting to an average distance
of 0.50 KM. and filling in Ditches, Low lying area and road embankment in layers not exceeding 15cm thick,
consolidating each deposited layer by watering and ramming including all operational, incidental, labour
charges, hire charges of T&P etc., complete for finished item of work.
17 Carting of useful excavated earth available at site(using machine) duly carting to an average distance
of 3 KM. and filling in Ditches, Low lying area and road embankment in layers not exceeding 15cm thick,
consolidating each deposited layer by watering and ramming including all operational, incidental, labour
charges, hire charges of T & P etc., complete for finished item of work.
Unit - One Cum
1 Rehandling charges with machine(P.7 of preamble) 6.50 1 cum 6.50
18 Drillng holes of 25 MM dia and 800 mm deep in hard rock or sheet rock with pneumatic compresssor and
placing of 20mm dia Tor steel bars and grouting the holes with C.M (1;2) prop excluding cost of steel and its
fabrication charges but including cost and conveyance of all materials and labour charges etc complete as
directed by department for finished item of work.
Unit - One R M
1 Drillilng of holes rate as per item 229 (ii), P.22 110.00 1 RM 110.00
1 Grouting charges as per Item No.232(ii), P.22 81.00 1 RM 81.00
Total Rate per 1 RM 191.00
20 Plain cement concrete work of mix (1:5:10) prop. using 40mm guage hard granite machine crushed metal
including cost of machine mixing, laying, levelling, tamping, curing and conveyance of all materials and all
operational, incidental and labour charges,seignorage charges etc. complete for levelling course below
column footings and below flooring.
Unit-One Cum
0.92 Rate of 40 mm HBG Metal (as per lead chart) 1017.43 1 Cum 936.03
0.46 Cost of C.M (1:5) 2760.34 1 Cum 1269.76
1.00 Labour charges as per labour chart including 774.00 1 Cum 774.00
MA&LI
1.00 Machine mixing charges (item 292, P 151 of 45.00 1 Cum 45.00
common SSR)
-0.46 (-) deduct mortar mixing charges 28.00 1 Cum -12.88
-0.46 (-) deduct allowance on mortar mixing charges 14.84 1 Cum -6.83
Total 3005.08
Sundries 0.02
Total Rate per 1 CUM 3005.10
21 Construction of Random Rubble stone masonry in CM (1:8) prop: (Cement: Sand) using using hard
stones of granite variety from approved quarry including cost and conveyance of all materials like cement,
sand, water, stones etc., from approved quarry, to site and including seigniorage charges, sales & other
taxes on all materials including labour for cutting stones to required size and shape, mixing, of cement,
mortar, construction, scaffolding charges, curing etc., complete for finished item of work below plinth beam,
side drains etc.,
Unit-One Cum
1.10 Rate of R.R. Stone of granite variety ( as per lead 546.60 1 Cum 601.26
chart)
0.34 Cost of cement mortar (1:8) 2274.34 1 Cum 773.28
1 Labour charges as per labour chart including 1158.09 1 Cum 1158.09
MA&LI
2532.63
Sundries 0.07
Total Rate per 1 CUM 2532.70
22 PCC (1:3:6) Prop: Mix with graded hard granite stone aggregate of size 20mm SS-5 hard Granite including
cost and conveyance of all materials and water to work site seignorage, all operational incidential, labour
charges such as centering form work (steel centering), mixing concrete, laying, lift charges, tamping, curing
etc., complete for finished item of work as per standard specifications for Bed Blocks and hold fasts as
directed by the department.
b 0.92 Cost of 12mm HBG SS5 graded metal 1157.44 1 Cum 1064.84
0.30 Cost of cement 4100.00 1 MT 1230.00
0.46 Cost of sand 1421.50 1 Cum 653.89
1.00 Labour Charges as per labour chart inclusive of 1369.29 1 Cum 1369.29
MA&LALI
1.00 Mixing charges as per design mix(item 1009, P62) 100.00 1 Cum 100.00
Basic Rate 4418.02
Sundries 0.08
Total Rate per 1 CUM 4418.10
24 VRCC M25 grade Design Mix (by weigh batching)to the required strength as per SS and IS-456:2000
using stone aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 300 kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) mixing concrete, laying, lift charges, vibrating, curing etc., complete for finished item
of work as per standard specification but excluding cost of steel reinforcement and its fabrication charges
etc., complete for finished item of work as directed by the department (Basic Rate).
25 VRCC M 30 grade Design Mix (by weigh batching)to the required strength as per SS and IS-456:2000
using stone aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 320 kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) mixing concrete, laying, lift charges, vibrating, curing etc., complete for finished item
of work as per standard specification but excluding cost of steel reinforcement and its fabrication charges
etc., complete for finished item of work as directed by the department (Basic Rate).
Unit - One Cum
0.92 Cost of 20mm HBG SS5 graded metal 1338.69 1 Cum 1231.59
0.32 Cost of cement 4100.00 1 MT 1312.00
0.46 Cost of sand 1421.50 1 Cum 653.89
1.00 Labour Charges as per labour chart inclusive of 1369.29 1 Cum 1369.29
MA & LA LI
1.00 Mixing charges as per design mix using weigh 100.00 1 Cum 100.00
batching (item 1009, P62)
Basic Rate 4666.77
Sundries 0.03
Total Rate per 1 CUM 4666.80
26 VRCC M 30 grade Design Mix (by weigh batching)to the required strength as per SS and IS-456:2000
using Coarse aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 320 kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) providing steel centering, shuttering and scaffolding with props and steel plate as per
the approved shuttering plan and other accessories as per the norms and stability calculations including
cost and conveyance of all accessories, mixing concrete, laying, lift charges, vibrating, curing etc., complete
for finished item of work as per standard specification but excluding cost of steel reinforcement and its
fabrication charges etc., complete for finished item of work as directed by the department for footings.
Unit - One Cum
1.00 Cost of M 30 design mix concrete 4666.77 1 Cum 4666.77
1.00 Centering charges (I No.978, P.61) 715.00 1 Cum 715.00
1.00 Vibrating charges (p.151, Item..291) 43.00 1 Cum 43.00
Total 5424.77
Sundries 0.03
Total Rate per 1 CUM 5424.80
27 VRCC M 25 grade Design Mix (by weigh batching)to the required strength as per SS and IS-456:2000
using Coarse aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 300 kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) providing steel centering, shuttering and scaffolding with props and steel plate as per
the approved shuttering plan and other accessories as per the norms and stability calculations including
cost and conveyance of all accessories, mixing concrete, laying, lift charges, vibrating, curing etc., complete
for finished item of work as per standard specification but excluding cost of steel reinforcement and its
fabrication charges etc., complete for finished item of work as directed by the department for footings.
Unit - One Cum
28 VRCC M 30 grade Design Mix (by weigh batching)to the required strength as per SS and IS-456:2000
using Coarse aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 320 kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) providing steel centering, shuttering and scaffolding with props and steel plate as per
the approved shuttering plan and other accessories as per the norms and stability calculations including
cost and conveyance of all accessories, mixing concrete, laying, lift charges, vibrating, curing etc., complete
for finished item of work as per standard specification but excluding cost of steel reinforcement and its
fabrication charges etc., complete for finished item of work as directed by the department for Pedestals
Unit-One Cum
1.00 Cost of M 30 design mix concrete 4666.77 1 Cum 4666.77
1.00 Centering charges (I No.978, P.61) 963.00 1 Cum 963.00
1.00 Vibrating charges (p.151, Item..291) 43.00 1 Cum 43.00
Total 5672.77
Sundries 0.03
Total Rate per 1 CUM 5672.80
29 VRCC M 25 grade Design Mix (by weigh batching)to the required strength as per SS and IS-456:2000
using Coarse aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 300 kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) providing steel centering, shuttering and scaffolding with props and steel plate as per
the approved shuttering plan and other accessories as per the norms and stability calculations including
cost and conveyance of all accessories, mixing concrete, laying, lift charges, vibrating, curing etc., complete
for finished item of work as per standard specification but excluding cost of steel reinforcement and its
fabrication charges etc., complete for finished item of work as directed by the department for Pedestals.
Unit-One Cum
1.00 Cost of M 25 design mix concrete 4584.77 1 Cum 4584.77
1.00 Centering charges (I No.978, P.61) 963.00 1 Cum 963.00
1.00 Vibrating charges (p.151, Item..291) 43.00 1 Cum 43.00
Total 5590.77
Sundries 0.03
Total Rate per 1 CUM 5590.80
30 VRCC M 30 grade Design Mix (by weigh batching)to the required strength as per SS and IS-456:2000
using Coarse aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 320 kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) providing steel centering, shuttering and scaffolding with props and steel plate as per
the approved shuttering plan and other accessories as per the norms and stability calculations including
cost and conveyance of all accessories, mixing concrete, laying, lift charges, vibrating, curing etc., complete
for finished item of work as per standard specification but excluding cost of steel reinforcement and its
fabrication charges etc., complete for finished item of work as directed by the department for Plinthbeams.
Unit-One Cum
1.00 Cost of M 30 design mix concrete 4666.77 1 Cum 4666.77
1.00 centering charges (I No.980, P.61) 1071.00 1 Cum 1071.00
31 VRCC M 25 grade Design Mix (by weigh batching)to the required strength as per SS and IS-456:2000
using Coarse aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 320 kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) providing steel centering, shuttering and scaffolding with props and steel plate as per
the approved shuttering plan and other accessories as per the norms and stability calculations including
cost and conveyance of all accessories, mixing concrete, laying, lift charges, vibrating, curing etc., complete
for finished item of work as per standard specification but excluding cost of steel reinforcement and its
fabrication charges etc., complete for finished item of work as directed by the department for Plinthbeams.
Unit-One Cum
1.00 Cost of M 25 design mix concrete 4584.77 1 Cum 4584.77
1.00 centering charges (I No.980, P.61) 1071.00 1 Cum 1071.00
1.00 Vibrating charges (p.151, Item..291) 43.00 1 Cum 43.00
Total 5698.77
Sundries 0.03
Total Rate per 1 CUM 5698.80
32 VRCC M 30 grade Design Mix(by weigh batching) to the required strength as per SS and IS-456:2000
using stone aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 320kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) using adjustable jack screw props and Acro span beams including all pipe bracings,
clamps, coupling,prefabricated steel "H" frames,cross members mixing concrete, laying, lift charges,
vibrating, curing etc., complete for finished item of work as per standard specification but excluding cost of
steel reinforcement and its fabrication charges etc., complete for finished item of work as directed by the
department for columns .
Unit-One Cum
1.00 Cost of M 30 design mix concrete 4666.77 1 Cum 4666.77
1.00 Centering charges (P.61, Item 983 / 994 ) 1587.00 1 Cum 1587.00
1.00 Vibrating Charges (P. 25, item 291) 43.00 1 Cum 43.00
Total 6296.77
Sundries 0.03
Cellar / Stilt /Ground floor rate Total Rate per 1 CUM 6296.80
33 VRCC M 25 grade Design Mix(by weigh batching) to the required strength as per SS and IS-456:2000
using stone aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 300kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) using adjustable jack screw props and Acro span beams including all pipe bracings,
clamps, coupling,prefabricated steel "H" frames,cross members mixing concrete, laying, lift charges,
vibrating, curing etc., complete for finished item of work as per standard specification but excluding cost of
steel reinforcement and its fabrication charges etc., complete for finished item of work as directed by the
department for columns .
34 VRCC M 30 grade Design Mix (by weigh batching) to the required strength as per SS and IS-456:2000
using stone aggregate of size 20 mm gauge graded hard granite machine crushed metal from approved
quarry using a minimum quantity of 320 kgs of cement per cum of concrete mechanically mixed, and
placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) using adjustable jack screw pipes and Acro span beams including all pipe bracings,
clamps, coupling, prefabricated steel "H" frames, cross members,mixing concrete, laying, lift charges,
vibrating, curing etc., complete for finished item of work as per standard specification but excluding cost of
steel reinforcement and its fabrication charges etc., complete for finished item of work as directed by the
department for beams.
Unit-One Cum
1.00 Cost of M 30 design mix concrete 4666.77 1 cum 4666.77
1.00 Centering charges (P.62, Item 997) 2415.00 1 cum 2415.00
1.00 Vibrating Charges (P. 25, item 291) 43.00 1 cum 43.00
Total 7124.77
Sundries 0.03
Cellar / Stilt /Ground floor rate Total Rate per 1 CUM 7124.80
35 VRCC M 25 grade Design Mix (by weigh batching) to the required strength as per SS and IS-456:2000
using stone aggregate of size 20 mm gauge graded hard granite machine crushed metal from approved
quarry using a minimum quantity of 300 kgs of cement per cum of concrete mechanically mixed, and
placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) using adjustable jack screw pipes and Acro span beams including all pipe bracings,
clamps, coupling, prefabricated steel "H" frames, cross members,mixing concrete, laying, lift charges,
vibrating, curing etc., complete for finished item of work as per standard specification but excluding cost of
steel reinforcement and its fabrication charges etc., complete for finished item of work as directed by the
department.for beams.
