OPSS - Muni 310 Nov17 Construction Specification For Hot Mix Asphalt

Download as pdf or txt
Download as pdf or txt
You are on page 1of 30

ONTARIO OPSS.

MUNI 310
PROVINCIAL November 2017
STANDARD
SPECIFICATION

CONSTRUCTION SPECIFICATION FOR


HOT MIX ASPHALT

TABLE OF CONTENTS

310.01 SCOPE

310.02 REFERENCES

310.03 DEFINITIONS

310.04 DESIGN AND SUBMISSION REQUIREMENTS - Not Used

310.05 MATERIALS

310.06 EQUIPMENT

310.07 CONSTRUCTION

310.08 QUALITY ASSURANCE

310.09 MEASUREMENT FOR PAYMENT

310.10 BASIS OF PAYMENT

APPENDICES

310-A Commentary
310-B Supplemental Requirements for Using the MTO Performance Graded
Asphalt Cement (PGAC) Price Index in Municipal Contracts
310-C Supplemental Requirements for Using Warm Mix Asphalt in Municipal
Contracts

310.01 SCOPE

This specification covers the requirements for the placement and compaction of hot mix asphalt designed
using the Marshall or Superpave methods.

310.01.01 Specification Significance and Use

This specification is written as a municipal-oriented specification. Municipal-oriented specifications are


developed to reflect the administration, testing, and payment policies, procedures, and practices of many
municipalities in Ontario.

Use of this specification or any other specification shall be according to the Contract Documents.

November 2017 Page 1 of 30 OPSS.MUNI 310


310.01.02 Appendices Significance and Use

Appendices are not for use in provincial contracts as they are developed for municipal use, and then, only
when invoked by the Owner.

Appendices are developed for the Owner’s use only.

Inclusion of an appendix as part of the Contract Documents is solely at the discretion of the Owner.
Appendices are not a mandatory part of this specification and only become part of the Contract Documents
as the Owner invokes them.

Invoking a particular appendix does not obligate an Owner to use all available appendices. Only invoked
appendices form part of the Contract Documents.

The decision to use any appendix is determined by an Owner after considering their contract requirements
and their administrative, payment, and testing procedures, policies, and practices. Depending on these
considerations, an Owner may not wish to invoke some or any of the available appendices.

310.02 REFERENCES

When the Contract Documents indicate that municipal-oriented specifications are to be used and there is a
municipal-oriented specification of the same number as those listed below, references within this
specification to an OPSS shall be deemed to mean OPSS.MUNI, unless use of a provincial-oriented
specification is specified in the Contract Documents. When there is not a corresponding municipal-oriented
specification, the references below shall be considered to be the OPSS listed, unless use of a provincial-
oriented specification is specified in the Contract Documents.

This specification refers to the following standards, specifications, or publications:

Ontario Provincial Standard Specifications, Construction

OPSS 914 Waterproofing Bridge Deck with Hot Applied Asphalt Membrane

Ontario Provincial Standard Specifications, Material

OPSS 1003 Aggregates - Hot Mix Asphalt


OPSS 1101 Performance Graded Asphalt Cement
OPSS 1103 Emulsified Asphalt
OPSS 1150 Hot Mix Asphalt
OPSS 1151 Superpave and Stone Mastic Asphalt Mixtures

Ontario Ministry of Transportation Publications

MTO Laboratory Testing Manual:


LS-261 Preparation of Marshall Specimens
LS-262 Bulk Relative Density of Compacted Bituminous Mixtures
LS-263 Resistance to Plastic Flow of Bituminous Mixtures Using Marshall Apparatus

November 2017 Page 2 of 30 OPSS.MUNI 310


LS-264 Theoretical Maximum Relative Density of Bituminous Paving Mixtures
LS-265 Percent Air Voids in Compacted Dense Bituminous Pavement Mixtures
LS-282 Quantitative Extraction of Asphalt Cement and Analysis of Extracted Aggregate from
Bituminous Paving Mixtures
LS-287 The Determination of Percent Compaction of Compacted Bituminous Paving Mixture (MRD
Method)
LS-292 Quantitative Determination of Asphalt Cement Content by Ignition and Analysis of
Remaining Aggregate from Bituminous Paving Mixtures
LS-306 Bulk Relative Density of Compacted Bituminous Mixtures Using Paraffin-Coated
Specimens

ASTM International

D 6752-17 Standard Test Method for Bulk Specific Gravity and Density of Compacted Bituminous
Mixtures Using Automatic Vacuum Sealing Method

American Association of State Highway and Transportation Officials (AASHTO)

M320-16 Standard Specification for Performance Graded Asphalt Binder


M323-13 Standard Specification for Superpave Volumetric Mix Design
T40-02(2012) Sampling Bituminous Materials
T166-13 Bulk Specific Gravity of Compacted Bituminous Mixtures Using Saturated Surface-Dry
Specimens
T209-12 Theoretical Maximum Specific Gravity and Density of Bituminous Paving Mixtures
T275-07 Bulk Specific Gravity of Compacted Bituminous Mixtures Using Paraffin-Coated
Specimens

310.03 DEFINITIONS

For the purpose of this specification, the following definitions apply:

AMRL means the AASHTO Materials Reference Laboratory.

Anti-Stripping Treatment means a treatment used to minimize stripping of asphalt cement from HMA
aggregates as defined in OPSS 1151.

Attribute means one of the following: Designated Large Sieve (DLS), 4.75 mm sieve, 600 µm sieve, 75 µm
sieve, asphalt cement content, air voids, or compaction.

Binder Course means a HMA course between a surface course and either a granular base course or
stabilized base course, an existing pavement, or another HMA binder course.

CCIL means the Canadian Council of Independent Laboratories.

Designated Large Sieve (DLS) means the sieve size specifically designated for each mix type for
gradation testing according to Table 1.

Draindown means that portion of stone mastic asphalt or stone matrix asphalt (SMA) mix, fines, and
asphalt cement that separates and flows downwards through the mix.

Fat Spot means an area of pavement substantially blacker than the surrounding pavement.

Hot Mix Asphalt (HMA) means hot mixed, hot laid asphaltic concrete. The terms are used interchangeably.
HMA may include recycled or specialty mixes.

Hot Mix Asphalt Miscellaneous means HMA that is placed in areas other than the roadway, as specified
in the Contract Documents.

November 2017 Page 3 of 30 OPSS.MUNI 310


Hot Mix Asphalt Padding means an HMA layer used for correcting crossfall and profile deficiencies in the
existing pavement before placing the levelling, binder, or surface course.

Hot Mix Asphalt Patching means an HMA surface course placed over localized areas of distressed
pavement, generally for the purpose of improving strength, rideability, or safety.

Job-Mix Formula (JMF) means the percentage passing on each designated sieve of the total mass of
aggregate and the amount of asphalt cement as a percentage by mass of the mix that are based on
specified mix design procedures that when mixed result in an HMA that is according to this specification.

Joint means a vertical contact between a new HMA pavement course and any HMA pavement or any rigid
object that exists at the time the HMA is laid.

Levelling Course means an HMA course of variable thickness used to eliminate transverse and
longitudinal irregularities on an existing surface prior to placing an HMA binder or surface course.

Lot means a specific quantity of material or a specific amount of construction normally from a single source
and produced by the same process.

Mix Properties means the percent passing the DLS, 4.75 mm sieve, 600 µm sieve, and 75 µm sieve; the
asphalt cement content; and the air voids.

Paving in Echelon means two or more pavers are used to pave multiple adjacent lanes simultaneously.

Performance Graded Asphalt Cement (PGAC) means asphalt cement that is produced from petroleum
residue, either with or without the addition of non-particulate modifiers, according to AASHTO M320.

