source code
source code
INTRODUCTION
In this transformer is the industrial purposed transformer of, furnace transformer.
The high voltage is 11KV, low voltage is 1150V. power rating of the transformer is 8630KVA
the construction of transformer is the core type transformer. The cooling type of the transformer
is the oil natural air natural. The transformer is the off circuit tap changer (OCTC). The
induction furnace has coil constructed from heavy copper tubing. It is designed and tuned to
the inverter circuit which applied medium frequency of induction coil. The magnetic field
produced by the induction coil induces eddy current in the charge and heats it. Medium
frequency is necessary to enhance the rate of heat generation. The transformer which are used
for transforming available three phase A.C voltage to required voltage for converter circuit of
the induction furnace transformer. Depending on the rating of the transformer input voltage is
derived from standard three phase AC distribution voltage is 11KV.
The transformer must be designed to resist the high levels of electrical, the thermal and
mechanical stress to they are during utilisation. The designing for electric arc furnaces are the
high secondary currents to fusion process and the wide range of secondary voltages, they are
normally regulated by an on load tap changer(OLTC), but this job required for the off circuit
tap changer(OCTC), on the high voltage winding an a intermediate booster located within the
same tank.
The furnace transformer thus has special features to handle such high currents
compared to to conventional (Distribution) transformer. The electric arc furnace has three
electrodes connected to the secondary terminal of the furnace transformer. The secondary
terminal of the transformer is frequent short circuit during the melting process through the
charge and arc. The furnace transformer need to be specially designed to withstand the
frequent short circuits.
1
CHAPTER 2
TESTING OF TRANSFORMER
2. TESTING OF TRANSFORMER:
Transformer testing is done for maintaining the specifications and performance of an
electrical power transformer. The transformer is the main part of an electrical
generation/distribution system so if it is not working properly then it will affect the whole
generation/distribution system. Hence it is very important to make sure its perfectly fine for
which periodical testing and maintenance is required. The need for transformer testing is to
check the functioning of the transformer and to decrease the chance of failure. All electrical
equipment needs to be maintained safely from some of the failures. Transformer failure can
happen because of electrical, thermal, or mechanical factors. Insulation breakdown will also
cause transformer failure. Power Electrical offers various routine and special testing services
with precise and reliable assessment for Power transformers, Distribution transformers, and
Instrument transformers.
3
have a very important role in protection and monitoring of the system. The following are
thetestes for Instrument transformers:
• Polarity
• Ratio
4
CHAPTER 3
The transformer turns ratio test is used to determine the number of turns in one winding
of a transformer (Primary winding) in relation to the number of turns in the other winding
(Secondary) of the same phase of the transformer.
The performance of the transformer largely depends upon the perfection of specific turns
or voltage ratio of the transformer. So, transformer ratio test is an essential type test of
transformer. The voltage should be applied only in high voltage winding in order to avoid
unsafe voltage during testing. Actually, the no load voltage ratio of transformer is equal to the
turns ratio of the transformer.
LIST OF EQUIPMENT:
PRECAUTIONS:
2.Do not operate the tap changer switch at the time of reset.
PROCEDURE:
1. First, the tap changer of transformer is kept in the lowest position and LV
terminals are kept open.
2. Then apply three phase 415V supply on HV terminals. Measure the voltages
applied on each phase (Phase-Phase) on HV and induced voltages at LV terminals
simultaneously.
5
4. Repeat the same for each of the tap position separately.
The above ratio test can also be performed by portable transformer turns ratio meter(TTR).
They have an in-built power supply, with the voltages commonly used being very low, such
as8-10V and 50 Hz. The HV and LV windings of one phase of a transformer are connected to
the instrument and the internal bridge elements are varied to produce a null indication of the
detector.
Let’s have the discussion on transformer turns ratio(TTR) meter method of turn ratio test of
transformer.
A phase voltage is applied to the one of the windings by means of a bridge circuit and the ratio
of induced voltage is measured at the bridge. The accuracy of the measuring instrument is <
0.1%.