Unit-One Cum
1.00 Cost of M20 design mix concrete 4584.77 1 cum 4584.77
1.00 Centering charges (P.62, Item 997) 2415.00 1 cum 2415.00
1.00 Vibrating Charges (P. 25, item 291) 43.00 1 cum 43.00
Total 7042.77
Sundries 0.03
Ground floor rate Total Rate per 1 CUM 7042.80
Unit-One Cum
a) Cellar slab - 175 mm Thick
1.00 Rate of M 30 design mix concrete 4666.77 1 Cum 4666.77
5.71 Centering charges (item 998) 334.00 1 Sqm 1907.14
1.00 Vibrating Charges (P 25 Item 291) 43.00 1 Cum 43.00
Total 6616.91
Sundries 0.09
Ground Floor Total Rate per 1 CUM 6617.00
36 VRCC M 25 grade Design Mix ( by weigh batching) to the required strength as per SS and IS-456:2000
using stone aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 300 kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering) using adjustable jack screw props and Acro span beams including all pipe
bracings,clamlps,couplings,prefabricated steel "H" frames,cross members,mixing concrete, laying, lift
charges, vibrating, curing etc., complete for finished item of work as per standard specification but excluding
cost of steel reinforcement and its fabrication charges etc., complete for finished item of work as directed by
the department.for Roof Slabs.
Unit-One Cum
a) 115 mm Thick
1.00 Rate of M 25 design mix concrete 4584.77 1 Cum 4584.77
8.70 Centering charges (item 998) 271.00 1 Sqm 2357.70
1.00 Vibrating Charges (P 25 Item 291) 43.00 1 Cum 43.00
Total 6985.47
Sundries 0.03
Ground Floor Total Rate per 1 CUM 6985.50
c) 175 mm Thick
1.00 Rate of M 25 design mix concrete 4584.77 1 Cum 4584.77
5.71 Centering charges (item 998) 334.00 1 Sqm 1907.14
1.00 Vibrating Charges (P 25 Item 291) 43.00 1 Cum 43.00
Total 6534.91
Sundries 0.09
Ground Floor Total Rate per 1 CUM 6535.00
37 VRCC M30 grade Design Mix (by weigh batching) to the required strength as per SS and IS-456:2000
using stone aggregate of size 20mm SS-5 HBG gauge graded hard granite machine crushed metal from
approved quarry using a minimum quantity of 320kgs of cement per cum of concrete mechanically mixed,
and placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form
work (steel centering), mixing concrete, laying, lift charges, vibrating, curing etc., complete for finished item
of work as per standard specification but excluding cost of steel reinforcement and its fabrication charges
etc., complete for finished item of work as directed by the department for Retaining wall.
Unit-One Cum
1.00 Rate of M 30 design mix concrete 4666.77 1 Cum 4666.77
1.00 Centering charges (SL.No.301, P.28) 850.00 1 Cum 850.00
1.00 Vibrating Charges (P 25 Item 291) 43.00 1 Cum 43.00
Total 5559.77
Sundries 0.03
Sub cellar Floor Total Rate per 1 CUM 5559.80
38 Reinforced Cement Concrete M20 grade Design Mix (by weigh batching) to the required strength as per
SS and IS-456:2000 using stone aggregate of size 12 mm gauge graded hard granite machine crushed
metal using a minimum quantity of 300 kgs. of cement per one cum of concrete mechanically mixed, and
placing necessary reinforcement in position including cost and conveyance of all materials and water to
work site, seigniorage fee, all taxes and operational, incidental, labour charges such as centering from
work (steel centering) using adjustable jack screw props and Acro span beams including all pipe
bracings,clamlps,couplings,prefabricated steel "H" frames,cross members, mixing concrete, laying, lift
charges, vibrating, curing etc., complete 75 mm thick at fixed end, 50 mm thick at free end with average
thickness of 6.25 cm including plastering to all exposed faces 12mm thick in two coats with base coat of
8mm thick in CM(1:6) prop. and top coat of 4mm thick in CM(1:4) with dubara sponge finishing including
providing drip course band of 12 mm x 12 mm in cm(1:4) prop. including labour charges for mixing mortor
,laying,
and curing etc., charges
its fabrication completeetc.,
but complete
excludingfor
cost
60ofcm
steel
wide Sun-shades (or) Chajjas.
Unit-One Sqm
0.0625 Rate of M20 design mix concrete 4418.10 1 Cum 276.13
1.00 Centering charges (S.No 993) 220.00 1 Sqm 220.00
2.00 Plastering charges (as per data item No.47) 155.40 1 Sqm 310.80
Total 806.93
Sundries 0.07
Ground Floor Total Rate per 1 Sqm 807.00
fabrication charges etc., complete for finished item of work as directed by the department for Lintels and
Bressumers.
Unit-One Cum
1.00 Rate of M20 design mix concrete 4584.77 1 Cum 4584.77
1.00 Centering charges (item 980 P.61) 1071.00 1 Cum 1071.00
1.00 Vibrating Charges (P 151 Item 291) 43.00 1 Cum 43.00
Total 5698.77
Sundries 0.03
Ground Floor /Stilt Floor Total Rate per 1 CUM 5698.80
40 RCC M20 grade Design Mix (by weigh batching)to the required strength as per SS and IS-456:2000 using
stone aggregate of size 12 mm SS-5 GRADED gauge graded hard granite machine crushed metal using a
minimum quantity of 300 kgs of cement per one cum of concrete mechanically mixed, and placing
necessary reinforcement in position including cost and conveyance of all materials and water to work site,
seigniorage fee, all taxes and all operational, incidental, labour charges such as centering from work (steel
centering), mixing concrete, laying, lift charges, vibrating, curing including plastering 12mm thick with base
coat of 8 mm thick in CM(1:6) and finishing coat of 4mm thick in CM(1:4) dubara sponge finish to all
exposed surfaces for finished item of work as per standard specification but excluding cost of steel and its
fabrication charg,es etc., complete for finished item of work as directed by the Engineer in charge for
Platforms and Lofts of 50mm thick.
Unit-One Sqm
0.05 Rate of M20 design mix concrete 4418.10 1 cum 220.91
1.00 Centering charges 138.00 1 Sqm 138.00
2.00 Plastering charges two coats 155.40 1 Sqm 310.80
669.71
Sundries 0.09
Ground Floor Total Rate per 1 Sqm 669.80
41 RCC M20 grade Design Mix (by weigh batching) to the required strength as per SS and IS-456:2000 using
stone aggregate of size 12 mm SS-5 HBG gauge graded hard granite machine crushed metal using a
minimum quantity of 300 kgs of cement per one cum of concrete mechanically mixed, and placing
necessary reinforcement in position including cost and conveyance of all materials and water to work site,
seigniorage fee, all taxes and all operational, incidental, labour charges such as centering from work (steel
centering) mixing concrete, laying, lift charges, vibrating, curing etc., complete plastering with CM (1:4)
prop. 12mm thick with a base coat of 8 mm thick in CM(1:6) and finishing coat of 4mm thick in CM(1:4)
dubara sponge finish to all exposed surfaces for finished item of work as per standard specification but
excluding cost of steel and its fabrication charg,es etc., complete for finished item of work as directed by the
department for Racks/Shelves of 25.4mm thick. Unit-One Sqm
0.0254 Rate of M20 design mix concrete 4418.10 1 cum 112.22
42 Plain Cement Concrete M 25 Design Mix ( by weigh batching ) to the required strength as per
IS:456:2000 using stone aggregate of size 20mm hard granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 300 kgs. of cement per 1 cum of concrete
including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate,
water etc., to site and cost of seigniorage charges on all materials including steel centering, shuttering,
machine mixing, laying concrete, vibrating,lift charges, curing etc., complete for finished item of work as
directed by the department for steps.
Unit-One Cum
1.00 Rate of M25 design mix concrete 4584.77 1 Cum 4584.77
-1.00 Deduct design mix labour charges 1369.29 1 Cum -1369.29
1.00 PCC labour charges 774.00 1 Cum 774.00
1.00 Centering charges (item 991) 715.00 1 Cum 715.00
1.00 Vibrating Charges (P 21 Item 291) 43.00 1 Cum 43.00
Total 4747.48
sundries 0.02
Ground Floor 4747.50
First Floor
Lift charges 55.00 1 Cum 4802.48
sundries 0.02
First Floor rate 4802.50
43 VRCC M 25 grade Design Mix (by weigh batching) to the required strength as per SS and IS-456:2000
using stone aggregate 20mm (SS 5) graded hard granite machine crushed metal from approved quarry
using a minimum quantity of 300 kgs of cement per cum of concrete, placing necessary reinforcement in
position including cost and conveyance of all materials, water to work site, seigniorage charges and all
taxes and all operational, incidental, labour charges such as centering form work (steel centering) and
scaffolding charges for RCC members including all materials and labour charges for forming including
mixing concrete as per design mix in mechanical Weigh Batching units upto 15 Cum/hr capacity, placing
concrete, lift charges, vibrating, curing etc., complete but excluding cost of steel and its fabrication charges
etc., complete for finished item of work as per standard specifications and as directed by the Engineer in
charge for Terrace water tank side walls.
Unit-One Cum
a) 150 mm Thick
1.00 Rate of M 25 design mix concrete 4584.77 1 Cum 4584.77
6.67 Centering charges (item 33-b-(4)) 452.00 1 Sqm 3013.33
1.00 Vibrating Charges (P 25 Item 291) 43.00 1 Cum 43.00
Total 7641.10
Sundries 0.00
Ground Floor Rate per 1 Cum 7641.10
First Floor
Lift charges 55.00 1 Cum 7696.10
Sundries 0.00
1st Floor Rate Rate per 1 Cum 7696.10
45 Masonry in CM (1:6) prop. with Fly ash Gypsum, stone quarry dust and lime solid blocks of size
290x150x140 mm (made up of Flyash, Lime and Gypsum) with compressive strength not less than
50kg/sq.cm including cost and conveyance of all materials, labour charges, curing etc., complete for
external walls and corridor walls.
Unit-One Cum
148 Cost of Flyash lime soild blocks 7.00 1 Nos 1036.00
0.10 Cost of Cement Mortar (1:6) 2544.34 1 Cum 254.43
1.00 Labour charages including MA & LALI 1039.73 1 Cum 1039.73
2330.16
Scaffolding Lift
Ground Floor/Stilt Floor rate
Basic rate +scaffolding(36) (61/970) 40.00 0.00 2370.16
Sundries 0.04
Ground Floor/Stilt Floor rate Total Rate per 1 CUM 2370.20
46 Reinforced Masonry for partition walls 100mm thick in CM(1:6) prop. using Flyash Gypsum, stone
quarry dust lime solid blocks of size 290mmx100mmx140mm made up of Fly ash Gypsum and lime having
minimum compressive strength of not less than 50 Kg/Sq.cm and placing 2 Nos. of 6mm M.S plain rods at
sill and lintel level with free ends of the reinforcement pegged into mortar joints of main brick walls where
ever applicable including cost and conveyance of all materials, scaffolding charges,seignorage charges
curing, etc., complete but excluding cost of steel and its fabrication charges complete for finished item of
work as directed by the Engineer in charge.
Unit-1 Cum
222 Cost of Flyash lime soild blocks . 6000.00 1000 Nos 1332.00
0.10 Cost of Cement Mortar (1:6) 2544.34 1 Cum 254.43
1.00 Labour charges including MA & LALI 1039.73 1 Cum 1039.73
Total 2626.16
1.00 Scaffolding charges (P 61,969) 40.00 1 Cum 40.00
Total 2666.16
Sundries 0.04
47 Fabrication and placing of Tor steel/Fe 415 grade steel reinforcement confirming to IS-226 and 1786-1985
of SAIL/ VSP/ TISCON or any approved TMT of different diameters straightening, cutting & bending to
required sizes & shapes placing in position with cover blocks of approved material & size tieing firmly with
MS binding wire 18 guage forming grills for reinforcement work as per approved design & drawings to be
supplied at the time of executing the work including cost & conveyance of steel and all materials and all
wastages such as overlaps, couplings, welded joints, chairs,space bars, binding wire, cover blocks and all
operational, incidential, labour charges such as cutting, bending, placing in position, tieing etc., complete for
finished item of work as directed by Engineer in charge.
Ground floor
Total Rate per 1 MT 44822.00
First floor
1 Rate as above 44822.00 1 M.T 44822.00
1 Lift charges as per SSR 148 250.00 1 M.T 250.00
45072.00
48 Fabrication and placing of Mild steel/ Fe 250 grade steel reinforcement confirming to IS-226 and 1786-
1985 of SAIL/ VSP/ TISCON or any approved TMT of different diameters straightening, cutting & bending to
required sizes & shapes placing in position with cover blocks of approved material & size tieing firmly with
MS binding wire 18 guage forming grills for reinforcement work as per approved design & drawings
supplied at the time of executing of work including cost & conveyance of steel and all materials and all
wastages such as overlaps, couplings,welded joints,chairs,space bars, binding wire, cover blocks and all
operational, incidential, labour charges such as cutting, bending, placing in position, tieing etc., complete for
finished item of work as directed by the Deptt.