Protection Board means a durable panel specifically designed to provide an interface protection barrier
between the HMA and the asphalt waterproofing membrane.

Quality Assurance (QA) means a system or series of activities carried out by the Owner to ensure that
materials received from the Contractor meet the specified requirements.

Quality Control (QC) means a system or series of activities carried out by the Contractor to ensure that
materials supplied to the Owner meet the specified requirements.

Random Sample means a sample from a location chosen by the Contract Administrator based on random
numbers such that any portion of a lot or sublot has an equal probability of being selected.

Range means the numerical difference between the maximum and minimum test results within a lot.

Reclaimed Asphalt Pavement (RAP) means the processed HMA material that is recovered by partial or
full-depth removal.

Referee Testing means testing by an independent laboratory selected by the Owner and acceptable to the
Contractor, the results of which are used for resolving differences between QC and QA testing.

Screed means the unit of the paver that strikes off and imparts initial compaction to the HMA.

Segregation means a condition of the pavement characterized by areas with comparatively coarser or finer
texture than that of the surrounding pavement.

Southern Ontario means that area of Ontario south of a line joining Waubaushene, Severn Bridge,
Bancroft, and Ottawa.

Stone Mastic Asphalt or Stone Matrix Asphalt (SMA) means HMA consisting of a gap graded, stone-
on-stone coarse aggregate skeleton with an asphalt cement-rich mortar.

November 2017 Page 4 of 30 OPSS.MUNI 310


Sublot means approximately equal divisions or portions of a lot.

Superpave means the method for specifying material components and asphalt mix design using the
Superpave gyratory compactor (SGC).

Surface Course means an HMA wearing course of any flexible or composite pavement.

Vertical Surface means all edges of concrete curbs, catch basins and other appurtenances, longitudinal
joints, and transverse joints for application of tack coat.

310.05 MATERIALS

310.05.01 Hot Mix Asphalt

The materials used in the production of the HMA shall be according to OPSS 1150 for Marshall mixes and
OPSS 1151 for Superpave and SMA mixes.

310.05.02 Tack Coat Material

Tack coat shall consist of SS-1 or SS-1HH emulsified asphalt diluted with an equal volume of water. The
undiluted material shall be according to OPSS 1103.

The use of an alternate product may be permitted at the Contractor’s request, provided that such a request
is submitted in writing to the Contract Administrator a minimum of 14 Days prior to the intended use of the
alternate product. The Contractor’s proposal shall include, but not be limited to, the following:

a) The reasons for the use of the alternate material.

b) Material Safety Data Sheets and any other information for the safe handling, transportation, and storage
of the product.

c) Testing protocols to be used in confirming the properties of the material.

d) Typical test results.

e) Required application rates.

f) Cost implications for the use of the alternate product.

The Contract Administrator shall review this proposal and respond in writing within 7 Days of receiving it,
either accepting the use of the alternate product or not accepting its use with reasons. The alternate product
shall not be used until permission has been granted in writing by the Contract Administrator.

310.06 EQUIPMENT

310.06.01 Tack Coat Distributors

For main lane paving, tack coat shall be applied using self-propelled or tow-along pressure distributors
capable of applying the product at the specified rate and in a continuous and uniform manner both
longitudinally and transversely for the full lane width. The distributors shall be equipped with a volume-
metering system of sufficient sensitivity to measure the quantity of tack coat dispensed, measurable to
within four or five litres.

The use of a hand held pressure applicator is acceptable for tack coating protection board and small
irregularly shaped areas such as tapers.

November 2017 Page 5 of 30 OPSS.MUNI 310


310.06.02 Paving Equipment

Asphalt pavers shall be self-propelled and capable of laying a consistent satisfactory mat that is true to the
crossfall, profile, cross-section, and alignment specified in the Contract Documents. Pavers shall be
equipped with hoppers and distributing augers capable of placing the HMA evenly in front of the screeds.
Screeds shall be capable of being heated and being adjustable as to level and crown. Pavers shall be
capable of simultaneously placing the shoulder pavement and roadway pavement whether the shoulder
pavement is at the same or different crossfall from the roadway pavement.

In all cases, pavers shall be equipped with automatic longitudinal and transverse grade and slope controls
capable of being operated from either side of the paver. The longitudinal grade control shall be adjustable
for mat thickness in small increments, without the necessity of stopping the paver. The paver shall be
equipped to operate from a 12 m ski or floating beam, a 3 m ski, or a joint matching shoe. When the ski is
a flexible unit, it shall be equipped with a spring-tensioned wire extending between brackets fitted on and
slightly above each end of the ski. The sensing grid shall ride on the wire, not on the ski.

Plows or other edge ramping devices that are attached to or towed by the screed portion of the paver shall
not be permitted.

A 3 m straight edge shall be provided on each paver. The straight edge shall be made of metal with a level
recessed in its upper surface parallel to the lower edge.

310.06.03 Rollers

310.06.03.01 Classification of Rollers

Rollers shall be classified into categories as follows:

Class S Self-propelled steel-drum, tandem, or three-wheel rollers according to Table 2.

Class R Self-propelled pneumatic-tired rollers according to Table 3.

Class V Self-propelled vibratory rollers specifically designed for HMA compaction having either dual
vibratory rolls or a combination of vibratory roll and pneumatic tires with a contact area equal
to or greater than 70% of the roll width according to Table 4.

310.06.03.02 Requirements for Rollers

310.06.03.02.01 General

All rollers shall be capable of reversing without backlash.

The Contract Administrator shall be provided with the mass of the rollers and may require the weighing of
the rollers in his presence.

The rolls or drums shall be kept moist with water or non-petroleum based release agents to prevent
adhesion of HMA to them. Excess water or release agents shall not be permitted.

310.06.03.02.02 Steel-Drum Rollers

The drums of tandem steel-drum rollers shall not be less than 1.20 m in width.

310.06.03.02.03 Pneumatic-Tired Rollers

Pneumatic-tired rollers shall be constructed so that the wheels on either the front or back oscillate either
independently or in pairs. The wheels shall be mounted with smooth rubber tires. Tire inflation pressure
shall be a minimum of 350 kPa when the tires are cold. All tires shall have equal pressure. Skirts or

November 2017 Page 6 of 30 OPSS.MUNI 310


windbreaks shall be provided at all times to protect all tires from the cooling effects of atmospheric
conditions. Each roller shall be equipped with a suitable tire pressure gauge for checking tire inflation
pressure.

For SMA mixes, pneumatic-tired rollers are not permitted.

310.06.03.02.04 Vibratory Rollers

Vibratory rollers shall be according to the following requirements:

a) Frequency of vibrations of the vibratory roller shall be 2,200 vibrations per minute or greater.

b) Rollers shall be equipped with provision for automatic shut-off of vibrations before coming to a stop.

310.07 CONSTRUCTION

310.07.01 Quality Control

QC procedures shall be conducted to ensure the HMA meets the requirements of the Contract Documents.
The Contractor shall be responsible for the interpretation of the QC test results and the determination of
any action to be taken to ensure that all materials and work are according to the requirements of the
Contract Documents. QC documentation shall be made available to the Contract Administrator upon
request. Sampling and testing methods shall be included in the QC documentation.

A laboratory that has current CCIL Type B Certification or AMRL equivalent certification or other equivalent
certified laboratory acceptable to the Contract Administrator shall be used. Testing of the samples shall be
conducted under the direction and constant supervision of technicians certified to perform the QC tests
according to CCIL or equivalent certification.