LV winding voltage
This theoretical turn ratio is adjusted on the transformer turn ratio tested or TTR by the
adjustable transformer. It should be changed until a balance occurs in the percentage error
indicator.
The reading on this indicator implies the deviation of measured turn ratio from expected turn
ratio in percentage.
Out-of-tolerance, ratio test of transformer can be due to shorted turns, especially if there is an
associated high axcitation current. Open turns in HV winding will indicate very low exciting
current and no output voltage since open turns in HV winding causes no excitation current in
the winding means no flux hence no induced voltage.
But open turn in LV winding causes, low fluctuating LV but normal excitation current in HV
winding. Hence open turns in LV winding will be indicated by normal levels of excitation
current, but very low levels of unstable output voltage. The turns ratio test of transformer also
detects high resistance connections in the lead circuitry or high contact resistance in tap
changers by higher excitation current and a difficulty in balancing the bridge
6
3.1 MEASUREMENT OF TURNS RATIO(Dyn11)
7
3.2 MAGNETIC BALANCE TEST OF TRANSFORMER:
Magnetic balance test is basically to ensure that there is no inter turn fault in the windingwhich
is generally reflected in high excitation current in faulty winding.
PRINCIPLE OF TEST:
1. Magnetic balance test indicates that the transformer is magnetically balanced .If there
is any inter turn short circuit that may result in the sum of the two voltage not being equal to
the applied voltage.
LIST OF EQUIPMENT:
Digital multimeter
Leakage current tester
Cables
PRECAUTIONS:
1. This test to be carried out before winding resistance measurement and insulation
resistance measurement.i.e. during magnetic balance test core should not get saturated.
2. Can should be taken during exciting current measurement to avoid the effect of
residual magnetism in the transformer core. The residual magnetism result in the measurement
of higher than normal exciting current.
4.Do not touch live part of the conducter at the time of set.
5. While performing the test in secondary side, remove any cable are clamped in the
primary side for conducting further test.
8
PROCEDURE OF MAGNETIC BALANCE TEST:
3. Then apply single phase 230V AC supply across one of the HV winding terminals
and neutral terminal.
There are three limbs placed side by side in a core of the transformer. One phase
winding is wound in one limb. The voltage induced in different phases depends upon the
respective position of the limb in the core. The voltage induced in different phases of a
transformer in respect to neutral terminals.
9
TEST EQUIPMENT:
Digital multimeter
Clam meter
Cable
Test board
TEST PROCEDURE:
1.Keep the tap changer in the lowest position and open all HV and LV terminals. 2.Then
apply three phase 415 V supply on the line terminals for three-phase transformers
and single phase 230 V supply on single phase transformers.
3. Measure the supply voltage and current in each phase.
4. Now repeat the magnetizing current test of transformer test with keeping the tap at
highest position.
Normally, there are two similar higher readings on two outer limb phases on
transformer core and one lower reading on the centre limb phase, in the case of three phase
transformers.
An agreement to within 30% of the measured current with the previous test is usually
considered satisfactory. If the measured exciting current value is 50 times higher than the value
measured during factory test, there is a likelihood of a fault in the winding which needs further
analysis.
10
3.4 VECTOR GROUP TEST OF TRANSFORMER:
TEST EQUIPMENT:
Digital multimeter
Cables
Test board with MCB arrangements.
TEST PROCEDURE:
2. Draw the superimposed vector diagram from the name plate detail provided
bythe transformer manufacturer.
4. Connect the testing lead say 2.5 sq.mm copper cable to the primary and
secondary side and shorting of terminal to be done as per the vector diagram from the
transformer.
11
S.No Terminals Measured Voltage
(V)
1 1W2w 388.7
2 1W2v 430.9
3 1V2w 390.3
4 1V2v 390.9
5 1U2n 27.18
6 1V2n 403.1
7 1U1V 429.4
1W2w<1W2v 388.7<430.9
1V2w≈1V2v 388.7=390.9
Dyn11
1U2n+2n1V =1U1V 27.18+403.1=429.4
430.28=429.4
12
S.No Terminal Measured
Voltage(V)
1 1W3w 381.8
2 1W3v 408.0
3 1V3v 383.6
4 1U3v 46.90
5 1U1V 429.7
13
3.5 INSULATION RESISTANCE TEST OR MEGGER TEST OF
TRANSFORMER:
Insulation resistance test of transformer is essential type test. This test is carried out to
ensurethe healthiness of the overall insulation system of an electrical power transformer.