Ground floor
Total Rate per 1 MT 58006.00
First floor
1 Rate as above 58006.00 1 M.T 58006.00
1 Lift charges as per SSR 148 250.00 1 M.T 250.00
58256.00
50 Providing impervious coat to exposed RCC roof slab surfaces of water tank inside and toilet bottom
etc. to required slopes with CM (1:4) prop. 12mm thick mixed with water proofing compound manufactured
by reputed manufacturers as approved by Engineer-in-charge at 1 Kg per bag of cement(50 Kgs), laid over
roof slab when it is green, finished smooth with a floating coat of neat cement and thread lining at regular
intervals of 45cmx45cm where ever necessary including cost and conveyance of all materials like cement,
sand, water proofing compound, water etc., to site, including seigniorage charges, sales & other taxes on all
materials and operational, incidental, and labour charges for mixing mortar, laying, lift charges, rendering
smooth and thread lining, curing including rounding off junctions of wall and slab etc., complete for finished
item of work). Unit-1 Sqm
0.15 Cost of Cement Mortar (1:4) prop. 3084.34 1 Cum 462.65
1.00 Labour charges 682.90 1 Cum 682.90
1.44 Accoproof powder (P.20, item No.320) 24.00 1 kg 34.56
0.12 Cost of Cement 205.00 1 Bag 24.60
Rate per 10 Sqm 1204.71
Rate per 1 sqm 120.48
0.02
Rate per 1 sqm 120.50
51 Plastering 12mm thick in 2 coats with a base coat of 8mm thick in CM (1:6) prop and top coat 4mm thick
in CM(1:4)prop with dubara sponge finishing including cost and conveyance of all materials seignorage fee,
all taxes, water to work site and all operational, incidential labour charges such as scaffolding, mixing,
motor, lift charges, curing etc. complete for finished item of work as per SS No. 901, 904 for external walls.
Scaffolding Lift
1st Floor Rate
Lift charges+scaffolding charges 44.00 11.00 1608.03
Rate per 10 Sqm 1608.03
Total Rate per 1 Sqm 160.81
0.09
Rate per 1 Sqm 160.90
52 Plastering 12mm thick in 2 coats with a base coat of 8mm thick in CM (1:6) prop and top coat 4mm thick
in CM(1:4)prop with dubara sponge finishing including cost and conveyance of all materials seignorage fee,
all taxes, water to work site and all operational, incidential labour charges such as scaffolding, mixing,
motor, lift charges, curing etc. complete for finished item of work as per SS No. 901, 904 for internal walls
& Ceiling.
Unit - 1 Sqm
0.1125 Cost of Cement Mortar (1;6) prop 2544.34 1 Cum 286.24
0.0375 Cost of Cement Mortar (1:4) prop 3084.34 1 Cum 115.66
10.00 Labour charges as per chart 1151.13 10 Sqm 1151.13
Total 1553.03
Ground Floor Rate Total Rate per 1 Sqm 155.30
0.00
Rate per 1 Sqm 155.30
53 Plastering 12mm thick in single coat with CM (1:3) prop with dubara sponge finishing including cost and
conveyance of all materials seignorage fee, all taxes, water to work site and all operational, incidential
labour charges such as scaffolding, mixing, motor, lift charges, curing etc. complete for finished item of work
as per SS No. 901, 904.
Unit - 1 Sqm
0.15 Cost of Cement Mortar (1:3) prop 3624.34 1 Cum 543.65
54 Plastering 12mm thick in single coat with CM (1:5) prop with dubara sponge finishing including cost and
conveyance of all materials seignorage fee, all taxes, water to work site and all operational, incidential
labour charges such as scaffolding, mixing, motor, lift charges, curing etc. complete for finished item of work
as per SS No. 901, 904.
Unit - 1 Sqm
0.15 Cost of Cement Mortar (1:5) prop 2760.34 1 Cum 414.05
1.00 Labour charges as per labour chart including 682.90 1 Cum 682.90
MA&LALI
Rate for 10 Sqm 1096.95
Rate for 1 Sqm 109.77
0.03
Rate for 1 Sqm 109.80
55 Supplying and laying of polished shabad stone of tandur blue variety of 15 to 18mm thick of size 0.457x
0.304 M over a base of 20 mm thick in C. M (1:8) with neat cement joints to full depth including cost and
conveyance of all materials and labour charges for laying, cutting seigniorage charges and curing etc
complete for Flooring in Corridors & mid landing.
Lift charges (as per Item No.1024 P.63) 23.00 10 Sqm 3674.92
1st Floor Rate 3674.92
Rate per One Sqm 367.49
0.01
Rate per One Sqm 367.50
56 Flooring with Non skid Ceramic tiles 7.3 mm thick 1st quality of approved shade, design and
pattern of KAZARIA / JHONSON make and size not less than 300mm x 300mm set over a base coat in
C.M (1:6), 12mm thick incluidng applying neat cement slurry honey like consistency spread at the rate of
3.30kg/Sqm and filling the joints with white cement mixed with pigments of matching shade laid over
existing concrete bed/RCC slab including cost of base coat, cost and conveyance of all materials,
excluding CC bed / RCC slab, labour charges for mixing cement mortar, laying of tiles to required
slopes/levels, curing etc., complete for finished item of work for all Floors.
Unit - 10 Sqm
10.10 Cost of Non skid ceramic tiles (Item 60, P.10) 374.00 1 Sqm 3777.40
0.12 Cost of Cement Mortar (1:6) prop 2544.34 1 Sqm 305.32
33.00 Cost of Cement 4100.00 1000 Kg 135.30
10.00 Labour charges as per labour chart inclusive of MA 1684.04 10 Sqm 1684.04
& LALI
57 Flooring with Edge Cut - Rectified Ceramic tiles 8 mm thick 1st quality of approved shade, design
and pattern of KAZARIA / JHONSON make and size not less than 400x400mm set over a base coat in C.M
(1:6), 12mm thick incluidng applying neat cement slurry honey like consistency spread at the rate of
3.30kg/Sqm and filling the joints with white cement mixed with pigments of matching shade laid over
existing concrete bed/RCC slab including cost of base coat, cost and conveyance of all materials,
excluding CC bed / RCC slab, labour charges for mixing cement mortar, laying of tiles to required
slopes/levels, curing etc., complete for finished item of work for all Floors.
Unit - 10 Sqm
10.10 cost of Edge cut rectified ceramic tiles(Item 51) 450.00 1 Sqm 4545.00
0.12 Cost of Cement Mortar (1:6) prop 2544.34 1 Sqm 305.32
33.00 Cost of Cement 4100.00 1000 Kg 135.30
10.00 Labour charges as per labour chart inclusive of MA 1684.04 10 Sqm 1684.04
& LALI
Rate for 10 Sqm 6669.66
Rate for One Sqm 666.97
0.03
Rate for One Sqm 667.00
58 Granolithic concrete Flooring 20 mm thick with Vibrated cement concrete M20 design mix using 12 mm
size (SS5) grade hard granite machine crushed graded metal from approved quary laid Granalothically over
an existing bed of CC 1:5:10 Prop, CC slab laid in alternate panels of size not exceeding 1.50 X 1.50m and
finishing the top surface to required smooth ness and slopes including cost and conveyance of all meterials
and all operational incidental and seinarage charges and mixing concrete, laying, curing etc. complete for
finished item of work.(APSS NO:701and 707 )
Unit-1 Sqm
1 Cost of VRCC M20 design mix 4584.80 1 cum 4584.80
-1 Deduct difference in cost of 20mm graded metal 181.25 1 cum -181.25
and 12mm graded metal
-1 Deduct difference in Labour charges for RCC and 595.29 1 cum -595.29
PCC
Total for 1 Cum 3808.26
59 Providing skirting to internal wall 10cm height with Edge Cut - Rectified Ceramic tiles 8mm thick 1st
quality of approved shade, design and pattern of KAZARIA / JHONSON make length equal to flooring
tiles set over base coat of CM(1:5) 12mm thick with grey cement slurry of honey like consistency spread at
the rate of 3.3 Kgs of cement per Sq.m and jointed with cement to full depth (joints of stone should be
flushed)including cost and conveyance of all materials like cement, sand, water, etc., to site including
seigniorage charges, sales & other taxes on all materials, operational & incidental charges and all labour
charges like dressing to the required size, mixing of mortar, curing and lift charges including cutting the
brick wall to place the stones and redoing the surface smooth, including cost of base coat complete for
finished item of works. (APSS No.701 & 707). for all Floors
Unit - 1 RM
10 Rate of Edge cut Ceramic flooring as above 6669.66 10 Sqm 6669.66
Rate of Skirting for 10 Cm thick( for 100 Mts) 66.70
0.00
Rate per 1 RM 66.70
Unit - 1 RM
10 Rate of Non skid Ceramic flooring as above 5902.06 10 Sqm 5902.06
Rate of Skirting for 10 Cm thick( for 100 Mts) 59.02
0.08
Rate per 1 RM 59.10
61 Providing skirting to internal wall to 10.00 cm height with 15 to 18mm thick polished Shahabad stone
(Tandur blue) 1st quality with length equal to flooring stones set over base coat of CM (1:5) 12mm thick with
grey cement slurry of honey like consistency spread at the rate of 3.3 Kgs of cement per Sq.m and jointed
with cement to full depth (joints of stone should be flushed)including cost and conveyance of all materials
like cement, sand, water, etc., to site including seigniorage charges, sales & other taxes on all materials,
operational & incidental charges and all labour charges like dressing to the required size, mixing of mortar,
curing and lift charges including cutting the brick wall to place the stones and redoing the surface smooth,
including cost of base coat complete
Unit - for
1 RMfinished item of works.
10.10 Cost of polished Shahabad stone 1351.00 10 Sqm 1364.51
0.12 Cement Mortar (1:5) prop 2760.34 1 Cum 331.24
33.00 Cost of Cement 4100.00 1000 Kg 135.30
10 Labour charges as per Labour chart inclusive of MA 1684.04 10 Sqm 1684.04
& LALI
Rate for 10 Sqm 3515.09
Rate per 1 RM 35.16
0.04
Ground Floor Rate 35.20
1st Floor
Lift charges (as per Item No.1024 P.63) 23.00 10 Sqm 3538.09
Rate for 10 Sqm 3538.09
Rate per 1 RM 35.39
0.01
Rate per 1 RM 35.40
62 Supplying and laying of polished shahabad stone of tandur blue variety of 15 to 18mm thick of required
size in a single piece over a base of 20 mm thick in CM (1:5) pointed to full depth including cost and
conveyance of all materials and labour charges for laying, cutting flat nosing to the exposed edges
including seignorage fee and all taxes, labour charges etc. complete for finished item of work for steps
of staircase (Treads & Risers).
Unit-One Sqm
i) Risers of 0.15m height
For 1 mt length
0.15 cost of 15 to 18mm thick polished shabad stone at 2026.50 10 30.40
sq.m.
1.50 times
63 Supply and fixing of 16 to 18 mm thick high polished granite slabs of black colour of first quality (upto
2.43 Mts length) with half round edge and set over 12 mm thick C.M (1:5) base coat in single piece
including neat cement slurry of honey like consistency spread at the rate of 3.30 kg/Sq mt cost of
seigniorage charges, and all other taxes and conveyance of all materials and water to work site, cost of
base coat and all operational and labour charges such as mixing mortar, half rounding the edges including
polishing, dressing, fixing in position, lift charges etc complete for finished item of work for in single piece
kitchen platform.
Unit -One Sqm
10.00 Cost of 18 to 20 mm thick slab(SSR item No.40) 1639.00 1 Sqm 16390.00
0.12 Cost of cement Mortar (1:5) 2760.34 1 Cum 331.24
16.7 Half Rounding the edge including polishing(Item No.46) 115.00 1 RM 1920.50
0.96 Mason 1st class 206.00 1 each 197.76
2.24 Mason 2nd class 188.00 1 each 421.12
2.24 Man Mazdoor 146.00 1 each 327.04
1.10 Woman Mazdoor 146.00 1 each 160.60
10.00 Siegionarage charges (Rs.1500/- per Cum) 25.50 1 Sqm 255.00
0.53 Add for MA & LALI @ 53% 1106.52 1 586.46
Ground Floor rate 20589.72
Rate per 1 Sqm 2058.98
64 Dadooing with colour glazed tiles 300x200 MM, 1st quality (Jhonson/Khazaria make) over a base coat of
12 mm thick in CM (1:5) prop incluidng applying neat cement slurry honey like consistency spread at the
rate of 3.30kg/Sqm and jointed with white cement mixed with pigment of matching shade including cost and
conveaynce of all materials and labour charges etc. complete for finished item of work to walls in toilets
and kitchen as directed by the Department for all Floors.
Unit - 1 Sqm
10.10 cost of tiles (as per item 70, P.10) 332.00 1 Sqm 3353.20
10.00 Cost of Plastering with CM(1:5) 12mm thick 1096.95 10 Sqm 1096.95
33.00 Cost of Cement 4100.00 1000 Kg 135.30
10.00 Labour charges (as per chart) 122.40 1 Sqm 1224.00
Total 5809.45
Rate for 1 Sqm 580.97
0.03
Rate for 1 Sqm 581.00
65 Supplying and application of two coats of ALTEK super fine , one coat of ALTEK water based cement
primer and twocoats of ALTEK flora ( plastic emulsion paint ) to interior faces of new walls and ceiling of
approved colour as per manufacturer's specifications including cost and conveyance of all materials to site
and labour charges such as preparing the wall and surface, applying primary coat,all Taxes, etc. complete
for finished item of work as directed by the department for INTERNAL WALLS AND CEILING (Total 3
coats).for all Floors.