310.07.02 Preparation of Foundation and Existing Pavement

310.07.02.01 Granular Grade

Prior to placing any course of HMA on a granular grade, a Class S roller of a minimum of 7 tonnes or an
equivalent Class V roller with a drum width of at least 1.2 m shall be used to finish roll the grade ahead of
the paver to ensure a compacted, smooth, and float-free surface. Any distortion that will impact the specified
thickness of the pavement to be placed shall be repaired.

310.07.02.02 Existing Pavement

Prior to placing any HMA, all HMA and concrete surfaces shall be clean of all loose, broken, and foreign
materials. Milled surfaces shall be swept with a power broom.

310.07.03 Tack Coat

310.07.03.01 Application of Tack Coat

Surfaces to be tack coated shall be free of standing water and contamination, such as mud, loose
aggregate, or debris.

Protection board shall be dry and clean when the tack coat is applied.

Tack coat shall be placed sufficiently ahead of the paving operation to allow for curing.

Paving and construction equipment shall not be permitted onto the tack coat until it has broken and set.

November 2017 Page 7 of 30 OPSS.MUNI 310


Traffic shall be prevented from travelling upon the tack coat.

Tack coat shall be applied to the following:

a) Protection board.

b) All pavement surfaces including, but not limited to, hot mix and Portland cement concrete.

c) Milled pavement surfaces.

d) Expanded asphalt surfaces.

e) Cold-in-place recycled surfaces.

Tack coat may also be applied to other surfaces as specified in the Contract Documents.

310.07.03.02 Tack Coat Rate of Application

The diluted emulsion shall be applied at the rate of 0.35 kg/m2 to all existing pavement surfaces, milled
pavement surfaces, expanded asphalt surfaces, and any binder course surface that has been left open to
traffic over at least one winter.

For cold-in-place recycled surfaces and new surfaces that have been paved in the same calendar year, the
rate of application shall be 0.20 kg/m2.

The rate of application on protection board shall be 0.50 kg/m2.

310.07.03.03 Tack Coating of Joints

Vertical surfaces at which joints are made shall be tack coated with a thin uniform and continuous coating
of tack coat material, except for longitudinal joints between lanes paved in echelon.

The joint between pavement lanes paved with an infrared joint heater shall not be painted.

310.07.04 Transportation of Hot Mix Asphalt

The HMA shall be transported from the asphalt plant to the work in leak proof truck boxes that have been
previously cleaned of all foreign materials. If required, truck boxes shall be lightly coated with a uniform
application of a non-petroleum based release agent. Truck boxes shall be drained after each application
and before loading. No release agents shall be used that can adversely affect the quality or performance
of the HMA. Release agents shall be used according to the proprietary requirements.

Each truck shall use a tarpaulin of sufficient size to completely cover the load at all times.

310.07.05 Sampling

310.07.05.01 Asphalt Cement

310.07.05.01.01 General

When specified in the Contract Documents, the Contractor shall obtain asphalt cement samples according
to OPSS 1101 for QA testing.

310.07.05.01.02 Frequency and Location

The asphalt cement sampling frequencies and locations shall be as specified in the Contract Documents.
A minimum of one sample shall be randomly chosen for each asphalt cement used on the Contract.

November 2017 Page 8 of 30 OPSS.MUNI 310


310.07.05.01.03 Labelling

Asphalt cement samples shall be labelled with the following:

a) Contract number.

b) Date (i.e., yyyy-mm-dd) and time of sampling.

c) Performance grade of the asphalt cement.

d) Supplier's name.

e) Refinery name.

f) Waybill number.

g) Tanker number.

h) Whether the sample was taken from a delivery tanker or from a storage tank at the plant.

i) Name and proportions of additives in the asphalt cement.

310.07.05.01.04 Delivery

Samples for the Owner shall be delivered within 4 hours of sampling to the location specified in the Contract
Documents.

310.07.05.02 Hot Mix Asphalt

310.07.05.02.01 General

The Contractor is responsible for obtaining QA and referee HMA samples using sample plates for Marshall
mixes and other methods approved by the Contract Administrator for Superpave and SMA mixes. The
Contractor may obtain a QC sample at the same location of the QA and referee samples. Samples shall
be taken in accordance with the Contract Documents under the direction and in the presence of the Contract
Administrator. Samples shall be placed in an appropriate container supplied by the Contractor. The
Contract Administrator may apply security seals to the samples prior to transportation.

310.07.05.02.02 Frequency and Location

The minimum frequency for sampling and testing shall be as specified in Table 6.

310.07.05.02.03 Labelling

HMA samples shall be labelled with the following:

a) Contract number.

b) Location of sampling.

c) Date (i.e., yyyy-mm-dd) and time of sampling.

d) Asphalt type.

November 2017 Page 9 of 30 OPSS.MUNI 310


310.07.05.02.04 Cores

When a coring and testing program is undertaken to resolve a dispute related to HMA compaction, the
Contractor shall be responsible for all traffic control required to carry out the coring, obtaining and labelling
the core samples, delivery of the samples to a mutually agreed upon third part referee laboratory, and
repairing core sample holes.

Cores shall be 150 mm in diameter.

The minimum frequency of sampling and testing shall be as determined by the Contract Administrator.

Core samples shall be labelled with the following:

a) Contract number.

b) Location of core sample.

c) Date (i.e., yyyy-mm-dd) and time of sampling.

d) Asphalt type.

310.07.05.02.05 Delivery

All samples for the Owner shall be delivered within 4 hours of sampling to the location specified in the
Contract Documents.

310.07.05.03 Repair of Sampling Locations

HMA and compaction requirements for filling all sample holes shall be the same as the adjacent undisturbed
pavement. All sample holes shall be cleaned, dried, and filled and then compacted using a mechanical,
self-powered gas, electric, or air powered compactor immediately after sampling.

310.07.06 Placing Hot Mix Asphalt

310.07.06.01 General

Prior to roller compaction, obvious defects in the HMA material placed shall be corrected. Irregularities in
the alignment and grade along the outside edges shall be corrected.

A through lane paving course shall be completed prior to the placement of adjacent side roads, speed
change lanes, and other paved areas. For all courses, each adjacent lane shall be completed to
approximately the same location at the end of each day’s paving.

At the end of each completed portion and prior to opening the lanes to traffic, the completed sections of
HMA course shall be ramped transversely to the existing pavement to a maximum of 30H:1V. In all cases,
the ramps shall not form part of the permanent asphalt pavement and shall be removed prior to continuing
paving operations.

The temperature of the HMA prior to placement shall be within the temperature range that corresponds to
the PGAC manufacturer's recommended mix temperature.

The temperature of the HMA immediately after spreading and prior to initial rolling shall not be less than
120 °C.

310.07.06.02 Operational Constraints

Paving shall not be carried out if the roadbed is frozen.

November 2017 Page 10 of 30 OPSS.MUNI 310


The granular grade shall be free of standing water at the time of HMA placement.

The surface of a pavement upon which HMA is to be placed shall be dry at the time of HMA placement. An
HMA course shall not be placed on a previously laid course until a minimum 4 hours have elapsed, following
final compaction of the previous course, and the temperature of the previous course is 60 °C or less.

Binder courses shall not be placed unless the air temperature at the surface of the road is a minimum of
2 °C and rising.

For surface course, the air temperature at the surface of the road shall be at least 7 °C, except for SMA
and Superpave 12.5 FC2, the air temperature at the surface of the road shall be at least 12 °C.

Traffic shall be kept off the SMA surface until it has cooled below 60 °C.

310.07.07 Use of Paving Equipment

Levelling, binder, and surface courses shall be laid by means of mechanical self-propelled pavers.