Insulation resistance caused by numerous factor including design, temperature, dryness and
cleanliness.
TEST EQUIPMENT:
High voltage insulation meter
Cables
PRECAUTIONS:
1. Transformer and the bushing under test shall be thoroughly cleaned
with dry cloth.
7. Do not touch the live part of the conductor at the time of test.
14
PROCEDURE FOR INSULATING RESISTANCE TEST:
1. Disconnect all the line and neutral terminals of the transformer.
Measuring the resistance of the transformer winding assures that each circuit is wired
properly and that all connections are tight. Transformer winding resistance measurements are
obtained by passing a known DC current through the winding under test and measuring the
voltage drop across each terminal (Ohm’s Law). Modern test equipment for this purposes
utilizes a Kelvin bridge to achieve results.
PRINCIPLE OF TEST:
Transformer winding resistance can be measured by Kelvin bridge method. This
method based on comparing an unknown resistance with a known resistance.
TEST EQUIPMENT:
Winding resistance meter
cables
Infrared thermometer.
PRECAUTIONS:
1. Charged battery of sufficient capacity or at least 10A shall be used
with the bridge to avoid error due to drop in battery voltage during
measurements.
3. The polarity of the core magnetization shall be kept same during all
resistance reading
4. The voltage lead shall be independent of the current lead and shall be
connect as closely as possible to the terminal of the winding to be
measured.
16
5. The current used shall not exceed 15% of the rated current of the
winding whose resistance is to be measured. Larger value may cause
inaccuracy due to heating of the winding and then by changing the
temperature of resistance.
TEST PROCEDURE:
1. Before measurement, the transformer should be kept in off condition without
excitation at least for 3-8 hours, during this time the winding temperature will become
equal to its oil temperature. The test should be done in all tap position for primary as
well as secondary side of transformer.
3. The winding resistance meter consist of four clamps c+, c- (current injection
cable) and v+,v-(voltage drop measuring cable).c+,c- should be connected to the
starting point of the winding and c-,v- should be connected the ending point of the
winding.
4. The current cable (c+,c-) should be outer or top side of the bushing stem and
the voltage cable (v+,v-)should be clamped at the inner or bottom part of the bushing
stem with respect to the current cable.
5. The applied current shall not exceed 15% of the rated current of the winding.
TAP 1W-1U
1U-1V 1V-
NO
1W
1 80.18 80.14 79.70
2 78.27 78.94 77.96
3 76.40 76.41 76.12
4 75.31 74.50 74.44
5 72.60 72.64 72.69
6 70.60 70.93 70.91
7 69.20 69.06 68.77
17
LV Winding Resistance in(mΩ)
18
CHAPTER 4
FINAL INSPECTION
The transformer turns ratio test is used to determine the number of turns in one winding
of a transformer (Primary winding) in relation to the number of turns in the other winding
(Secondary) of the same phase of the transformer.
The performance of the transformer largely depends upon the perfection of specific
turns or voltage ratio of the transformer. So, transformer ratio test is an essential type test of
transformer. The voltage should be applied only in high voltage winding in order to avoid
unsafe voltage during testing. Actually, the no load voltage ratio of transformer is equal to the
turns ratio of the transformer.
LIST OF EQUIPMENT:
PRECAUTIONS
PROCEDURE:
1. First, the tap changer of transformer is kept in the lowest position and LV
terminals are kept open.
2. Then apply three phase 415V supply on HV terminals. Measure the voltages
applied on each phase (Phase-Phase) on HV and induced voltages at LV terminals
simultaneously.