Unit 1 Sqm
1.00 Rate as per SSR item No.421 112.00 1 Sqm 112.00
Rate per One Sqm 112.00
66 Supply and application of one coat of Altek water based cement primer and two coats of Altimate (Acrylic
emulsion paint exterior grade) to exterior faces of new walls as per manufacturer's specifications including
cost and conveyance of all materials to site and labour charges such as preparing the wall, applying primary
coat etc complete for finished item of work for EXTERNAL WALLS (Total 3 coats) for all Floors
Unit 1 Sqm
1.00 Rate as per SSR item No.424 136.00 1 Sqm 136.00
Rate per One Sqm 136.00
67 Painting to new wood work and flush shutters with lappam finish , over a primary coat and painting two
coats of synthetic enamel paint 1st grade of approved brand and shade (Total 3 coats) including cost and
conveyance of all materials to site cost of primer coat and all labour charges etc. complete including
applying sand paper on lappam coats for neat finish including sales & other taxes on cost of all materials
etc. complete (APSS No.1200, 1207 & 1211) in all floors.
Unit 1 Sqm
10.00 Cost Lappam / Putty (SSR Item No.388) 36.00 1 Kg 360.00
1st Primer Coat (S.No.305)
0.60 Cost of Wood Primer (Sl No. 322) 121.00 1 Ltrs 72.60
0.21 1st class Painter 206.00 1 each 43.26
0.49 2nd class Painter 188.00 1 each 92.12
0.53 Add for MA & LALI @ 53% 135.38 1 71.75
2nd Primer Coat
68 Supply & applying Melamine Polish/Glossy /Matt finish to the wood works duly cleaning the surface and
applying emery paper, Sand the wood with 180 No.emery paper and then with 320 No. emery paper, clean
& wipe off loose dust, applying suitable knifing paste filler/wood filler by putty knife/muslin pad, air dry for 2-
3 hrs, sand with 180 and 320 No., emery paper, apply two component wood sealer, air dry for 24 hrs, Sand
with 320 No. emery paper, applying one coat of approved brushing lthinner or general purpose thinner (for
brushing) and apply (either with spray or brush) two coats of approved brand melamine including cost &
labour charges, emery papers, cost of thinner & melamine polish of approved brands such as Jenson &
Nicholson, Asian Paints, Berger Paints or equivalent etc., complete for finished item of work for all Floors.
Unit 1 Sqm
1.00 Rate as per SSR item No.306 356.00 1 Sqm 356.00
Rate per 1 Sqm 356.00
69 Painting two coats with synthetic enamel paint first grade to new iron work including cost and
conveyance of all materials to site, sales & other taxes, incidental, operational and all labour charges etc.,
complete for finished item of work.
Unit 1 Sqm
1.1 Cost of Synthetic Enamel paint 175.00 1 Ltrs 192.50
0.33 1st class Painter 206.00 1 each 67.98
0.77 2nd class Painter 188.00 1 each 144.76
0.53 Add for MA & LALI @ 53% 212.74 1 112.75
Rate per 10 Sqm 517.99
Rate per 1 Sqm 51.80
0.00
Rate per 1 Sqm 51.80
70 Providing water proof cement paint of approved make color and shade to faces of walls in two coats over
primary coat of white cement (total 3 coats) including cost and conveyance of all materials, sales & other
taxes on cost of all materials , water to site, including cost of brushes, scaffolding charges, lift charges etc.
and all labour charges curing etc., complete for finished item of work in all floors. (APSS No. 912)
71 Providing RCM railing 50mm thick in CM(1:3) using rabit wire mesh required guage and nominal
reinforcement with dubara spone finishing , including cost and conveyance of materials and water to work
site seigniorage fee and all operational, incidential labour charges such as scaffolding, centering from
work,steel centering, mixing mortar, lift charges curing etc. complete for finished item of work but excluding
cost of reinforcement steel and its fabrication charges for stair case and balcony railings.
72 Providing MS hand railing as per drawings using 40mm hollow MS tube at top, 20mm MS square bars at
600mm c/c for verticals and 20mm x 6mm MS flat in two rows in middle including cutting bars, welding,
fixing in position, applying one coat of red oxide including cost & conveyance of all materials to site labour
charges etc complete for finished item of work in all floors (0.90mts height).
Cost Analysis
6.50 Cost of 40mm MS Tube 50000.00 1000 Kg 324.90
11.30 Cost of 20mm MS Square bars 44800.00 1000 Kg 506.42
3.60 Cost of 20 x 6 mm MS Flats 44800.00 1000 Kg 161.28
21.40 Labour charges 12.00 1 Kg 256.82
0.53 Add for MA & LALI @ 53% 256.82 1 Kg 136.11
Rate per 1.80 mts length and 0.90 mts height 1385.53
Rate per 1 Sqm 855.27
0.03
Rate per 1 Sqm 855.30
73 Supplying and fixing of four shutter cupboards as per drawing with 2nd class teak wood frames of size
75mm x 32mm and 18mm thick prelaminated particle board (BSL) interior grade for shutters with 18mm x
12mm teak wood beading alround duly providing 4 Nos. piano hinges (for full length of cup board) and
aluminium tower bolts 4 Nos. of 75mm x 10mm, 4 Nos aluminium handles of 75mm long and standard
locking arrangements for shutters including cost and conveyance of all materials to site, labour charges
etc., complete for finished item of work.for all Floors
Unit 1 Sqm
For Cup board of size 1.20m x 1.80m
0.0173 Second class teak wood frame 75194.00 1 Cum 1300.86
4 Piano hinges 70.00 1 Each 280.00
18mm thk. prelaminated particle board(SSR 1395.36
2.16 No.513) 646.00 1 Sqm
8.4 Teak wood beading 18mm x 12mm 15.00 1 RM 126.00
4 AluminiumTower bolts 75mm 47.00 1 Each 188.00
4 Al. Handles 75mm 45.00 1 Each 180.00
2 Cupboard locks 50.00 1 Each 100.00
2.16 Labour charges (SSR No.961) 383.00 1 Sqm 827.28
0.53 Add for MA & LALI @ 53% 827.28 1 438.46
Add LS for Screws, Nails etc. 10.50
Total 4846.46
2243.73
0.07
Rate per 1 Sqm 2243.80
74 Supply and fixing of MS Grill door of size 2.10mts x 1.00mts using frame with 40mm x 40mm x 5mm
alround and shutters 2nos using 25 mm x 25 mm x5mm MS angle welded with 10 mm MS square bars at
100 mm c/c duly welding MS poswder coated aldrop of size 300 mm x 16 mm dia as per drawing including
cutting bars and angles, welding, fixing in position with 6 nos of MS Z hold fasts of size 300mm x 40mm x
5mm, 6 nos of 150 mm MS powder coated hinges and 2 nos 200mm x 12 mm MS powder coated tower
bolts including primer coat using 1st quality u redoxide, cost and conveyance of all materials to site,
labour cahrges etc., complete for finished item of work in all floors.
75 Supply and fixing of partitions made of seccolor pre-painted steel (base steel as per IS 513 of 0.6mm thick
‘D’ quality, galvanized as per IS 277 with Zinc of 120 GSM). Primer coated with epoxy primer of 5-7
microns thick, finish painted with a polyester paint of 12-16 microns thick alkyd backer. Section for outer
frame should be 46x52mm, section for shutter should be 46x46mm, section for mullion should be
46x70mm, section for beading should be 18x25mm and section for middle and bottom rail (Lock Rail and
Kick Rail) of size should be 23x130mm. The partition should be paneled with 9mm pre-laminated particle
board to a height of 0.91m from the bottom, and remaining height with 5mm thick plain glass. with Ethyl
Propylene Diamine Monomer (EPDM) Gaskets. The sections are to be cut to length, mitre joined with
corner bracket Centre mullions are to be fixed using mullion cap. Gaskets made of Ethyl Propylene
The above
Diamine frames (EPDM).
Monomer should beCorner
fixed to the concrete/masonry
brackets made of CRCAwall withby means
zinc of self expanding
phosphating. screws,
Mullion caps madeandof
complete for finished
Glass filled nylon. item of work. Fixed Partition: Outer frame section size of 46x52mm, mullion section
should be of 46x70mm, fixed beading should be of 18x25mm. for fixed partition with Door.
Unit Each
Rate as per SSR No.819
4.88 For 8'-0" x 6'-6" 3901.00 1.00 Sqm 19036.88
0.02
Rate for Each of 8' x 6.6' size partition 19036.90
3901.0041
76 Supply and fixing of doors as per approved drawings with 2nd class teak wood frame of section 100mm x
65 mm and ISI marked flush door shutter of 35mm thick single shutter with bond wood solid block board
type Core having cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde
synthetic resin factory made conforming to IS 2202-1991 (Part-I) with teak veneer on one face and
commercial ply on another face (lipping) including cost and conveyance to site of teak wood frame,
marked fixtures
flush shutter of 3Nos
including Brass
supply butt hinges
and fixing 150mm
6 Nos.MS Z holdlong,
fasts 1No.
of sizeAluminium aldrop 300mm
300mmx40mmx5mm long,cost
including 1No.
of
Aluminium
ISI tower bolt of 300 mm long at top, 1No. 150mm long Brass handle, 1No. Brass door stopper and
1No rubber bush including cost of second class teak wood frame, making, finishing and fixing the fixtures to
door with required number of screws, bolt and nuts including all labour charges for fixing the frame in
position, fixing the shutter to the frame etc., complete for finished item of work as per APSS 1001 & 1002
(The vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm) of size 1.05 x
2.00 mts (3’-6” x 6’-6”)
77 Supply fixing Mild steel hollow door frame of section 105 x 60mm with 30mm rebate manufactured by
cold rolled forming process using cold rolled steel coil of 1.25mm thick with bright CRCA strips of "D" quality
M.S. grade confirming to IS 4351-1976 suitable for fixing of 30mm thick single leaf Flush door shutter
confirming to IS 2201, solid bond wood block board type with both sides commercial ply including six (6)
Nos. standard lugs made from flat strip not less than 1.60 mm thick including base tie of section
50mmx25mm, 4Nos. prefixed hinges of size 100mm x 65mm x 2mm, fixed to frame for fixing shutter, 3 Nos.
rubber buttons insertion in the frame, necessary arrangements for aldrop and tower bolt eyes including
painting to frame with Zink chromate red oxide paint, including fixing 1 No. of 250 mm long Aluminium
Aldrop, 2 Nos of 200 mm long Aluminium tower bolts, 1 No. of Al. heavy duty door stopper, 2 Nos. of 150
mm long Aluminium door handles including necessary screws etc., and filling the M.S Door frame with C.C
(1:3:6) prop. but
etc., complete forexcluding cost of
finished item of Cement
work as Concrete (1:3:6),
directed by including
Engineer cost all
in charge fortaxes
Door and all labour
of size 0.90mtcharges
x 2.00mt
( 3 'x 6’-6” ).
Unit-each
4.88 Cost of cold rolled formed door frame 3-0"x6-6" 233.00 1 RM 1137.04
=16.00 or 4.876 RM @ the rate of Rs.233 R.M
(Sl.No.652) with Hinges and tower bolts etc.,
1.564 Cost of Flush door shutter of 30 mm thick wood 626.00 1 Sqm 979.06
black Board commercial ply on both faces. (657)
1.811 Labour charges for wrought and put up including 288.00 1 Sqm 521.57
fxinig in position the frame and shutter (962)
2 250 mm long, 16 MM dia Al.aldrop each (195) 238.00 1 each 476.00
2 Al. Door handle 150 mm long (item No.184) 85.00 1 each 170.00
1 200mm long Al. tower bolts each (Sl.No.161) 86.00 1 each 86.00
1 Door stopper Heavy duty(item No.209) 34.00 1 each 34.00
0.53 Add for MA & LALI @ 53% 521.57 1 276.43
Total 3680.10
sundries 0.00
Cost of Each Door 3680.10
2 Al. Door handle 150 mm long (item No.184) 85.00 1 each 170.00
2 200mm long Al. tower bolts each (Sl.No.161) 86.00 1 each 172.00
0.53 Add for MA & LALI @ 53% 434.88 1 230.49
Total 3140.15
Sundries 0.05
Total Rate per each 3140.20
79 NCL or Equivalent ECO 4000 SERIES WINDOWS (SUITABLE FOR RESIDENTIAL BUILDINGS WITH
GRILL & FLYMESH PROVISION)
Providing & Fixing of windows made of pre-painted steel (Base Steel as per IS 513 of 0.6mm thick
galvanized as per IS 277 with zinc of 150 GSM). Primer coated with epoxy primer of 5-7 microns thick,
finish painted with a polyester paint of 12-16 microns thick and back coated with 5-7 microns thick alkyd
backer. Section for outer frame should be of 72x55mm, centre mullion should be of 72x50mm, Section for
fixed glass beading section should be of 12x12mm and section for shutters should be of 47x20mm. Outer
frame & mullion sections to have rebate for glazed shutters, fly mesh and a 20mm provision for guard
bars/grills. Fly mesh shutter section should be of 20x40mm. The sections are to be cut to length meter
joined with corner bracket. Centre mullions are to be fixed with mullion cap, seccolor stay, seccolor
The above
handles, frameslatch
seccolor should beoffixed
2 Nos to duty
heavy the stainless
concrete/masonry
steel pivotwall by means
hinges shall beofprovided
self expanding screws.
per Shutter. The
Including 10mm Square guard bars with 6” (152.4mm) pitch , complete for finished item of work.
windows should be paneled with 5mm thick plain float glass and S.S. Mesh for fly mesh shutter(304 grade).