Pavers working in echelon shall maintain a distance of less than 60 m between them.

The longitudinal alignment of the spreader shall be controlled by the use of a string line placed at each
outer edge of the pavement. The spreader shall be directed at all times by the string line and not by the
edge of the preceding course, except for the trailing paver when paving in echelon.

The automatic screed controls and all compaction aids on the paver shall be operational while the HMA is
being placed, except when placing padding, a levelling course, or paving around appurtenances.

Single pavers or the lead paver when paving in echelon shall be controlled as to longitudinal grade by a
12 m ski or floating beam.

The pavers shall operate continuously at a uniform speed necessary to match the output of the HMA plant.
However, in no case shall the speed of the paver exceed 18 m/min.

If the HMA for surface course paving comes from more than one mixing plant, the HMA from each plant
shall be placed by a separate paver.

310.07.08 Widenings and Irregular Sections

When it is necessary to hand-spread the HMA in sections adjacent to machine-laid areas, such hand-
spreading shall be carried out concurrently with machine-laying operations.

a) Widenings

The HMA shall be placed in widenings so that the top of the compacted HMA is flush with the top of the
existing pavement. When stepped joints are specified in the Contract Documents, the layers placed in the
widening shall be placed to the top of each step in separate operations.

HMA shall be placed in the widening using equipment specially designed for this purpose.

b) Irregular Sections

In turn-outs, driveways, and other irregular sections where it is impractical to use machine methods to
spread and finish the binder, levelling, or surface courses, the Contractor shall use other spreading
equipment or shall spread the HMA by hand.

November 2017 Page 11 of 30 OPSS.MUNI 310


310.07.09 Hot Mix Asphalt Padding

HMA padding shall be carried out as specified in the Contract Documents.

310.07.10 Hot Mix Asphalt Patching

Prior to HMA patching, temporary patching material shall be removed from the locations designated for
such removal in the Contract Documents. The resulting areas shall be filled and compacted with HMA, as
specified in the Contract Documents.

The HMA patching material shall be machine laid to the required thickness, grade, and crossfall.

Transverse and longitudinal joints between the existing pavement and the patch shall be perpendicular butt
joints formed by a milling process or keyed in, as specified in the Contract Documents.

310.07.11 Longitudinal and Transverse Joints

310.07.11.01 General

All joints shall be made to ensure a full face bond and a smooth riding surface.

Longitudinal and transverse butt or stepped joints between the new HMA pavement and the existing
pavement shall be constructed by trimming the existing pavement edge to a straight clean vertical surface
of at least 40 mm.

All dirt or other foreign material and all loose material shall be removed from all vertical surfaces.

When matching a compacted joint, the depth of the uncompacted mat shall be set to allow for compaction.
The paver screed shall overlap the adjoining mat by no more than 50 mm.

310.07.11.02 Longitudinal Joints

Longitudinal joints shall be properly set up, with the back of a rake or lute, at the proper height and grade
prior to rolling, unless the Contractor has demonstrated acceptable joint construction.

For multiple lifts of HMA, the width of subsequent courses shall be staggered to an offset of 150 to 300 mm
so that longitudinal joints do not coincide. This shall also apply to the joint between through lanes and
speed change lanes and other similar longitudinal joints. The longitudinal joints in the surface course shall
correspond to the demarcation between the driving lanes, speed change lanes, and tapers specified in the
Contract Documents.

During surface course paving, excess material shall not be cast onto the surface of the freshly laid mat.

When resurfacing against a rigid object, a butt joint shall be constructed by milling the existing pavement
to provide an exposed vertical surface of at least 25 mm at the face of the rigid object. The milling shall be
feathered out to zero over a minimum length of 1.25 m from and parallel to the exposed face of the rigid
object providing a minimum of 40 mm of resurfacing material over the area of removal.

310.07.11.03 Transverse Joints

The paver shall not move more than 15 m from any transverse joint until that joint has been rolled and
checked with a straight edge. If the joint is not satisfactory, it shall be corrected immediately before the
paver is allowed to proceed.

Joints between HMA pavement laid under this Contract and existing HMA courses not laid under this
Contract shall be constructed as follows:

November 2017 Page 12 of 30 OPSS.MUNI 310


a) When a binder course is placed flush against an existing HMA pavement and a butt joint is to be made,
the existing pavement shall be trimmed back to form a straight vertical surface.

b) When a surface course is placed flush against an existing HMA pavement, a stepped joint shall be
prepared by removing the existing surface course to its full depth for a minimum length of 0.5 m and
the remaining face shall be trimmed to form a straight vertical surface.

c) When a binder course and surface course are not placed flush against an existing HMA pavement, the
binder course shall be feathered out and the surface course shall be butt jointed by removing the
existing surface course to a minimum depth of 40 mm and for a longitudinal distance not less than 3 m.

310.07.11.04 Paving on Bridge Decks

The temperature of the HMA immediately after spreading shall not be less than 115 oC. The temperature
of the HMA mat ahead of initial rolling shall be measured and recorded. Compaction shall be accomplished
using, as a minimum,

a) a Class S roller with a minimum mass of 9 tonnes and minimum mass of 4.5 kg per mm total roll width,
and

b) a Class R roller with a minimum mass of 18 tonnes and minimum mass of 2,500 kg per tire.

The operating speed of Class S rollers shall not exceed 5 km/h and shall be operated in a manner to avoid
undue displacement of the HMA. If Class V rollers are used, they shall be used in static mode. Rollers
shall operate with the drive wheel forward in the direction of paving.

The mixture shall be uniformly compacted as soon after placing as it can support the rollers without checking
or undue displacement. Rolling shall start longitudinally at the lower edge and proceed towards the higher
edge of the course, overlapping on successive passes. Alternate passes of the roller shall be staggered.

Passes by the Class R roller shall overlap previous passes. The roller shall be operated to prevent pick-
up of the HMA on the tires.

310.07.12 Compaction

310.07.12.01 Rolling

310.07.12.01.01 Static Rolling

Compaction shall be accomplished using the minimum combination number of rollers specified in Table 5.

The Contractor shall determine the correct sequence of rollers used for compacting in order to achieve
compaction requirements.

The operating speed of steel drum rollers shall not exceed 5 km/h and shall be operated in a manner to
avoid undue displacement of the mix. Rollers shall operate with the drive wheel forward in the direction of
paving.

Rolling procedures shall be as follows:

a) Breakdown Rolling

The mix shall be uniformly compacted as soon after placing as it can support the roller without checking or
undue displacement. Rolling shall start longitudinally at the lower edge and proceed towards the higher
edge of the course, overlapping on successive passes. Alternate passes of the roller shall be staggered.

b) Intermediate Rolling

November 2017 Page 13 of 30 OPSS.MUNI 310


The intermediate roller shall follow the breakdown roller as closely as possible. Passes shall overlap
previous passes. The roller shall be operated to prevent pick-up of the HMA on the tires.

c) Finish Rolling

Finish rolling shall start longitudinally at the higher edge and proceed towards the lower edge.

310.07.12.01.02 Vibratory Rolling

For all HMA being compacted on bridge decks, vibratory rollers shall be operated in static mode.

310.07.12.02 Compaction of Irregular Sections and Inaccessible Areas

At all places not accessible to rollers, the mix shall be compacted by mechanical, self-powered gas, electric,
or air powered equipment.

310.07.13 Tolerances

After final compaction, each course shall be smooth and true to the established crown and grade. HMA
binder and surface courses shall be free from deviations exceeding 6 mm and 3 mm, respectively, as
measured in any direction with a 3 m straight edge.