19
3. After measuring the voltages at HV and LV terminals, the tap changer of the
transformer should be raised by one position and repeat test.
The above ratio test can also be performed by portable transformer turns ratio meter (TTR).
They have an in-built power supply, with the voltages commonly used being very low, such as
8-10V and 50 Hz. The HV and LV windings of one phase of a transformer are connected to the
instrument and the internal bridge elements are varied to produce a null indication of the
detector.
Let’s have the discussion on transformer turns ratio(TTR) meter method of turn ratio test of
transformer.
A phase voltage is applied to the one of the windings by means of a bridge circuit and the ratio
of induced voltage is measured at the bridge. The accuracy of the measuring instrument is <
0.1%.
The reading on this indicator implies the deviation of measured turn ratio from expected turn
ratio in percentage.
Out-of-tolerance, ratio test of transformer can be due to shorted turns, especially if there is an
associated high excitation current. Open turns in HV winding will indicate very low exciting
current and no output voltage since open turns in HV winding causes no excitation current in
the winding means no flux hence no induced voltage.
But open turn in LV winding causes, low fluctuating LV but normal excitation current in HV
winding. Hence open turns in LV winding will be indicated by normal levels of excitation
current, but very low levels of unstable output voltage. The turns ratio test of transformer also
20
4.1MEASUREMENT OF VOLTAGE RATIO:
4.1.1 HV (DELTA) TO
LV1(STAR)
4.1.2 HV (DELTA) TO
LV2(DELTA)
TAP CALCULA MEASURED RATIO & %
NO D RATIO ERROR
1U - 1V % 1V - 1W % 1W - 1U %
3u - 3v ERROR 3v - 3w ERROR 3w - 3u ERRO
R
1 10.283 10.281 -0.019 10.280 -0.029 10.280 -0.029
2 10.043 10.057 0.139 10.058 0.149 10.059 0.159
3 9.804 9.836 0.326 9.835 0.316 9.835 0.316
4 (N) 9.565 9.591 0.272 9.592 0.282 9.591 0.272
5 9.326 9.347 0.225 9.348 0.236 9.347 0.225
6 9.087 9.103 0.176 9.103 0.176 9.103 0.176
21
Figure 4.1 RATIO TEST
PRINCIPLE OF TEST:
LIST OF EQUIPMENT:
Digital multimeter
Leakage current tester
Cables
22
PRECAUTIONS:
4.Do not touch live part of the conducter at the time of set.
3. Then apply single phase 230V AC supply across one of the HV winding
terminals and neutral terminal.
There are three limbs placed side by side in a core of the transformer. One phase winding is
wound in one limd. The voltage induced in different phases depends upon the respective
position of the limb in the core. The voltage induced in different phases of a transformer in
respect to neutral terminals
23
4.2 MAGNETIC BALANCE TEST of TRANSFORMER:
PHASE 1U - 1V (V) 1V - 1W 1W - 1U
(V) (V)
24
4.3 MAGNETIZING CURRENT TEST OF TRANSFORMER:
Magnetic current test of transformer is performed to locate defects in the magnetic core
structure, shifting of windings, failure in between turn insulation or problem in tap changers.
These conditions change the effective reluctance of the magnetic circuit, thus affecting the
current required to establish flux in the core.
TEST EQUIPMENT:
Digital multimeter
Clam meter
Cable
Test board
PROCEDURE:
1. Keep the tap changer in the lowest position and open all HV and LV
terminals.
2. Then apply three phase 415 V supply on the line terminals for three-phase
transformers and single phase 230 V supply on single phase transformers.
4. Now repeat the magnetizing current test of transformer test with keeping the
tap at highest position.
Normally, there are two similar higher readings on two outer limb phases on transformer core
and one lower reading on the center limb phase, in the case of three phase transformers.