Rubber Gaskets are provided all around the glass.
Unit-1 Sqm
a Single shutter Window 2’0”x4’0” (609.6mm x
1219.2mm). Outer frame section size of 72x50mm
shutter frame section size of 47x20mm
1.0 Window (750x1200) SL NO 801 5434.00 1.00 Sqm 5434.00
0.00
Rate for 1 Sqm 5434.00
Unit - 1 Sqm
Fixed louvers 2'-0" x 2'-0" (609.6x609.6mm)(Box
section) outer frame section size of 33 x 57 mm
1.0 Ventilators of size 600x600 mm, 1200x600 mm 3334.00 1.00 Sqm 3334.00
and 1200x1000 mm SL NO. 793 to 795
Rate for 1 Sqm 3334.00
81 Flush Pointing to R.R Masonry with CM (1:3) including cost and conveyance of all materials to site,
seigniorage charges, curing, all labour charges etc. complete as per standard specifications and as directed
by the Engineer in charge for finished item of work.
82 Flush Pointing to Brick Masonry in CM (1:3) including cost and conveyance of all materials to site,
seigniorage charges, curing, all labour charges etc. complete as per standard specifications and as directed
by the Engineer in charge for finished item of work.
0.006 Cement Mortar (1:3) 3624.34 1 Cum 21.75
1.00 Labour charges as per Labour charges 987.22 10 Sqm 98.72
Rate per 1 Sqm 120.47
Sundries 0.03
Rate per 1 Sqm 120.50
83 Raised pointing with CM(1:4) prop. including cost and conveyance of all materials, seigniorage charges,
curing, all labour charges etc., complete as per standard specifications and as directed by the Engineer in
charge for finished item of work.
Unit 1 Sqm
0.009 Rate of cement mortar (1:4) 3084.34 1 Cum 27.76
1.00 Labour charges as per Labour charges 1156.34 10 Sqm 115.63
Rate per 1 Sqm 143.39
Sundries 0.01
Rate per 1 Sqm 143.40
84 Providing Expansion joint treatment with poly sulphide compound of approved make of finished size 25
x 12mm including making of 25mm x 12mm groove and primer coat over finished groove with finishing of
edges true to straight line and level over the finished surface of expansion joint including cost and
conveyance of all materials to site, all incidental, operational, labour charges etc. complete for finished item
of work as per approved drawing (for all floors on top of slab i.e in the flooring and for internal vertical joints
of grooves in dadooing surface)
Unit - One RM
1.00 As per market rate 370.00 1 RM 370.00
85 Providing and fixing of 25.4 mm thick bituminous mastic pad of approved make inside the Expansion
joint including cost, all taxes and conveyance of all materials to site, cutting in to required size, placing in
position with necessary arrangements as directed by Engineer in charge, all incidental, operational, labour
charges etc., complete for finished item of work as per approved drawing for all floors.
86 Providing and fixing of 24 gauge alluminium sheet over expansion joint groove of width 15cm fixed to
walls / columns at one edge and resting over the other block walls/columns concealing expansion joint with
slotted holes for free edge of aluminium sheet to facilitate free movement of aluminium sheet over the
finished surface of expansion joint and wall face using sheet metal screws with nylon receiver complete
including cost, all taxes and conveyance of all materials to site, cutting to required size as directed by
Engineer in charge, all incidental, operational, labour charges etc., complete for finished item of work as per
approved drawing for all floors for vertical joints and bottom of slab.
Unit - One Rm
0.15 Cost of aluminium sheet (226) 262.00 1 Sqm 39.30
1.00 Add for labour charges including cost of nails, 5.00 1 RM 5.00
making holes to wall and in aluminium sheet etc.
Total 44.30
0.00
Rate per RM 44.30
87 Supplying and fixing 110 mm(4") dia. PVC /SWR pipes & fittings of make SUDHAKAR / NANDI / PRINCE
or equivalent down take water spout pipe of 4 kg/sq.cm pressure with air tight joints duly fixing with PVC
clamps at every 1mt length and using plain bend at down end to keep the down water away from the walls
with all materials required and necessary nails and screws and bell mouth finishing at inlet including shoe
and bend and making all arrangements etc, complete for Rain water down take pipe as directed by the
Engineer in charge.
88 Masonry with CM (1:6) prop: (cement : sand) with Flyash cement/ lime solid blocks with compressive
strength of 50 Kg/Sq.cm - IS:12894-1990 - CLASS - 5 of size 290 x150 x 140 mm including cost and
conveyance of all materials like cement, sand, Flyash solid blocks, water etc., to site, including seigniorage
charges, sales & other taxes on all materials and such as labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges, curing, etc., complete for finished item of work for
Compound walls (APSS No. 501 & 504).
Unit-One Cum
148 Cost of Flyash lime soild blocks 7.00 1 Nos 1036.00
0.10 Cost of Cement Mortar (1:6) 2544.34 1 Cum 254.43
1.00 Labour charages including MA & LALI 1039.73 1 Cum 1039.73
2330.16
89 Plain Cement Concrete M 20 grade Design Mix (by weigh batching) to the required strength as per SS
and IS-456:2000 using stone aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine
crushed metal from approved quarry using a minimum quantity of 300 kgs of cement per cum of concrete
mechanically mixed, and placing concrete as directed by the Engineer in charge including cost and
conveyance of all materials and water to work site, seigniorage fee, all taxes and all operational, incidental,
labour charges such as centering form work (steel centering) mixing concrete, laying, lift charges, vibrating,
Unit item
curing etc., complete for finished - Oneof Cum
work as per standard specification and as directed by the Engineer
in charge Cost
0.92 for of 20mm
Coping (APSSHBG SS5 graded metal
402). 1338.69 1 Cum 1231.59
0.30 Cost of cement 4500.00 1 MT 1350.00
0.46 Cost of sand 1421.50 1 Cum 653.89
1.00 Labour Charges as per labour chart inclusive of 774.00 1 Cum 774.00
MA&LALI
1.00 Mixing charges as per design mix(item 1009, P62) 100.00 1 Cum 100.00
Basic Rate 4109.48
Sundries 0.08
Total Rate per 1 CUM 4109.56
Bitumen 16/06/2008
12 Bitumen - 80/100 grade Visakhapatnam 525 30867.77 1575 32442.77
13 Bitumen - 60/70 grade - Do - 525 32167.44 1575 33742.44
14 Bitumen - Emulsion - Do - 525 24539.84 1575 26114.84
II 9.5mm to 4.75mm
(Av. rate of 9.5-11.2mm , 5-7mm & 2.36 - 5mm HBG M/C metal)
1 Rate of 9.5 mm to 11.2 mm HBG metal as per Lead chart 1092.43
2 Rate of 5 mm to 7 mm as per Lead chart 929.93
3 Rate of 2.36 mm to 5 mm as per Lead chart 684.93
2707.28
Average Rate of 9.5 mm to 4.75 mm 902.43
IV 25 mm to 10mm
(Average rate of 25-27mm, 19-22mm, 12-14mm & 9.5-11.2mm HBG M/C metal)
1 Rate of 25 mm to 27mm HBG metal as per Lead chart 1429.93
2 Rate of 19 mm to 22 mm HBG metal as per Lead chart 1448.68
3 Rate of 12 mm to 14 mm HBG metal as per Lead chart 1254.93
4 Rate of 9.5 mm to 11.2 mm HBG metal as per Lead chart 1092.43
5225.95
Average Rate of 25 mm to 10 mm 1306.49
V 45mm to 22.40mm
(Av. Of 40-45 mm, 25-27 mm & 19-22mm HBG M/C metal)
1 Rate of 40mm to 45mm HBG metal as per Lead chart 1017.43
2 Rate of 25 mm to 27mm HBG metal as per Lead chart 1429.93
3 Rate of 19 mm to 22 mm HBG metal as per Lead chart 1448.68
3896.03
Average Rate of 45 mm to 22.40 mm 1298.68
VI 10mm to 5mm
Av. of 9.5-11.2mm, 5 to 7mm
1 Rate of 9.5mm to 11.2mm HBG metal as per Lead chart 1092.43
2 Rate of 5mm to 7mm HBG metal as per Lead chart 929.93
2022.35
Khammam
44
SSR 2008-09
APRSCL
Khammam
45
SSR 2008-09
APRSCL
0
ROADS DATA
S.No Qty Particulars Rate unit Amount
1 Earth Work Excavation and depositing on bank with an initial lead of 10mts and lift of 2 mts in loamy and
clayey soils like black cotton soils, red earth and ordinary gravel including breaking clods,
ramming,sectioning, levelling the surface to correct formation etc., complete as directed by the Dept.
Unit 1Cum
1.00 Rate of earth work as per SSR (P.240) - SS - 37.50 1 Cum 37.50
20 B
0.53 Add for MA & LALI @ 53% 37.50 1 19.88
57.38
Sundries 0.02
Rate per 1 Cum 57.40
2 Earth Work Excavation and depositing on bank with an initial lead of 10mts and lift of 2 mts in hard
gravelly soils including breaking clods, ramming,sectioning, levelling the surface to correct formation
etc., complete as per standard specifications and as directed by Engineer in charge for foundations
Unit 1Cum
1.00 Rate of earth work as per SSR(P.243)-S.S20A 43.00 1 Cum 43.00
3 Earth work excavation for levelling using machinery in all soils upto soft disintegrated rock and stone
matrix and dumped within a radius of 5 mts. including all incidental charges, hire, charges of machinary
and vehicles etc., complete for finished item of work.
Unit 1 cum
Rate as per GO MS No.10 of Finance (Works &
1.00 Projects) Dept. dt.26.07.2005 13.00 1 cu.m. 13.00
Rate per 1 Cum 13.00
4 Filling with available excavated earth in low level area with an average lead of 500m and watering and
consolidation to Proctor Density with 8 to 10 T power roller including watering and conveyance of water
with an initial lead of 1/2 KM including all labour charges,power roller hire charges etc. complete for
finished item of work
Unit 1 cum
1.00 Conveyance charges 75.00 1 Cum 75.00
-1.00 Deduct stacking 5.50 1 Cum -5.50
1.00 Labour charges for sectionig 3.50 1 Cum 3.50
0.53 Add for MA & LALI @ 53% 3.50 1 Cum 1.86
0.53 Add for MA & LALI @ 53% 18.50 1 Cum 9.81
(Loading + Unloading)
1.00 Add consolidation to proctar density with power 28.00 1 Cum 28.00
roller, watering, charges(SSR-279c-p26)
112.67
Sundries 0.03
Rate per 1 Cum 112.70
5 Excavation in rock by way of benching, chiseling, wedging and boring in rock in foundations, grade
levelling including all lead and lift charges and disposal of rock from the site as directed by the
department (Rs.180/- per cum will be recovered to the extent of entire stone quantity excavated.Site
should be cleared by the contractors at his own cost by disposing the excavated rock soon after
excavation is done as directed by the department.)
Model-Munaganoor-data-29-08-08)
Page 46 (Cellar+Stilt) M30 & other floors with M25
APRSCL
6 Earth work excavation in hard gravelly soils using machinery and Forming Embankment including
carting with 1KM lead, watering and consolidation to proctor density with 8 to 10 tones capacity power
road roller including Seigniorage charges, watering, conveyance of water with initial lead of 1/2 KM
complete as directed by the Engineer in charge.
Unit 1 cum
1.00 Rate of earth work as per SSR(243)S.S-20 A 13.00 1 Cum 13.00
1.00 Carting of earth with a lead of 1 KM 100.00 1 Cum 100.00
1.00 For Extra watering and consolidation to 28.00 1 Cum 28.00
Proctors density with power roller of capacity of
8 to 10 Tonnes including watering, including
conveyance of water for a lead of 1/2 KM (Rate
as per SSR No.279, P-26)
-1.00 Deduct for loading, unloading and stacking 24.00 1 Cum -24.00
charges
1.00 Seigonarage charge 20.00 1 Cum 20.00
Total 137.00
Sundries 0.00
Rate per 1 Cum 137.00
7 Earth work excavation in hard gravelly soils using machinery and Forming Embankment including
carting with 3KM lead, watering and consolidation to proctor density with 8 to 10 tones capacity power
road roller including Seigniorage charges, watering, conveyance of water with initial lead of 1/2 KM
complete as directed by the Engineer in charge.
Unit 1Cum
1.00 Rate of earth work as per SSR(243)S.S-20 A 13.00 1 Cum 13.00
1.00 Carting of earth with a lead of 3 KM 112.00 1 Cum 112.00
1.00 For Extra watering and consolidation to 28.00 1 Cum 28.00
Proctors density with power roller of capacity of
8 to 10 Tonnes including watering, including
conveyance of water for a lead of 1/2 KM (Rate
as per SSR No.279, P-26)
-1.00 Deduct for loading, unloading and stacking 24.00 1 Cum -24.00
charges
1.00 Seigonarage charge 20.00 1 Cum 20.00
Total 149.00
Sundries 0.00
Rate per 1 Cum 149.00
8 Dry Rolling the Embankment with 8 T to 10 T power road roller, including cost and conveyance of all
materials labour and hire charges for power road roller etc., complete for finished item of work.