310.07.14 Surface Appearance

Each course after final compaction shall be of uniform texture and shall be free of defects such as
segregation, fat spots, oil spills, and roller marks. Defective areas shall be removed and replaced with HMA
of the same type and compacted to the satisfaction of the Contract Administrator.

If the Contractor’s actions fail to prevent continued medium or severe segregation regardless of cause, the
Contract Administrator may instruct the Contractor to cease paving until the problem has been corrected.

From the time that the Contractor receives notification of midlane segregation, the Contractor shall be
allowed a maximum of 500 tonnes of mix to be placed on the Contract, in order to demonstrate the
effectiveness of any repairs and adjustments that have been made to a defective paver. The Contractor
shall demonstrate his repairs or adjustments or both to the Contract Administrator. If the Contractor is
unable to eliminate midlane segregation to the satisfaction of the Contract Administrator by making repairs
or adjustments to the paver within the allowable 500 tonnes of HMA, then the Contractor shall discontinue
the use of that paver.

310.07.15 Management of Excess Material

Management of excess material shall be according to the Contract Documents.

310.08 QUALITY ASSURANCE

310.08.01 General

The Contract Administrator is responsible for conducting QA procedures for all HMA aggregates, asphalt
cement, and compaction to meet the requirements of the Contract Documents. QA HMA testing shall be
conducted at a frequency specified in Table 6 or as specified in the Contract Documents.

Acceptance of hot mix aggregates and asphalt cement shall be according to OPSS 1003 and OPSS 1101,
respectively.

November 2017 Page 14 of 30 OPSS.MUNI 310


All QA testing shall be completed in a certified laboratory that is CCIL Type B and C, or AMRL accredited,
or equivalent. Testing of the samples shall be conducted under the direction and constant supervision of
technicians certified to perform the QA tests.

The Contract Administrator may reject visually defective HMA areas based on, but not limited to the
following defects: flushing, bleeding, segregation, fat spot, surface damage, and surface contamination.
Such defective HMA or areas shall be removed from the work and replaced with acceptable HMA.

When the HMA fails to consistently meet the requirements of the Contract Documents, the Contract
Administrator may refuse further material until the mix properties are verified for compliance by one of the
following methods:

a) For Marshall mixes, samples shall be used to determine compliance to asphalt cement content,
aggregate gradation, air voids, flow, voids in mineral aggregate, and stability requirements.

b) For Superpave mixes, samples shall be used to determine compliance to asphalt cement content,
aggregate gradation, and Superpave mix properties.

310.08.02 Acceptance of Tack Coat Application Rate

Tack coat application shall be visually uniform. Areas of insufficient or non-uniform tack coat coverage
shall be re-sprayed. When tack coating is performed using hand held devices, the visual appearance of
such areas shall be consistent with the adjacent areas of machine applied material.

310.08.03 Acceptance of Joint Painting Application Rate

The joint painting shall provide a thin, uniform, and continuous coating to the satisfaction of the Contract
Administrator.

310.08.04 Aggregate Gradation and Asphalt Cement Content Acceptance

Aggregate gradation and asphalt cement content test results for HMA samples based on LS-282 and
LS-292 shall meet the JMF tolerance requirements as specified in Table 7.

If the HMA is deemed borderline for aggregate gradation or asphalt cement content according to Table 7,
the Contractor shall be notified in writing by the Contract Administrator and shall take immediate corrective
action through process control at the HMA plant. A total of three borderline test results for the same
attributes representing up to 5,000 tonnes of HMA production shall result in the work being deemed
rejectable.

If the HMA is deemed rejectable according to Table 7, both the Contract Administrator and the Contractor
shall review, agree, and identify the limits of rejected HMA that has been placed. Referee samples within
the limits of the affected area shall be delivered by the Contractor to a mutually agreed upon third party
referee laboratory to verify aggregate gradation or asphalt cement content or both. When the results from
the referee samples are deemed rejectable according to Table 7, the HMA pavement shall be removed and
replaced with acceptable HMA pavement. Alternatively, the Contract Administrator may accept a
guaranteed maintenance bond, an increased maintenance period, or a negotiated price adjustment.

310.08.05 Hot Mix Asphalt Properties Acceptance

Marshall test results for hot mix samples based on LS test procedures shall meet the requirements specified
in Table 8. The production air voids for all HMA mixes shall be evaluated according to Table 9.

If the HMA is borderline for air voids as specified in Table 9, the Contractor shall be notified in writing by
the Contract Administrator and shall take immediate corrective action through process control at the HMA
plant.

November 2017 Page 15 of 30 OPSS.MUNI 310


If the HMA does not meet Table 8 minimum requirements for Marshall stability or Marshall flow or is deemed
rejectable for air voids according to Table 9, both the Contract Administrator and Contractor shall review,
agree, and identify the limits of rejected HMA that has been placed. Referee samples within the limits of
the affected area shall be delivered by the Contractor to a mutually agreed upon third party referee
laboratory to verify Marshall test or air void results or both. When the results from the referee samples do
not meet Table 8 minimum requirements or are deemed rejectable according to Table 9, the HMA pavement
shall be removed and replaced with acceptable HMA pavement. Alternatively, the Contract Administrator
may accept a guaranteed maintenance bond, an increased maintenance period, or a negotiated price
adjustment.

310.08.06 Compaction Requirements

310.08.06.01 General

Compaction testing of the placed HMA shall meet the requirements specified in Table 10.

Nuclear density test gauge results shall be used to assess in-place compaction. When compaction test
results do not meet the minimum percent compaction specified in Table 10, the Contractor shall be notified
in writing and either the affected area of HMA pavement shall be removed and replaced with acceptable
HMA pavement or, in the case of a dispute, the Contractor or the Owner may request that a coring and
testing program be undertaken to verify compaction percentage of the mix. The cores shall be provided to
the Owner and compaction shall be determined according to the Compaction Determined by Core Density
Testing clause using a mutually agreed upon third party referee laboratory. When compaction results from
core densities do not meet the minimum percent compaction specified in Table 10, the HMA pavement
shall be removed and replaced with acceptable HMA pavement.

310.08.06.02 Compaction Determined by Nuclear Density Gauge

Compaction testing shall be conducted randomly at a minimum frequency of every 100 m per lane or 150 m2
area.

310.08.06.02.01 Marshall Hot Mix Asphalt

Percent compaction shall be determined by comparing the nuclear density in situ Bulk Relative Density
(BRD) according to LS-262 to the average plant produced HMA Maximum Relative Density (MRD)
according to LS-264.

310.08.06.02.02 Superpave Hot Mix Asphalt

Percent compaction shall be determined by comparing the nuclear density in situ BRD to the average plant
produced HMA MRD both according to AASHTO T209.

310.08.06.03 Compaction Determined by Core Density Testing

310.08.06.03.01 Marshall Hot Mix Asphalt

Density testing of the cores shall be in accordance with LS-287. Percent compaction shall be determined
by comparing the core BRD according to LS-262 to the average MRD according to LS-264 of the plant
produced HMA.

310.08.06.03.02 Superpave Hot Mix Asphalt

Density testing of the cores shall be according to AASHTO T166. If the percent water absorbed by the
specimen is found to exceed 2% by volume as described in AASHTO T166, then the bulk specific gravity
shall be according to AASHTO T275, LS-306, or ASTM D 6752. Percent compaction shall be determined
by comparing the core BRD to the average MRD both according to AASHTO T209 of the plant produced
HMA.

November 2017 Page 16 of 30 OPSS.MUNI 310


310.09 MEASUREMENT FOR PAYMENT

310.09.01 Actual Measurement

310.09.01.01 Hot Mix Asphalt

Measurement of each type of HMA shall be by mass in tonnes or by area in square metres as specified in
the Contract Documents.