An aggrement to within 30% of the measured current with the previous test is usually
considered satisfactory. If the measured exciting current value is 50 times higher than the value
measured during factory test, there is a likelihood of a fault in the winding which needs further
analysis
25
4.3 MEASUREMENT OF MAGNETIZING CURRENT AT LOW
VOLTAGE
4.3.1 HV ( TAPNO: 4)
Voltage applied on HV 1U - 1V 1V - 1W 1W - 1U
26
4.4 VECTOR GROUP TEST OF TRANSFORMER:
In a three phase transformer, it is essential to carry out a vector group test of transformer.
Proper vector grouping in a transformer is some essential criteria for parallel operation of
transformers.
TEST EQUIPMENT:
Digital multimeter
Cables
Test board with MCB arrangements.
PRECAUTIONS:
2. Use the proper insulated copper cable and clamping of the cable at the stem
of the bushing should be done properly in order to prevent small amount of voltage drop at the
time of test.
TEST PROCEDURE:
1. Vector group is performed between primary and secondary side of the transformer
in the rated tap position.
2. Draw the superimposed vector diagram from the name plate detail provided by
the transformer manufacturer.
4. Connect the testing lead say 2.5 sq.mm copper cable to the primary and secondary
side and shorting of terminal to be done as per the vector diagram from the transformer.
4.4.1 HV - LV1(Dyn11)
28
3.4 HV - LV2(Dd0)
29
4.5 INSULATION RESISTANCE TEST OR MEGGER TEST OF
TRANSFORMER:
Insulation resistance test of transformer is essential type test. This test is carried out to
ensure the healthiness of the overall insulation system of an electrical power transformer.
TEST EQUIPMENT:
PRECAUTIONS:
1. Transformer and the bushing under test shall be thoroughly cleaned with dry cloth.
2.During the measurement the test area shall be demarked with warning tape.
6.Do not operate the tap changer switch at the time of test.
7. Do not touch the live part of the conductor at the time of test.
8. Deenergize or connect the bushing lead to the earth after performing the test for
each circuirt combination, as it will prevent us from electrical shock due to some residual
charges present in transformer.
30
4. Megger leads to be connected to LV bushing studs and transformer tank earth point
to measure insulation resistance IR value in between the LV windings and earth.
NB: It is unnecessary to perform insulation resistance test of transformer per phase wise in
three-phase transformer. IR values are taken between the windings collectively as because all
the windings on HV side are internally connected together to form either star or delta and also
all the LV windings are connected together to form either star or delta.
31
APPLIED MEASURD INSULATION POLARIZATION
VOLTAGE ACROSS RESISTANCE (GΩ) INDEX (PI)
(V)
60 SECONDS 600
SECONDS
32
4.6 WINDING RESISTANCE TEST OF THE TRANSFORMER:
Winding resistance measurements are an important diagnostic tool for assessing possible
damage to transformers resulting from poor design, assembly, handling, unfavourable
environments, overloading or poor maintenance. The main purpose of this test is to
check for gross differences between windings and for opens in the connections.
Measuring the resistance of the transformer winding assures that each circuit is
wiredproperly and that all connections are tight.
Winding resistance in transformers will change due to shorted turns, loose connections,
ordeteriorating contacts in tap changers. Regardless of the configuration, the resistance
measurements are normally made phase-phase and the readings are compared with each
otherto determine if they are acceptable.
PRINCIPLE OF TEST:
TEST OF EQUIPMENT:
PRECAUTIONS:
1. Charged battery of sufficient capacity or at least 10A shall be used with the
bridge to avoid error due to drop in battery voltage during measurements.
2.To reduce the high inductive effect, it is advisable to use a sufficient high
current to saturate the core.
33
3.The polarity of the core magnetization shall be kept same during all
resistance readings.
4.The voltage lead shall be independent of the current lead and shall be
connect as closely as possible to the terminal of the winding to be measured.
5.The current used shall not exceed 15% of the rated current of the winding
whose resistance is to be measured. Larger value may cause inaccuracy due to heating
of the winding and then by changing the temperature of resistance
TEST PROCEDURE:
3. The winding resistance meter consist of four clamps c+, c- (current injection cable)
and v+,v-(voltage drop measuring cable).c+,c- should be connected to the starting point of the
winding and c-,v- should be connected the ending point of the winding.