Unit 1 Sqm
1.00 Dry Rolling embankment with Power Roller 7.00 10 Sqm 0.70
Rate per 1 Sqm 0.70
9 Supplying and spreading of Stone dust including watering and consolidation, conveyance of water for
initial lead of 5 km complete as directed by the Engineer in charge.
Unit 1 Cum
1.00 Stone Dust 558.30 1 Cum 558.30
1 Spreading charges (SSR item No.349, P.31) 230.00 10 Cum 23.00
Model-Munaganoor-data-29-08-08)
Page 47 (Cellar+Stilt) M30 & other floors with M25
APRSCL
581.30
Sundries 0.00
Rate per 1 Cum 581.30
10 Supplying and spreading of sand including watering and consolidation, conveyance of water for initial
lead of 5 km complete as directed by the Engineer in charge.
Unit 1 Cum
1.00 Sand 1306.50 1 Cum 1306.50
1 Spreading charges (SSR item No.349, P.31) 230.00 10 Cum 23.00
1329.50
Sundries 0.00
Rate per 1 Cum 1329.50
11 Collection and supply of good gravel for blindge including cost and conveyance of all materials and
labour charges, stacking at roadside to departmental gauge for pre-measurement including all leads and
lifts and transportation charges,seignorage charges etc., complete as directed by the department.
Unit 1Cum
1.00 Rate of good gravel as per lead chart 338.60 1 Cum 338.6
Sundries 0.00
Rate per 1 Cum 338.60
12 Plain cement concrete work of mix (1:4:8) prop. using 40mm guage hard granite machine crushed metal
including cost of machine mixing, laying, levelling, tamping, curing and conveyance of all materials and all
operational, incidental and labour charges,seignorage charges etc. complete for levelling course for
masonry walls as directed by the Deptt.
Unit 1 Cum
0.92 Rate of 40 mm HBG Metal ( as per lead chart) 1017.43 1 Cum 936.03
Total 3154.12
Sundries 0.08
Rate per 1 Cum 3154.20
13 Random rubble stone masonry in C.M(1:8) prop. using hard granite stones inlcudng cost and
converyane of all materials and labour charges, seigniorage charges, curing, etc complete for Electrical
& common pull pit & storm water grating chamber.
Unit 1 Cum
1.10 Cost of R.R. Stone 546.60 1 Cum 601.26
0.34 cost of cement mortar (1:8) 2274.34 1 Cum 773.28
1 Labour charges as per labour chart including 1158.09 1 Cum 1158.09
MA & LALI
2532.63
Sundries 0.07
Rate per 1 Cum 2532.70
14 Coursed rubble stone masonry in C.M(1:6) prop. using hard granite stones inlcudng cost and
converyane of all materials and labour charges, seigniorage charges, curing, etc complete for Road
median.
Unit 1 Cum
0.60 Cost of CR stone 611.60 1 Cum 366.96
0.50 Cost of RR stone 546.60 1 Cum 273.30
Model-Munaganoor-data-29-08-08)
Page 48 (Cellar+Stilt) M30 & other floors with M25
APRSCL
Model-Munaganoor-data-29-08-08)
Page 49 (Cellar+Stilt) M30 & other floors with M25
APRSCL
Labour charges
0.75 Mason 1st class 206.00 1 each 154.50
1.75 Mason 2nd class 188.00 1 each 329.00
1.40 Man mazdoor 146.00 1 each 204.40
1.40 woman Mazdoor 146.00 1 each 204.40
0.53 Add for MA & LALI @ 53% 892.30 1 472.92
2819.67
Sundries 0.03
Rate per 1 Cum 2819.70
15 Plastering 12mm thick in single coat in CM (1:4) prop with neat finishing including cost and conveyance
of all materials seignorage and water to work site and all operational ,incidential labour charges such as
mixing, mortar, lift charges, curing etc., complete for finished item of work as per SS No.901, 904.
Unit 1 Sqm
0.15 Cost of Cement Mortar (1:4) prop 3084.34 1 Cum 462.65
10.00 Labour charges 682.90 10 Sqm 682.90
Rate per 10 Sqm 1145.55
Rate per 1 sqm 114.56
Sundries 0.05
Rate per 1 Sqm 114.60
16 Raised pointing with CM(1:4) prop. including cost and conveyance of all materials, seigniorage
charges, curing, all labour charges etc., complete as per standard specifications and as directed by the
Engineer in charge for finished item of work.
Unit 1 Sqm
0.009 Rate of cement mortar (1:4) 3084.34 1 Cum 27.76
1.00 Labour charges as per Labour charges 1156.34 10 Sqm 115.63
Rate per 1 Sqm 143.39
Sundries 0.01
Rate per 1 Sqm 143.40
17 Plain cement concrete of M20 grade (Design Mix as per SS) 40 mm thick using 20 mm ss-5 Hard
graded guage hard granite machine crushed metal including machine mixing, laying, vibrating, curing,
finishing including cost and conveyance of all materials, labour charges, seignorage charges etc.,
complete over top of median wall.
Unit 1 Cum
1.00 Cost of M20 design mix concrete 4584.77 1 Cum 4584.77
1.00 centering charges (I No.978, P.61) 715.00 1 Cum 715.00
1.00 Vibrating charges (p.28, Item..291) 43.00 1 Cum 43.00
Total 5342.77
Sundries 0.03
Rate per 1 Cum 5342.80
18 Providing bed below CC pavement with PCC (1:4:8) prop using 40 mm guage HG mchine crushed
metal including cost of machine mixing, laying, leveling, temping and curing etc., including cost and
conveyance of all materials, labour charges, segniorage charges etc., complete for finished item of work.
Unit 1 Cum
0.92 Rate of 40mm HBG Metal (as per lead chart) 1017.43 1 Cum 936.03
0.46 Cost of C.M (1:4) 3084.34 1 Cum 1418.80
1.00 Labour charges as per labour chart 774.00 1 Cum 774.00
1.00 Machine mixing charges (item 292, P28 of 45.00 1 Cum 45.00
common SSR)
-0.46 (-) deduct mortar mixing charges p20 28.00 1 Cum -12.88
-0.46 (-)deduct allowance on mortar mixing charges 14.84 1 Cum -6.83
Total 3154.12
Model-Munaganoor-data-29-08-08)
Page 50 (Cellar+Stilt) M30 & other floors with M25
APRSCL
Sundries 0.08
Rate per 1 Cum 3154.20
19 Rough stone dry packing for approns & revetments with hard granite stone of 225mm size & above
having individual weight not less than 40kg. of approved quality from approved quarry including cost,
conveyance & taxes of all materials, seigniorage charges, all initial leads and lifts, cost of all labour
including filling the interstics with small stones by wedging & hammering & finishing to proper slope
including dewatering if required with T&P articles required for the work etc. complete as per standard
specification and as directed by the Engineer-in-Charge.
Unit 1 Cum
1.10 Rough Stone 225mm thick for Dry packing 441.60 1 Cum 485.76
(HBG) (96)
0.12 Ist class Mason 206.00 1 Each 24.72
0.28 Iind class Mason 188.00 1 Each 52.64
1.10 Men Mazdoor 146.00 1 Each 160.60
0.7 Women Mazdoor 146.00 1 Each 102.20
0.53 Add for MA & LALI @ 53% 340.16 1 180.28
1006.20
Sundries 0.00
Rate per 1 Cum 1006.20
20 Providing Gravel backing to revetments 150mm thick with good laterite moorum of approved quality from
approved quarry including cost and conveyance of gravel, and taxes of all materials, labour, T&P required
labour charges etc., complete for finished item of work as per standard specifications and as directed by
the Engineer in charge.
Unit 1 Cum
1.16 Gravel 338.60 1 Cum 392.78
0.70 Men Mazdoor 146.00 1 Each 102.20
0.4 Women Mazdoor 146.00 1 Each 58.40
0.53 Add for MA & LALI @ 53% 160.60 1 85.12
Total 638.50
Sundries 0.00
Rate per 1 Cum 638.50
21 Compacted granular bedding under pipe with gravel including cost of gravel, labour charges etc.,
complete for finished item of work.
Unit 1 Cum
1.20 Gravel 338.60 1 Cum 406.32
1.20 Rate as per SSR 286 14.00 1 Cum 16.80
0.53 Add for MA & LALI @ 53% 16.80 1 8.90
432.02
Sundries 0.08
Rate per 1 Cum 432.10
22 Providing KERBING to the roads with 1.0 x 0.2 x 0.2 mm size with M20 PCC including earthwork
excavation and jointing in CM(1:4) prop.true to line and joints flushed to the one another including curing
cost & conveyance of all material and labour charges etc., complete
Unit 1 Cum
Unit -1 RM Page 207 of Morth & H SDB
Taking output: 300.00 RM
A)Labour
0.72 Mate 188.00 1 Each 135.36
2.00 Mason 206.00 1 Each 412.00
16.00 Mazdoor 146.00 1 Each 2336.00
0.53 Add for MA & LALI @ 53% 2883.36 1 1528.18
4411.54
b) Machinary
Model-Munaganoor-data-29-08-08)
Page 51 (Cellar+Stilt) M30 & other floors with M25
APRSCL
Model-Munaganoor-data-29-08-08)
Page 52 (Cellar+Stilt) M30 & other floors with M25
APRSCL
c) Material
11.04 Crushed stone aggregate 20mm Graded size 1338.69 1 Cum 14779.14
60%
5.52 Coarse sand 30% 1306.50 1 Cum 7211.88
3.60 Cement 10% 4500.00 1 MT 16200.00
180.00 pointing in CM(1:4) 120.50 1 KL 21690.00
Sub Total 59881.02
A 4411.54
B 5640.00
C 59881.02
69932.56
Total for 1 RM = A+B+C /300 233.11
Sundries -0.01
Rate per 1 Rm 233.10
23 VRCC M25 grade Design Mix to the required strength as per SS and IS-456:2000 using coarse
aggregate of size 20 mm ss-5 gauge graded hard granite machine crushed metal mechanically mixed,
and Fine aggregate of zone-ii andplacing necessary reinforcement in position including cost and
conveyance of all materials and water to work site, seigniorage fee, all taxes and all operational,
incidental, labour charges such as centering from work (steel centering) mixing concrete, laying, lift
charges, vibrating, curing etc., complete for finished item of work as per standard specification but
excluding cost of steel and its fabrication charges etc., complete for finished item of work as directed by
the department for Culvert Slab.
Unit 1 Cum
200mm Thick
1.00 Rate of M25 design mix concrete 4584.77 1 Cum 4584.77
1.00 Centering charges (item 298 P.28) 950.00 1 Cum 950.00
1.00 Vibrating Charges (P 28 Item 291) 43.00 1 Cum 43.00
Total 5577.77
Sundries 0.03
Rate per 1Cum 5577.80
24 Providing and laying factory made hydraulically pressed mechanically vibrated and compacted
pre-cast Cement Concrete interlocking Regular Pavers of 60 mm thickness of M- 40 Grade of which
top 12 mm thick shall be of colour pigmentation with imported colours and white cement to get required
reflective glazing of approved design and colour in single layer approved pattern laid in position in
pavement/ foot path/ pathways etc., set over stone dust bed of 75mm thick, filling the joints with sand,
compacting the blocks with vibrator etc., complete including cost, all taxes and conveyance of all
materials and water to work site and all operational, incidental, labour charges, lift charges, curing etc.,
complete for finished item of work.
Unit 1 Sqm
1.00 Cost of Cement Concrete interlocking Regular 291.00 1 Sqm 291.00
Pavers of 60 mm thickness (SSR Item No.257)
25 Supply & fixing RCC cover 22" dia with nominal reinforcement 3 " thick and hooks for lifting
Unit 1 No
1.00 Rate as per SSR item 701 585.00 1 No 585.00
Rate per 1Sqm 585.00
Model-Munaganoor-data-29-08-08)
Page 53 (Cellar+Stilt) M30 & other floors with M25
APRSCL
26 Providing Plain Cement Concrete in (1:3:6) propotion (cement; fine aggregate: coarse agrgregate)
using 20mm size (SS5) crusher broken hard granite graded stone aggregate of approved quality from
approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate,
water etc., to site including cost, all taxes and seigniorage charges on all materials, centering and
shuttering with proper packing, machine mixing, laying concrete, vibrating, shuttering, finishing to proper
slope and level including curing etc., including hire and running charges of machinery required for the
work with all labour T&P complete as per the specification and as directed by the Engineer-in-Charge for
Body walls.
Unit 1 Cum
0.92 Cost of 20mm HBG SS5 graded metal 1338.69 1 Cum 1231.59
0.46 Cost of sand 1421.50 1 Cum 653.89
0.15 Cost of cement 6480.00 1 Cum 972.00
1.00 Labour charges 774.00 1 Cum 774.00
1.00 Centering charges (I No.978, P.61) 850.00 1 Cum 850.00
1 Machine mixing charges 45.00 1 cum 45.00
4526.48
Sundries 0.02
Rate per 1Cum 4526.50
27 Providing Plain Cement Concrete in (1:3:6) propotion (cement; fine aggregate: coarse agrgregate)
using 20mm size (SS5) crusher broken hard granite graded stone aggregate of approved quality from
approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate,
water etc., to site including cost, all taxes and seigniorage charges on all materials, centering and
shuttering with proper packing, machine mixing, laying concrete, vibrating, shuttering, finishing to proper
slope and level including curing etc., including hire and running charges of machinery required for the
work with all labour T&P complete as per the specification and as directed by the Engineer-in-Charge for
Bed.