310.09.01.01.01 By Mass

When payment is by mass:

All HMA that is delivered to the Work site shall be accompanied by a truck weigh ticket showing the truck
number, type of hot mix, Contract number, truck time in and out of the hot mix plant, tare mass to the
nearest 50 kg, gross mass to the nearest 50 kg, net mass in kg, and the driver’s signature.

The truck weigh ticket shall be printed by an electronic printer interfaced with the truck scale readout and
capable of recording the tare mass, gross mass, and net mass. The tare mass for the truck shall include
the vehicle, operator, fuel, spare tire, etc. The tare mass of the truck shall be taken at least once per shift.

The Contractor shall be responsible for ensuring that the truck weigh ticket or delivery ticket for each load
is handed to the Contract Administrator inspecting the HMA paving operation at the time the delivery truck
unloads at the paving site. The Contract Administrator may not accept delivery tickets that are not submitted
at the proper time or are submitted in groups after the delivery trucks have left the paving site.

The Contractor shall permit the Contract Administrator to make random checks of the gross mass and tare
mass of trucks hauling HMA by requiring them to be driven over an independent certified scale.

310.09.01.01.02 By Area

When payment is by area:

Random pavement cores, maximum 100 mm in diameter, shall be taken to verify the actual thickness
approximately every 100 m along the length of the roadway or 300 m 2 of pavement surface area. The
average thickness for a core shall be based on the measurement from each quadrant of the core. The
average thickness for the area shall be determined by averaging the core thicknesses.

When the average thickness is more than or equal to 95% of the specified thickness, the payment area
shall be the total surface area of the HMA type laid for the course.

When the average thickness is less than 95% of the specified thickness, the surface area for payment
purposes shall be calculated as follows:

Payment area = actual area x average thickness


specified thickness

310.09.01.02 Tack Coat

Measurement for tack coat shall be of the area applied in square metres.

310.09.01.03 Hot Mix Asphalt Miscellaneous

Measurement for HMA miscellaneous shall be of the area in square metres, regardless of the number of
lifts placed.

November 2017 Page 17 of 30 OPSS.MUNI 310


310.09.02 Plan Quantity Measurement

When measurement is by Plan Quantity, such measurement shall be based on the units shown in the
clauses under Actual Measurement.

310.10 BASIS OF PAYMENT

310.10.01 Hot Mix HL (“type”) - Item


Hot Mix HL (“type”) Patching - Item
Heavy Duty Binder Course Mix - Item
Medium Duty Binder Course Mix - Item
Dense Friction Course Mix - Item
Superpave (“type”) - Item
Superpave (“type”) Patching - Item
SMA - Item

Payment at the Contract price for the above tender items shall be full compensation for all labour,
Equipment, and Material to do the work.

Removal and replacement of the following shall be at no extra cost to the Owner:

a) Defective areas of HMA, including but not limited to those due to flushing, bleeding, segregation, fat
spots, surface damage, and surface contamination.

b) HMA that does not meet the requirements of the Contract Documents.

Referee testing undertaken to resolve a dispute shall be at no extra cost to the Owner if the referee test
results confirm that the HMA does not meet the minimum requirements of Table 8 or is deemed borderline
or rejectable according to Table 9.

A coring, testing, and traffic control program undertaken to resolve a dispute shall be at no extra cost to the
Owner if the mix compaction is confirmed to be below the minimum specified compaction.

No additional payment shall be made for any delays or costs attributed to verification of the gross mass and
tare mass of trucks requested by the Contract Administrator.

310.10.02 Hot Mix Asphalt Miscellaneous - Item

Payment at the Contract price for the above tender item shall be full compensation for all labour, Equipment,
and Material to do the work.

310.10.03 Tack Coat - Item

Payment at the Contract price for the above tender item shall be full compensation for all labour, Equipment,
and Material to do the work.

Payment for the tack coating of protection board shall be included under the Tack Coat tender item.

Payment for the tack coating of concrete surfaces completed in association with bridge deck waterproofing
shall be included in the bridge deck waterproofing item according to OPSS 914.

November 2017 Page 18 of 30 OPSS.MUNI 310


TABLE 1
Designated Large Sieve for Mix Types
Mix Type Designated Large Sieve
mm
Superpave 25.0 19.0

Superpave 19.0 12.5


Superpave 12.5, 12.5 FC1, and 12.5 FC2,
9.5
HL 1, HL 3, HL 3F, HL 3HS, DFC, and SMA 12.5
Superpave 9.5 4.75

Superpave 4.75 2.36

HL 8, MDBC, and HDBC (Note 1) 16.0

HL 4 and HL 4F 13.2

HL 2 2.36

Note:

1. HDBC is also known as HL 8HS.

TABLE 2
Requirements for Class S Rollers
Roller Minimum Minimum Mass
Mass Per mm Total Roll Width
t kg
S1 7 3.5

S2 9 4.5

TABLE 3
Requirements for Class R Rollers
Roller Minimum Mass Minimum Mass Per Tire
t kg
R1 8 900

R2 18 2,500

R3 25 3,600

November 2017 Page 19 of 30 OPSS.MUNI 310


TABLE 4
Requirements for Class V Rollers
Minimum Static Mass
Roller Minimum Roll Minimum Roll
Per mm
Diameter Width
Total Roll/Tire Width
m m
kg

V1 1.00 1.40 2.0

V2 1.20 1.60 2.6

V3 1.40 1.90 2.9

TABLE 5
Maximum Production Rates Per Paver for Combinations of Rollers

Minimum Roller Combinations


Maximum Production
t/h
Southern Ontario All Ontario

S2 + R1 + S1 S2 + R2 + S1
120
V1 + R1 V1 + R2

V2 + R1 V1 + R3
135
V1 + R2 V2 + R2

S2 + 2 x R1 + S1 S2 + 2 x R2 + S1

150 S2 + R2 + S1
S2 + R3 + S1
V2 + R2

200 V3 + R2 V3 + R2

220 V3 + R3 V3 + R3

November 2017 Page 20 of 30 OPSS.MUNI 310


TABLE 6
Sampling and Testing Frequency of Hot Mix Asphalt
Quantity Per Day Minimum Frequency of Minimum Marshall Minimum Superpave
Per HMA Type Sampling and Testing Sampling Size Sampling Size
(Note 1)
kg kg

≤ 500 tonnes One sample

One sample per 500


> 500 and ≤ 1,500 tonnes 10 20
tonnes or part thereof
One sample per 500
> 1,500 tonnes tonnes (Note 2), minimum
of 3
Notes:

1. One additional 5 kg sample is required for SMA mixes to test for draindown.

2. The Contract Administrator may reduce the testing frequency for HMA that is consistently being
produced to meet the specification requirements.