4. The current cable (c+,c-) should be outer or top side of the bushing stem and the
voltage cable (v+,v-)should be clamped at the inner or bottom part of the bushing stem with
respect to the current cable.
5. The applied current shall not exceed 15% of the rated current of the winding.
34
4.6.1 HV WINDING RESISTANCE
TAP NO MEASURED VALUES (mΩ) Ravg (mΩ) Ravg (mΩ)
1U - 1V 1V - 1W 1W - 1U @Tavg(° (75°C)
C)
1 83.28 83.41 83.18 83.29 96.56
2 81.41 81.52 81.41 81.45 94.42
3 79.65 79.74 79.60 79.66 92.35
4 (N) 77.69 77.84 77.72 77.75 90.14
5 75.69 75.67 75.64 75.67 87.72
6 73.84 73.90 73.75 73.83 85.59
7 71.87 71.74 71.79 71.80 83.24
2u - 2n 2v - 2n 2w - 2n @Tavg(° (mΩ)
C) (75°C)
NA 0.8967 0.8909 0.8823 0.8900 1.0317
TAP NO MEASURED VALUES (mΩ) Ravg (mΩ) Ravg (mΩ)
2u - 2v 2v - 2w 2w - 2u @Tavg(°C (75°C)
)
NA 1.6789 1.6682 1.6762 1.6744 1.9412
4.6.2.2 LV - 2(Dd0)
3u - 3v 3v - 3w 3w - 3u @Tavg(°C) (75°C)
35
Figure 4.6 WINDING RESISTANCE
36
CHAPTER 5
The purpose of the no load test is to measure no load loss and current at a specified
excitation voltage and a specified frequency.
PRINCIPLE OF TEST:
1. No load losses are those losses that are incident to the excitation of the
transformer. No load loss includes core loss, dielectricloss,copper loss in the winding
due to excitation and conductor loss due to circulating current in parallel winding.
These losses change with the excitation voltage.
2. No-load current is the current flow in any winding used to excite the
transformer when all other winding are open-circuited.it is generally expressed in
percent of the rated current of the winding.
LIST OF EQUIPMENT:
PRECAUTIONS:
2. Air release the bushing, turrents, transformer tank, and OLTC tank.
37
6.Test should be performed before the impulse test in order to avoid
reading errors.
TEST PROCEDURE:
1. Supply the rated voltage at rated frequency to one winding with the other
windings open circuited.
3. note down the R.M.S voltage & mean voltage, current, watts parameter and
frequency from power analyzer.
WINDING EXCITED HV
WINDING OPENED LV1 &
LV2
LV RATED 11
VOLTAGE (kV)
BASE KVA 8630
38
5.1.1 TRANSFORMER AT TAP NO - 4
39
5.2 DOUBLE VOLATGE DOUBLE FREQUENCY TEST:
In this test also called the dielectric test..this test are used to determine the
insulation strength of the transformer.
The test of transformer is intented to check the inter turn and line end insulation as
well as main insulation to earth and between winding
During the test double the rated voltage is applied to the transformer and double the
rated frequency is applied (100Hz).
PRINCIPLE OF TEST:
In alternating voltage shall be applied to the winding terminals of the transformer. The
from voltage shall be as nearly as possible sinusoidal and its frequency will be above rated
frequency for avoid excess magnetizing current during test.
TEST OF EQUIPMENT:
Starter
Motor and generator system
Step up transformer
Power analyser
Digital multimeter
Stop watch
Excitation system
PRECAUTIONS:
40
TEST PROCEDURE:
3. The test voltage will be much higher then the transformers rated
voltage, the test frequency should not be less then the twice the rated
frequency value, in order to avoid saturation of transformer core.
5. The test shall start with a voltage lower than 1/3 the full test voltage
and it shall be quickely increased up to desired value.
8. For the frequency above twice the rated frequency time duration of
the test shall be 120* Rated frequency/ Test frequency, but not less
then 15s.
9. At the end of the test, the voltage shall be reduced rapidly to less then
one third of the test value before switching off.