Unit 1 Cum
0.92 Cost of 20mm HBG SS5 graded metal 1338.69 1 Cum 1231.59
0.46 Cost of sand 1421.50 1 Cum 653.89
0.15 Cost of cement 6480.00 1 Cum 972.00
1.00 Labour charges 774.00 1 Cum 774.00
1.00 Centering charges (I No.978, P.61) 160.00 1 Cum 160.00
1 Machine mixing charges 45.00 1 cum 45.00
3836.48
Sundries 0.02
Rate per 1Cum 3836.50
27 PCC M25 Prop: Mix with graded hard granite stone aggregate of 20mm SS-5 size graded metal including
cost and conveyance of all materials and water to work site, seignorage, all operational incidential, labour
charges such as centering form work (steel centering), mixing concrete, laying, lift charges, tamping,
curing etc. complete for finished item of work as per standard specifications for Bed Blocks to hold fast
as directed by Engineer in charge.
Unit 1 Cum
0.92 Cost of 20mm Graded hard Granite metal 1338.69 1 Cum 1231.59
0.46 Cost of sand 1421.50 1 Cum 653.89
0.30 Cost of cement 6480.00 1 Cum 1944.00
1.00 Labour charges 774.00 1 Cum 774.00
1.00 Centering charges (item 299) 760.00 1 Cum 760.00
1 Machine mixing charges 45.00 1 cum 45.00
Rate per 1 Cum 5408.48
Sundries 0.02
Rate per 1 Cum 5408.50
Model-Munaganoor-data-29-08-08)
Page 54 (Cellar+Stilt) M30 & other floors with M25
APRSCL
28 Providing Weep holes with 110 mm dia. of required length with PVC pipe of make(SUDHAKAR / NANDI /
PRINCE) conforming to IS 49851 2000, of 2.5 kg/sqcm pressure and bell mouth finishing at inlet including
cost, all txes and all labour charges for conveyance to site, cutting into required sizes, placing in position,
maintaining slopes as directed by Engineer-in-charge etc., including metal spall backing 30cm X 30cm.
size in rear complete for Weep holes in all respects as per the specification & direction of the Engineer-in-
Charge.
Unit 1 RM
1.00 Cost of pipe (As per SSR P.200 ) 127.67 1 RM 127.67
1.00 Fixing charges (SSR item 16 , P.165 ) 5.00 1 RM 5.00
132.67
Sundries 0.03
Rate per 1RM 132.70
29 Supplying,laying and fixing 1200mm dia. NP2 Class RCC Hume pipes of socket and spigot type in
position including lifting, aligning etc., complete with (fixing ) collars includig cost and conveyance of all
materials and labour charges etc., complete for finished item of work.
Unit-One RM
Rate for 7.50 RM
Cost of 1200 mm dia. Pipes (SSR P-55, Table - 4239.80 1 31798.50
7.50 3) including excise duty RM
Conveyance charges p-60 for 10KM 119.30 1 894.75
7.50 (92.30+5X5.40) RM
7.50 Laying&fixing charges-(SSR P.29, Item 314) 100.00 1 RM 750.00
0.53 Add for MA & LALI @ 53% 750.00 1 397.50
Rate for 7.50RM 33840.75
Rate per 1 RM 4512.10
Sundries 0.00
Rate per 1RM 4512.10
30 Supplying, laying and fixing 1000mm dia. NP2 Class RCC Hume pipes of socket and spigot type in
position including lifting, aligning etc., complete with (fixing ) collars includig cost and conveyance of all
materials and labour charges etc., complete for finished item of work.
Unit-One RM
Rate for 7.50 RM
Cost of 1000 mm dia. Pipes (SSR P-55, Table - 3178.40 1 23838.00
7.50 3) including excise duty RM
Conveyance charges p-60 for 10KM 99.80 1 748.50
7.50 (92.30+5X5.40) RM
7.50 Laying&fixing charges-(SSR P.29, Item 314) 82.00 1 RM 615.00
0.53 Add for MA & LALI @ 53% 615.00 1 325.95
Rate for 7.50RM 25527.45
Rate per 1 RM 3403.66
Sundries 0.04
Rate per 1RM 3403.70
31 Supplying, laying and fixing 600mm dia. NP2 Class RCC Hume pipes of socket and spigot type in
position including lifting, aligning etc., complete with (fixing ) collars includig cost and conveyance of all
materials and labour charges etc., complete for finished item of work.
Unit-One RM
Rate for 7.50 RM
Cost of 600 mm dia. Pipes (SSR P-55, Table - 1249.32 1 9369.90
7.50 3) including excise duty RM
Conveyance charges p-60 for 10KM 34.60 1 259.50
7.50 (92.30+5X5.40) RM
7.50 Laying&fixing charges-(SSR P.29, Item 314) 23.50 1 RM 176.25
0.53 Add for MA & LALI @ 53% 176.25 1 93.41
Rate for 7.50RM 9899.06
Model-Munaganoor-data-29-08-08)
Page 55 (Cellar+Stilt) M30 & other floors with M25
APRSCL
32 Supplying,laying and fixing 300mm dia. NP2 Class RCC Hume pipes socket and spigot type in position
including lifting, aligning etc., complete with (fixing ) collars includig cost and conveyance of all materials
and labour charges etc., complete for finished item of work.
Model-Munaganoor-data-29-08-08)
Page 56 (Cellar+Stilt) M30 & other floors with M25
APRSCL
Unit 1 RM
Rate for 7.50 RM
7.50 Cost of 300mm dia. Pipes -page55 436.16 1 RM 3271.20
7.50 Conveyance charges p-60 13.00 1 RM 97.50
7.50 Laying&fixing charges-(SSR P.28, Item 308) 23.50 1 RM 176.25
0.53 Add for MA & LALI @ 53% 176.25 1 93.41
Rate for 7.50RM 3638.36
Rate per 1 RM 485.11
Sundries 0.09
Rate per 1RM 485.20
33 Supplying,laying and fixing 150mm dia. NP2 Class RCC Hume pipes in position including lifting, aligning
etc., complete with (fixing ) collars includig cost and conveyance of all materials and labour charges etc.,
complete for finished item of work.
Unit 1 RM
Rate for 7.50RM :
7.50 Cost of 150mm dia. Pipes -page55 219.24 1 RM 1644.30
7.50 Conveyance charges p-60 4.90 1 RM 36.75
7.50 Laying&fixing charges-(SSR P.28, Item 308) 17.00 1 RM 127.50
0.53 Add for MA & LALI @ 53% 127.50 1 67.58
Rate for 7.50RM 1876.13
Rate per 1 RM 250.15
Sundries 0.05
Rate per 1 RM 250.20
Unit 1 Cum
Page 95 of MoRT&H SDB
Taking output 300.00
(A) Labour
0.40 Mate 188.00 1 day 75.20
2.00 Mazdoor skilled 193.40 1 day 386.80
8.00 Mazdoor unskilled 146.00 1 day 1168.00
1630.00
0.53 Add for MA & LALI @ 53% 863.90
Total of A 2493.90
(B) Machinery
6.00 Motor grader 3.35M Blade @50 cum/Hr 2600.00 1 hr 15600.00
12.00 Tractor with Rotavator 345.00 1 hr 4140.00
6.00 Vibratory roller 8T 1550.00 1 hr 9300.00
3.00 Water tanker 6 KL 345.00 1 hr 1035.00
Total of B 30075.00
(C) Material
Coarse graded Granular sub-base material as
per Table 400-2 of MORT&H
255.00 9.5mm to 4.75mm @ 66% 902.43 1 Cum 230119.65
(Av. rate of 9.5-11.2mm , 5-7mm & 2.36 - 5mm
HBG M/C metal)
129.00 2.36mm and below @34% 558.30 1 Cum 72020.70
(Rate of 2.36mm & below HBG metal)
Total of C 302140.35
Model-Munaganoor-data-29-08-08)
Page 57 (Cellar+Stilt) M30 & other floors with M25
APRSCL
35 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix
Macadem specification including cost,seignorage of all materials and including premixing the material
with water at OMC in Mechanical mix plant carriage of mixed material by tipper to site , laying in uniform
layers with paver in base courses on well prepared surface and compacting with Vibratory roller to
acheive the desired density etc., as directed by the Engineer-in-Charge and as per MoRT&H
specification.406 (4th revision) for finished item of work. (Payment based on levels for finished item of
work)
Unit 1 Cum
Page 110,111 of MoRT&H SDB
Taking output 225.00
(A) Labour
0.48 Mate 188.00 1 day 90.24
2.00 Mazdoor skilled 193.40 1 day 386.80
10.00 Mazdoor 146.00 1 day 1460.00
1937.04
0.53 Add for MA & LALI @ 53% 1026.63
Total of A 2963.67
(B) Machinery
6.60 Wet mix plant of 60 tonne hr. capacity 1320.00 1 hr 8712.00
6.00 Electric generating set 125 KVA 1090.00 1 hr 6540.00
6.00 front end loader 1 cum capacity 1320.00 1 hr 7920.00
6.00 Mechanical Paver finisher 100 TPH 1090.00 1 hr 6540.00
3.90 Vibratory roller 8-10 T 1550.00 1 hr 6045.00
3.00 Water tanker 345.00 1 hr 1035.00
Total of B 36792.00
(C) Material
89.10 45 to 22.40mm IRC&MoRT&H HBG M/C 1298.68 1 cum 115711.94
metal@ 30%
(Av. Of 40-45, 25-27, 19-22mm )
118.80 22.4 to 2.36mm IRC&MoRT&H HBG M/C 1181.49 1 cum 140360.72
metal@40%
(Av. Of 19-22mm, 12-14mm, 9.5-11.2mm, 5-7mm,
2.36 - 5mm )
89.10 2.36mm to 75 micron @ 30% 558.30 1 cum 49744.53
(2.36mm & below)
Total of C 305817.19
Total of (A) + (B)+( C) 345572.86
36 Providing and laying Surface dressing in single coat using 6 mm nominal size IRC HBG machine
crushed stone aggregates @ 0.004cum/sqm on a layer of bitumen binder of 80/100 grade @ 0.75 kg /
sqm. including cost, seigniorage and conveyance of all materials to work site and laid on prepared
surface and rolling with 8-10 T Power Road Roller etc., complete for finished item of work as per
MoRT&H Specification 510 (4th Revision) and as directed by the Engineer-in-charge.
Unit 1 Sqm
Page 141,142 of MoRT&H SDB
Taking output 9000.00 Sqm
Model-Munaganoor-data-29-08-08)
Page 58 (Cellar+Stilt) M30 & other floors with M25
APRSCL
(A) Labour
0.44 Mate 188.00 1 day 82.72
9.00 Mazdoor 146.00 1 day 1314
2.00 Mazdoor skilled 193.40 1 day 386.8
1783.52
0.53 Add for MA & LALI @ 53% 945.27
Total of A 2728.79
(B) Machinery
7.20 Mechanical broom @ 1250 sqm/hr. 290.00 1 hr 2088.00
7.20 Air compressor 250 cfm 370.00 1 hr 2664.00
6.00 Hydraulic self propelled chip spreader @ 1500 s 2070.00 1 hr 12420.00
6.00 Tipper 10Tonne capacity for carriage of stone 575.00 1 hr 3450.00
chips from stock pile on road side to chip
spreader (Rate of Tipper 5 cum)
6.00 Front end loader 1 cum bucket capacity 1320.00 1 hr 7920.00
6.00 Bitumen pressure distributor @1750 sqm/hr 940.00 1 hr 5640.00
6.00 smooth wheeled roller 8 Ton 540.00 1 hr 3240.00
Total of B 37422.00
(C) Material
6.75 Bitumen 80/100 @ 0.75 Kg / sqm 32442.77 1 MT 218988.71
36.00 Crushed stone chippings 6mm nominal size 929.93 1 Cum 33477.30
@0.004 cum / sqm
Total of C 252466.01
37 Providing and applying Prime coat with bitumen Emulsion (Medium settting) (Bulk) using Emulsion
pressure distributor on prepared surface of Grannular base including cleaning of road surface and
spraying emulsion at the rate of 0.60 Kg/Sq.m using Emulsion pressure distributor for finished item of
work as directed by the Engineer-in-Chargeas and as per MoRT&H Specification No.502.
Unit 1 Sqm
Taking output 3500.00
(A) Labour
0.08 Mate 188.00 day 15.04
2.00 Mazdoor 146.00 day 292.00
307.04
0.53 Add for MA & LALI @ 53% 162.73
Total of A 469.77
(B) Machinery
2.80 Mechanical broom Hydraulic @ 1250 sqm/hr. 290.00 hr 812.00
2.80 Air compressor 250 cfm 370.00 hr 1036.00
2.00 Emulsion pressure distributor @1750 sqm/hr 690.00 hr 1380.00
Total 3228.00
Total of B 3228.00
(C) Material
2.10 Bitumen Emulsion @ 0.20 Kgs/sqm 26114.84 MT 54841.16
Total of C 54841.16
Model-Munaganoor-data-29-08-08)
Page 59 (Cellar+Stilt) M30 & other floors with M25
APRSCL
37 Providing and applying Tack coat with bitumen Emulsion (Medium settting) (Bulk) using Emulsion
pressure distributor at the rate of 0.20 kgs per sqm on the prepared bituminous/granular surface cleaned
with mechanical broom for finished item of work as per MoRT&H Specification 503 (4 th revision) and as
directed by the Engineer-in-Charge.