TABLE 7
Tolerances for the Job-Mix Formula Aggregate Gradation and Asphalt Cement Content
Tolerances on the Job-Mix Formula
(Note 1)
Mix Attribute %
Acceptable Borderline Rejectable
DLS, 4.75 mm
< 5.0 5.0 to 7.5 > 7.5
Sieve size
Surface Course 600 µm sieve size < 3.5 3.5 to 5.0 > 5.0

75 µm sieve size < 2.0 2.0 to 3.0 > 3.0


DLS, 4.75 mm
< 7.0 7.0 to 10.0 > 10.0
sieve size
Binder and Levelling
600 µm sieve size < 4.5 4.5 to 6.0 > 6.0
Courses
75 µm sieve size < 2.0 2.0 to 3.0 > 3.0
Asphalt Cement
All Mixes < 0.30 0.30 to 0.50 > 0.50
Content
Note:

1. Tolerances on the job-mix formula apply as both plus and minus from the job-mix formula percent.

November 2017 Page 21 of 30 OPSS.MUNI 310


TABLE 8
Marshall Stability and Flow Properties for Hot Mix Asphalt Types
HL 1, HL 3, HL 3HS,
Production Properties DFC HL 2, HL 3F,
HL 4, HL 8, HDBC,
and Test Methods and HL 4F
and MDBC
Minimum Marshall Stability:
Newtons (N) at 60 °C, (Note 1) (Note 1) (Note 1)
LS-261, and LS-263
Marshall Flow at 3.5% Air Voids:
8.0 minimum 8.0 - 14.0 9.0 - 18.0
LS-261, and LS-263
Note:

1. Stability requirements shall be according to OPSS 1150.

TABLE 9
Air Void Criteria for Hot Mix Asphalt Types (LS-265)

Mix Acceptable Borderline Rejectable


% % %

DFC 2.5 to 4.5 2.0 to 2.4 and 4.6 to 5.0 < 2.0 and > 5.0

All Other Mixes 3.0 to 5.0 2.0 to 2.9 and 5.1 to 6.0 < 2.0 and > 6.0

TABLE 10
Minimum Pavement Compaction Based on Maximum Relative Density

Mix Minimum Compaction


%

HDBC, Superpave 19.0 and 25.0 91.0

All Other Mixes 92.0

November 2017 Page 22 of 30 OPSS.MUNI 310


Appendix 310-A, November 2017
FOR USE WHILE DESIGNING MUNICIPAL CONTRACTS

Note: This is a non-mandatory Commentary Appendix intended to provide information to a designer, during
the design stage of a contract, on the use of the OPS specification in a municipal contract. This
appendix does not form part of the standard specification. Actions and considerations discussed in
this appendix are for information purposes only and do not supersede an Owner’s design decisions
and methodology.

Designer Action/Considerations

The designer should be aware that excluded from the specification is recycled ratio and Owner specified
use of reclaimed asphalt pavement in hot mix asphalt (HMA).

The designer should specify the following in the Contract Documents:

- HMA crossfall, profile, cross-section, and alignment. (310.06.01)

- HMA type requirements. (310.07.01)

- Sampling frequencies and locations for asphalt cement. (310.07.05.01.02)

- Asphalt cement sample delivery location. (310.07.05.01.04)

- Quality assurance (QA) sample requirements. (310.07.05.02.01)

- HMA sample delivery location. (310.07.05.02.04)

- Stepped joints when required. (310.07.08)

- HMA padding requirements. (310.07.09)

- Temporary patching material removal locations. (310.07.10)

- Existing HMA patching locations requirements. (310.07.10)

- Butt joint forming method. (310.07.10)

- Lane demarcation. (310.07.11.02)

- QA HMA testing frequency if different than OPSS 310, Table 6. (310.08.01)

- Unit of measure for each HMA type. (310.09.01.01)

The designer should determine if the following is required and, if so, specify it in the Contract Documents:

- Tack coating of surface not listed in this specification and the tack coat application rate for that surface.
(310.07.03)

Application rates for tack coat may vary depending on surface characteristics. (310.07.03)

The designer may specify in a special provision when quality control (QC) test results are to be used for
acceptance in place of QA test results.

November 2017 Page 23 of 30 OPSS.MUNI 310


Appendix 310-A

The designer may consider extending delivery times for samples required on Contracts in remote areas.
(310.07.05.01.04)

The designer should be aware that there is a 4 hour delivery requirement for samples and the laboratory
should be open to receive them. (310.05.01.04 and 310.07.05.02.05)

The designer may consider specifying a joint heater to address cold joint conditions. (310.06.01)

For smaller projects, the borderline category for tolerances on the job-mix formula in Table 7 may not be
appropriate. The designer may consider specifying that all work represented by borderline test results shall
be deemed rejectable. (310.08.03.01)

The complete tender item description for HMA should include a “type” of HMA according to Table 1 of OPSS
1150 for Marshall mixes and according to Tables 1 and 2 of OPSS 1151 for Superpave mixes.

For Superpave mixes, the designer should refer to the appropriate lift thickness guidelines according to
National Asphalt Pavement Association (NAPA), Information Series 128, HMA Pavement Mix Type
Selection Guide, page 10, Figure 5, Recommended Minimum Lift Thickness Ranges for Dense Graded
Mixes. Fine and coarse graded mixes as defined using primary control sieves are defined in OPSS 1151.

The designer may refer to the Best Practices for Testing of Superpave Hot Mix Quality Control Samples
guidelines developed by the Ontario Superpave Implementation Committee. When the designer is
including bonus or penalty clauses or both in relation to OPSS 310, more stringent laboratory procedures
should be considered.

In times of volatile asphalt cement prices, on multi-year contracts, and on Contracts with greater than
500 tonnes of machine laid HMA, municipal designers may consider using the MTO PGAC price index for
payment adjustment. If the designer wishes to use the PGAC price index, Appendix 310-B should be
invoked in the Contract Documents. Appendix 310-B contains information that amends OPSS 310 to
include the requirements for using the MTO PGAC price index for payment adjustment on municipal
contracts.

The MTO PGAC price index is available on the Ontario Ministry of Transportation website at
www.raqs.mto.gov.on.ca, by clicking on Contractor, Contract Bulletin, Asphalt Price Index.

The MTO PGAC price index is only a tool for qualifying hot mix prices and is not intended as a standard
asphalt cement price to be incorporated into the contract bid.

The MTO PGAC price index calculation for a given month takes in the average of the 4 weeks of the month
and is published on the last day of the month.

If the designer wishes to allow the use of warm mix asphalt, Appendix 310-C should be invoked in the
Contract Documents. Appendix 310-C contains information that amends OPSS 310 to include the
requirements for using warm mix asphalt on municipal contracts.

The following warm mix asphalt (WMA) processes are available: wax based, chemical based, and foam
based.

The designer should ensure that the General Conditions of Contract and the 100 Series General
Specifications are included in the Contract Documents.

Related Ontario Provincial Standard Drawings

No information provided here.

November 2017 Page 24 of 30 OPSS.MUNI 310


Appendix 310-B, November 2017
FOR USE IN MUNICIPAL CONTRACTS, WHEN REFERENCED IN THE CONTRACT DOCUMENTS

Note: This is a non-mandatory Additional Information Appendix intended to provide supplementary


requirements for the OPS specification in a municipal contract, when the appendix is invoked by the
Owner. It is written in mandatory language to permit invoking it by reference in the Contract
Documents. If the appendix has not been invoked by reference in the Contract Documents, it does
not apply.

Supplemental Requirements for Using the MTO Performance Graded Asphalt Cement (PGAC) Price
Index in Municipal Contracts

OPSS 310, Hot Mix Asphalt, is amended as follows:

310.02 REFERENCES

Section 310.02 is modified by the addition of the following to the Ontario Ministry of Transportation
Publications:

Contract Bulletin:
Asphalt Price Index

310.10 BASIS OF PAYMENT

Section 310.10 is amended by the addition of the following:

310.10.04 Payment Adjustment for Changes in the MTO Performance Graded Asphalt
Cement Price Index

Payment to the Contractor shall be adjusted based on changes to the MTO PGAC price index. The MTO
PGAC price index shall be published monthly in the Contract Bulletin. The MTO PGAC price index shall
be used to calculate the amount of the payment adjustment per tonne of new asphalt cement accepted into
the Work.