In this test also called High voltage test of the transformer ,and RMS voltage applied
to the HV and LV winding depend upon the insulation class of the transformer as per Indian
standard.
During the test high voltage winding and low voltage winding are shored separately.
when voltage applied to the HV side winding means another LV winding is earth due to the
safety of transformer.
The separate source test is more important in dielectric test, dielectric test is to
demonstrate that the transformer.
PRINCIPLE OF TEST:
A separate source voltage will be made with single phase alternating voltage as nearly
as possible sine wave from and not less than 80% of rated frequency for 60 sec.
LIST OF EQUIPMENT:
Auto transformer
2.High voltage transformer
42
Leakage tester
Power analyser
PRECAUTIONS:
2. Air release the bushings ,turrets ,transformer tanks , and OLTC tank.
TEST PROCEDURE:
1. The line terminals of the winding under test are connected together
and appropriate test voltage as nearly as possible to the sine wave form
and of any frequency not less than 80% of rated frequency as mentioned
in the standards is applied to them,
2. While the order windings and tank are connected together to earth.
The duration of the test shall be 60 seconds. after the completion of the
test, transformer shall be discharged.
44
5.4 SHORT CIRCUIT IMPEDANCE AND LOAD LOSS TEST OF THE
TRANSFORMER:
The load loss of a transformer are those losses incident to a specified load carried by
the transformer.
Load loss indicated I^2R loss in the winding due to load current and stray losses due
to eddy currents induced by leakage flux in winding, core lamps,magnetic shield,tank walls
and other conducting parts.
Impedence voltage is measured during the load loss test by measured the voltage
requires to circulate test current in windings.
PRINCIPLE OF TEST:
The short circuit impedance and load loss for a pair of winding shall be
measured at rated frequency with approximately sinusoidal voltage applied to the
terminal of one winding, with the terminal of the other winding short circuited, and
with possible other windings open circuited. The supplied current should be equal to
the relevant rated current (tapping current) but shall not be less than 50% thereof, the
measurement shall be performed quickly so that temperature rise do not causes
significant errors.
LIST OF EQUIPMENT:
Auto transformer
Step up transformer
Current transformer
Potential transformer
Power analyser
Capacitor ban
PRECAUTIONS:
45
3. Ensure dimmer is zero before switch on the panel.
TEST PROCEDURE:
2. Conduct the test any current from 50% to 100% of the rated current
in 226.5A and 452.9A.
4. Tempertaure of the winding shall be taken before and after the load
loss measurement.
5. Note down the corresponding voltage, current and losses from power
analyser or wattmeter method.
7. If the tapping ranges are more than 5%, measurement carried out at
rated tapping and external tapping.
8. Operate the tap changer +/- two steps 10 cycle from the bidirectional
tap during load loss measurement.
Where
46
I test = Test current
Fr = Rated frequency
Ft = Test frequency
WINDING SHORTED LV 1 +
LV 2
WINDING EXCITED HV
47
5.4.1 MEASURING PARAMETER:
TAP NO AVERAG AVERAGE AVERAGE FREQUENCY TOTAL
ECURREN PHASE LINE (Hz) POWER
T VOLTAGE VOLTAGE (KW
(A) (V) (V)
1 421.55 593.68 1028.25 50.060 52.31
4 (N) 452.62 561.47 972.46 50.031 54.72
7 489.56 546.20 946.01 50.073 59.24
48
5.5 TAN DELTA TEST FOR BUSHING:
PRINCIPLE OF TEST:
Capacitance and tan delta are determined by using schering bridge. The
dissipation factor is the ratio of the resistive current to the capacitive curtrent flowing
through the insulation on application of sinusoidal voltage under prescribed condition.
The capacitance values are relatively independent of temperature and prevailing
atmospheric condition.
TEST EQUIPMENT:
PRECAUTIONS:
1. The bushing terminal and test cap under test shall be thoroughly cleaned
with dry cloth to avoid surface leakage current.
2. If the bushing are shorted together, the test caps of the bushing that are not
under measurement must be tightly closed.