Unit 1 Sqm
Page 124 of MoRT&H SDB
Taking output 3500.00
(A) Labour
0.08 Mate 188.00 day 15.04
2.00 Mazdoor 146.00 day 292.00
307.04
0.53 Add for MA & LALI @ 53% 162.73
Total of A 469.77
(B) Machinery
2.80 Mechanical broom Hydraulic @ 1250 sqm/hr. 290.00 hr 812.00
2.80 Air compressor 250 cfm 370.00 hr 1036.00
2.00 Emulsion pressure distributor @1750 sqm/hr 690.00 hr 1380.00
Total 3228.00
Total of B
(C) Material
0.70 Bitumen Emulsion @ 0.20 Kgs/sqm 26114.84 MT 18280.39
Total of C 18280.39
38 Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant using hard
blasted granite crushed aggregates of Grading -2 as per table 500-15 of specification 508 of MoRT&H
(4th Revision), premixed with bituminous binder 60/70 grade @ 5% of mix and filler, transporting the hot
mix to work site, laying with mechanical paver finisher to the required grade, level and alignment, rolling
with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoRT&H
Specification 508 (4th Revision) complete for finished item of work in all respects as directed by Engineer-
in-charge.(Payment will be made based on levels for finished item of work)
Unit 1 Cum
Page 135,136,137 of MoRT&H SDB
Taking output 195.00 (450 tonnes.)
(A) Labour
0.84 Mate 188.00 1 day 157.92
14.00 Mazdoor working with HMP, Mechanical broom, 146.00 1 day 2044.00
paver,roller,asphalt cutter and assistance for
setting outlines,levels and layout of
construction.
5.00 Skilled Mazdoor for checking line and levels. 193.40 1 day 967.00
3168.92
0.53 Add for MA & LALI @ 53% 1679.53
Total of A 4848.45
Model-Munaganoor-data-29-08-08)
Page 60 (Cellar+Stilt) M30 & other floors with M25
APRSCL
(B) Machinary
11.00 Hot mix plant 40 to 60 TPH 15525.00 1 hr 170775.00
6.00 Mechanical Paver finisher @ 100 TPH 1090.00 1 hr 6540.00
6.00 Generator 250 KVA 1550.00 1 hr 9300.00
6.00 Front end loader 1 cum capacity 1320.00 1 hr 7920.00
3.90 Power road roller 8 tonne for initial break down rolling 540.00 1 hr 2106.00
3.90 Vibratory roler 8 tonne for intermediate rolling 1550.00 1 hr 6045.00
3.90 Finish rolling with 6-8 tonne smooth wheeled 540.00 1 hr 2106.00
tandem roller.
Total of B 204792.00
(C) Material
22.50 (I) Bitumen 60/70 grade @ 5% by weight of mix 33742.44 1 MT 759204.88
(ii) Aggregate
For Grading II
162.450 IRC & MORT&H HBG M/C chips 9.5 to 4.75mm 902.43 1 cum 146599.75
@ 57%
Average rate of IRC&MoRT&H HBG M/C
metal of sizes 9.5-11.2, 5-7mm,2.36 - 5mm
116.850 IRC &MORT&H HBG M/C chips 4.75 mm and 621.61 1 cum 72635.42
below @ 41%
Average rate of IRC & MoRT & H HBG M/C
metal of sizes 2.36 - 5mm and 2.36mm & below
39 Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing an average
output of 37.5 tonnes per hour using hard blasted granite crushed aggregates of Grading - II as per table
500-4 of MoRT&H specificaion 504 (4th Revision) premixed with bituminous binder of 80/100 grade @
3.3% by weight of total mixture, transported to site, laid over a previously prepared surface with
mechanical paver finisher to the required grade, level and alignment and rolled as per Clauses 501.6 and
501.7 to achieve the desired compaction for finished item of work as directed by the Engineer-in-Charge
including hire and opeational charges all T&P and all other contingent charges necessary including cost
of seigniorage charges on all materials etc., complete and as per MoRTH specification No. 504(4 th
Revision) .
Unit 1 Cum
Page 125,126,127 of MoRT&H SDB
Taking out put 205.00 (450 tonne)
(A) Labour
0.84 Mate 188.00 1 Each 157.92
14.00 Mazdoor working with HMP, mechanical broom, 146.00 1 Each 2044.00
paver, roller, asphalt cutter and assistance for
setting out lines, levels and layout of
construction.
5.00 Mazdoor skilled 193.40 1 Each 967.00
3168.92
0.53 Add for MA & LALI @ 53% 1679.53
Total of A 4848.45
Model-Munaganoor-data-29-08-08)
Page 61 (Cellar+Stilt) M30 & other floors with M25
APRSCL
(B) Machinery
12.00 Hot Mix Plant 40 to 60 TPH 15525.00 1 hr 186300.00
2.20 Air Compressor 250 cfm 370.00 1 hr 814.00
6.00 Mechanical Paver finisher 100 TPH 1090.00 1 hr 6540.00
6.00 Generator 250 KVA 1550.00 1 hr 9300.00
6.00 Front end loader 1 cum bucket capacity 1320.00 1 hr 7920.00
3.90 Smooth wheeled roller 8-10 tonnes for initial 540.00 1 hr 2106.00
break down rolling
3.90 Vibratory roller 8 T for intermediate rolling 1550.00 1 hr 6045.00
3.90 Finish rolling with 6-8 tonnes smooth wheeled 540.00 1 hr 2106.00
tandem roller.
Total of B 221131.00
(C) Material
i) Bitumen
14.85 Bitumen 80/100 @ 3.3 % of weight of 32442.77 1 MT 481775.16
mix=205x2.2=450 tonne
ii) Aggregate
Total weight of mix : 450 tonnes
weight of bitumen : 14.85 tonnes
Weight of aggregate : 450-14.85 = 435.15 tonnes
Taking density of aggregate : 1.5 tonne/cum
Volume of aggregate : 290.1 cum
Grading - II (19 mm nominal size)
116.04 Cum of 25-10mm @ 40%
116.04 IRC &MORT&H HBG M/C chips 25 to 10mm @ 1306.49 1 cum 151604.81
40%
Average rate of IRC&MoRT&H HBG M/C
metal of sizes 25-27mm, 19-22mm, 12-14mm,
9.5-11.2mm
116.04 IRC &MORT&H HBG M/C chips 10 to 5mm @ 902.43 1 cum 104717.98
40%
Average rate of IRC&MoRT&H HBG M/C
metal of sizes 9.5-11.2mm, 5 to 7mm
58.02 IRC &MORT&H HBG M/C chips 5mm and 621.61 1 cum 36065.96
below @ 20%
Average rate of IRC&MoRT&H HBG M/C
metal of sizes 2.36 to 5mm and 2.36mm&
below
Total of C 774163.91
Total of (A) + (B)+( C)+(D) 1000143.36
Model-Munaganoor-data-29-08-08)
Page 62 (Cellar+Stilt) M30 & other floors with M25
DATAS ( As per SSR-2007-08)
Add for MA & LALI @ 53% 0.53
Part-A Sub-Structure 'A' Civil work
S.No Qty Particulars Rate unit Amount
1 Earth work excavation and depositing on bank with an initial lead of 10 meters and lift of 2 meters in mixture of
gravel and soft disintegrated rock like shales, ordinary gravel stoney earth and earth mixed with fair sized
boulders which does not require blasting including shoring, shuttering and bailing out water for foundations.
2 Refilling with useful excavated soil other than sand complying with standard specifications in layers of 150
mm thick watering, tamping, consolidation including cost and conveyance of water to work site and all
operational, incidental, labour charges etc. complete for filling of basements.
Unit One Cum
1.00 Labour charges per cum as per SSR Item 286 Page 8.40 1 Cum 8.40
No.151
0.53 Add for MA & LALI @ 53% 8.40 1 4.45
Sundries 0.04
Total Rate per 1 CUM
3 Plain cement concrete work of mix (1:5:10) prop. using 40mm guage hard granite machine crushed metal
including cost of machine mixing, laying, levelling, tamping, curing and conveyance of all materials and all
operational, incidental and labour charges,seignorage charges etc. complete for levelling course below column
footings and below flooring.
Unit-One Cum
0.92 Rate of 40 mm HBG Metal ( as per lead chart) 826.85 1 Cum 760.70
0.46 Cost of C.M (1:5) 2412.40 1 Cum 1109.70
1.00 Labour charges as per labour chart including MA&LI 539.04 1 Cum 539.04
1.00 Machine mixing charges (item 292, P 151 of common 37.50 1 Cum 37.50
SSR)
-0.46 (-) deduct mortar mixing charges 22.50 1 Cum -10.35
Total 2436.59
Sundries 0.01
Total Rate per 1 CUM 2436.60
4 Construction of Random Rubble stone masonry in CM (1:8) prop: (Cement: Sand) using using hard stones of
granite variety from approved quarry including cost and conveyance of all materials like cement, sand, water,
stones etc., from approved quarry, to site and including seigniorage charges, sales & other taxes on all
materials including labour for cutting stones to required size and shape, mixing, of cement, mortar,
construction, scaffolding charges, curing etc., complete for finished item of work below plinth beam, side drains
etc.,
Unit-One Cum
1.10 Rate of R.R. Stone of granite variety ( as per lead chart) 480.50 1 Cum 528.55
6 Masonry in CM (1:2) prop. using Fly ash Interlocking Bricks made with flyash quarry dust and cement solid
blocks of size 15" x 15" x 4 1/2" and olid blocks having compressive strength not less than 50 Kg/Cm2 including
cost and conveyance of all materials, labour charges, curing etc., complete for pillars of Compound Walls.
Unit-One Cum
62 Cost of Flyash Interlocking bricks (Rate as per lowest 22.00 1 Each 1364.00
quotations)
0.10 Cost of Cement Mortar (1:2) 4313.20 1 Cum 431.32
1.00 Labour charges as per labour chart 715.68 1 Cum 715.68
10% Towards transportation of bricks 1364.00 1 136.40
2647.40
Rate per 1 Cum 2647.40
7 Supply and fixing of 40 x 40 x 6mm M.S Angle for barbed wire fencing including cutting, bending and placing in
position including cost, conveyance of all materials, all taxes and all labour charges for all operations etc.,
complete for finished item of work.
Unit-One Kg
1 Cost of M.S Angle 40 x 40 x 6mm 46600.00 1000 Kgs 46.60
1.00 Labour charges for fabrication( item 111) 10.00 1 Kgs 10.00
53% Add for MA & LALI @ 53% 10.00 1 5.30
61.90
Rate per 1 Kg 61.90
8 Providing fencing with barbed wire 12 gauge 3knot including cost all taxes and fixing with necessary material to
Y angle as directed by the Engineer In Charge.
Unit-One Kg
1 Cost of I.O.A. 12 Gauge barbed wire 35.00 1 Kgs 35.00
1.00 Labour charges 1.00 1 Kg 1.00
53% Add for MA & LALI @ 53% 1.00 1 0.53
36.53
Rate per 1 Kg 36.53
9 Paintingin two coats to Compound walls with Snowcem paint approved by the Engineer -in Charge including
cost and conveyance of all materials to site including all taxes and all labour charges etc. complete for finished
item of work.
S.No Qty Particulars Rate unit Amount
Unit-One Sqm
2.00 Cost of Snowcem 864.00 25 kgs 69.12
0.05 Painter First Class 180.00 1 Nos. 9.00
0.11 Painter Second Class 160.00 1 Nos. 17.60
0.05 Man Mazdoor 130.00 1 Nos. 6.50
0.27 Woman mazdoor 130.00 1 Nos. 35.10
0.53 Add for MA & LALI @ 53% 68.20 1 Cum 36.15
Rate per 10 sq.m. 173.47
Rate per 1 sq.m. 17.35
10 PCC M20 grade Design Mix (by weigh batching)to the required strength as per SS and IS-456:2000 using
stone aggregate of size 20 mm SS-5 HBG gauge graded hard granite machine crushed metal from approved
quarry using a minimum quantity of 300 kgs of cement per cum of concrete mechanically mixed, and placing
concrete as directed by the Engineer in charge including cost and conveyance of all materials and water to work
site, seigniorage fee, all taxes and all operational, incidental, labour charges such as centering form work (steel
centering) mixing concrete, laying, lift charges, vibrating, curing etc., complete for finished item of work as per
standard specification and as directed by the department (Basic Rate).
Inter locking CC
1.35 M blocks jointed with
0.23 M cement slurry
CRS masonry in
CM(1:8) with
0.45 M 0.38 M
Raised pointing in
CM(1:4)
Refilling
Ground Level
RRS masonry in
0.45 M 0.45 M
CM(1:8)
0.10 M PCC(1:5:10)
0.60 M
CROSS SECTION