TEST PROCEDURE:
49
2. Bushing dissipation factor and capacitance value are measured in
UST (Ungrounded specimen test) mode.
3. Apply the appreciate voltage (5000 & 10000 kv) to the bushing with
respect to the name plate detail and obtain the value of capacitance and
tan delta through automatic tan delta and capacitance analyser kit.
15 0.90
20 1.0
25 1.12
30 1.25
35 1.40
40 1.55
45 1.75
50 1.95
55 2.18
60 2.42
65 2.70
70 3.0
50
Where,
Fp20 =Fpt/k
Fp20 is the power factor corrected in 20℃
Fpt is the power factor measured at T
T is the test temperature ℃
K is the correction factor as per table
51
5.5 DETERMINATION OF CAPACITANCE AND DISSIPATION
FACTOR BETWEEN WINDING TO EARTH AND BETWEEN
WINDINGS
BDV test means Breakdown Voltage Test. It is done for checking the dielectric
strength of the oil of the Transformer. Dielectric strength means the maximum capacity to
withstand voltage of insulating oil. This test shows the dielectric strength of Transformer oil.
TEST EQUIPMENT:
PRECAUTIONS:
1. Before using JY6611 transformer oil breakdown voltage test, the tester shell
should be reliably grounded.
52
2. Check the distance between the electrodes. Rinse the electrode surface with
a qualified transformer oil.
3. When collecting transformer oil and oil samples, wipe the sampling valve
and slowly open it. First flush the test cup 2-3 times and then take the oil sample.
4. When placing or removing the oil cup, it should be done under the
condition of power off.
5. When placing or removing the oil cup, it should be done under the
condition of power off.
6. The speed of step-up of oil tester should not be too fast, about 3000V/s is
appropriate. The number of tests is 3 to 5 times. Each pressurization interval is 2 to 3
minutes. The voltage must be reduced to zero before the voltage is turned off.
TEST PROCEDURE:
1. The transformer oil is filled in the vessel of the testing device. Two
standard-compliant test electrodes with a typical clearance of 2.5 mm are
surrounded by the dielectric oil.
4. An instant after ignition of the arc, the test voltage is switched off
automatically by the testing device. Ultra-fast switch off is highly desirable, as
the carbonisation due to the electric arc must be limited to keep the additional
pollution as low as possible.
5.The transformer oil testing device measures and reports the root mean square
value of the breakdown voltage.
53
6. After the transformer oil test is completed, the insulation oil is stirred
automatically and the test sequence is performed repeatedly: typically, 5 repetitions,
depending on the standard.
54
Figure 5.6 OIL BDV TEST
55
CHAPTER 6
CONCLUSION
The project is discussing a method to testing of transformer in furnace used in metal melting
industry. The testing of transformer is identification of fault and improve the quality of
transformer life time increased. The transformer is designed and implemented with the
hardware unit is complex and it is complexity to install is most time of the transformer. The
test of high voltage in oc is measured the no load loss current sc is reduced maintain the loss
adjustable the capacitor per phase. The low voltage test in measured ratio of turns reduced ±
0.5%
56
CHAPTER 7
REFERENCE
S. Brodeur and H. Dinh "A station service voltage transformer designed and tested to withstand
a severe internal arc fault" Proc. CIGRE Canada Conf. pp. 1-8 Sep. 2019.
IEEE C57.13.5-2019 "IEEE Standard for Performance and Test Requirements for Instrument
Transformers of a Nominal System Voltage of 115 kV" Feb. 2020
S. Wang S. Wang N. Zhang D. Yuan and H. Qiu "Calculation and analysis of mechanical
characteristics of transformer windings under short-circuit condition" IEEE Trans. Magn. vol.
55 no. 7 pp. 1-4 Jul. 2019
J. Cai L. Zhou J. Hu C. Zhang W. Liao and L. Guo "High-accuracy localisation method for PD
in transformers" IET Sci. Meas. Technol. vol. 14 no. 1 pp. 104-110 Jan. 2020
57