The MTO PGAC price index is based on the price, excluding taxes, f.o.b. (free on board) the depots in the
Toronto area, of asphalt cement grade PG 58-28 or equivalent. One MTO PGAC price index shall be used
to establish and calculate the payment adjustment for all grades. The MTO PGAC price index is published
on the last day of the month and shall be applied to the hot mix asphalt placed in the same month.

A payment adjustment per tonne of new asphalt cement shall be established for each month in which paving
occurs when the MTO PGAC price index for the month differs by more than 5% from the MTO PGAC price
index for the month prior to tender opening. When the MTO PGAC price index differential is less than 5%,
there shall be no payment adjustment established for that month. Payment adjustments due to changes in
the MTO PGAC price index are independent of any other payment adjustments made to the hot mix asphalt
tender items.

The payment adjustment per tonne shall apply to the quantity of new asphalt cement in the hot mix asphalt
accepted into the Work during the month for which the payment adjustment is established. A payment
adjustment for paving work done after the approved time for completion of the Contract has expired,
including the expiration of any extensions of time that have been granted, shall be the lesser of the MTO
PGAC price index in the last month of the Contract or the month in which the paving is completed.

November 2017 Page 25 of 30 OPSS.MUNI 310


Appendix 310-B

The payment adjustment for the month shall be calculated from one of the following formula:

a) When Ip is greater than 1.05 ITO, the payment adjustment per tonne of asphalt cement shall be
(Ip - 1.05 ITO) and the Contractor shall receive additional compensation of:

PA = (Ip - 1.05 ITO) x quantity of new asphalt cement in tonnes

b) When Ip is less than .95 ITO, the payment adjustment per tonne of asphalt cement is (.95 ITO- Ip) and
the Owner receives a rebate of:

PA = (.95 ITO - Ip) x quantity of new asphalt cement in tonnes

where:

PA = payment adjustment for new asphalt cement, in dollars


ITO = MTO PGAC price index published for the month prior to Tender opening
Ip = MTO PGAC price index published for the month in which paving occurs

The quantity of new asphalt cement includes all grades of asphalt cement supplied by the Contractor with
and without polymer modifiers. For each month in which a payment adjustment has been established, the
quantity shall be calculated using the hot mix quantity accepted into the Work and its corresponding asphalt
cement content as required by the job mix formula except for mixes that contain reclaimed asphalt
pavement (RAP).

For mixes that contain RAP, the quantity of new asphalt cement shall be determined from the difference
between the asphalt cement content required by the job mix formula and the asphalt cement content of the
RAP incorporated into the hot mix, as calculated by the Owner.

For mixes containing a liquid anti-stripping additive, the quantity of anti-stripping additive shall be deducted
from the quantity of new asphalt cement. No other deductions shall be made for any other additives.

For progress payment purposes, payment adjustments shall be made on the monthly progress payment
certificate for the months in which hot mix paving occurs.

November 2017 Page 26 of 30 OPSS.MUNI 310


Appendix 310-C, November 2012
FOR USE IN MUNICIPAL CONTRACTS, WHEN REFERENCED IN THE CONTRACT DOCUMENTS

Note: This is a non-mandatory Additional Information Appendix intended to provide supplementary


requirements for the OPS specification in a municipal contract, when the appendix is invoked by the
Owner. It is written in mandatory language to permit invoking it by reference in the Contract
Documents. If the appendix has not been invoked by reference in the Contract Documents, it does
not apply.

Supplementary Requirements for Using Warm Mix Asphalt in Municipal Contracts

OPSS 310, Hot Mix Asphalt, is amended as follows:

310.01 SCOPE

Section 310.01 of OPSS 310 is amended by the addition of the following:

This specification covers the requirements for the placement and compaction of warm mix asphalt (WMA)
designed using the Marshall or Superpave methods.

310.03 DEFINITIONS

Section 310.03 is amended by the deletion of the definition for Hot Mix Asphalt (HMA) and replaced with
the following:

Hot Mix Asphalt (HMA) means hot mixed, hot laid asphaltic concrete and includes mix produced using
WMA technologies. The terms are used interchangeably. HMA may include recycled or specialty mixes.

Section 310.03 is amended by the addition of the following:

Warm Mix Asphalt (WMA) means warm mixed, warm laid asphaltic concrete produced using technologies
that allow for the mixing, handling, and compaction of the asphaltic concrete mixture at a temperature
typically 20 to 50 °C lower than conventional hot mix asphalt.

OPSS 310 is amended by the addition of the following:

310.04 DESIGN AND SUBMISSION REQUIREMENTS

310.04.01 Design Requirements for Warm Mix Asphalt

The Contractor shall be responsible for the following:

a) Selecting the WMA technology to be used on this Contract from recognized WMA technologies or from
the WMA technologies specified in the Contract Documents.

b) The WMA mix design and the job mix formula at the anticipated WMA production temperature, both of
which shall be according to the requirements detailed in the Contract Documents, except as amended
by this specification.

c) Ensuring that, during the development and verification of the WMA mix design, the WMA technology
does not adversely affect the asphalt cement performance grade and the WMA mixture performance.

November 2017 Page 27 of 30 OPSS.MUNI 310


Appendix 310-C

310.04.02 Submission Requirements for Warm Mix Asphalt

A minimum of 14 Days prior to paving with WMA, the following information shall be submitted to the Contract
Administrator in writing:

a) The name of the WMA technology selected for use on the Contract.

b) The complete name and address of the WMA technology supplier, if applicable.

c) Details on how the requirements of this specification shall be met.

d) If applicable, the type and dosage of WMA additives, how the additives are to be incorporated to
produce the WMA, and the WMA technology supplier's established recommendations for usage.

310.05 MATERIALS

Subsection 310.05.01 is deleted in its entirety and replaced with the following:

310.05.01 Warm Mix Asphalt

The materials used in the production of WMA shall be according to OPSS 1150 for Marshall mixes or OPSS
1151 for Superpave and SMA mixes.

The Contractor shall be responsible for the following:

a) Identifying and using a facility capable of producing the WMA according to the WMA technology
supplier’s instructions for the use of its WMA technology.

b) Obtaining from the WMA technology supplier all information required for the proper preparation,
handling, storage, and use of the WMA materials, including Material Safety Data Sheets.

c) Obtaining materials; producing mixes; and the transportation, storage, and use of all materials.

d) Ensuring that the WMA is produced according to the WMA technology supplier’s recommendations to
prevent any deleterious effects to the finished product.

e) Using an anti-stripping additive recommended by the WMA technology supplier when an anti-stripping
additive is to be incorporated into the WMA.

The WMA shall be produced within the temperature range recommended by the WMA technology supplier
to achieve target compaction in the field and to meet the requirements specified in the Contract Documents.

310.06.02.02 Requirements for Rollers

The last paragraph in clause 310.06.02.02.01, General, is deleted in its entirety and replaced with the
following:

The rolls or drums shall be operated according to the WMA technology supplier's requirements to avoid
mat segregation or roller pickup or both.

November 2017 Page 28 of 30 OPSS.MUNI 310


Appendix 310-C

Subsection 310.07.04 is deleted in its entirety and replaced with the following:

310.07.04 Transportation of Warm Mix Asphalt

The WMA shall be transported from the asphalt plant to the work in leak-proof truck boxes that have been
previously cleaned of all foreign materials. If required, truck boxes shall be lightly coated with a uniform
application of release agent in accordance with the WMA technology supplier's recommendations. Truck
boxes shall be drained after each application and before loading. No release agents shall be used that can
adversely affect the quality or performance of the WMA. Release agents shall be used according to the
proprietary requirements.

Each truck shall use a tarpaulin of sufficient size to completely cover the load at all times.

310.07.06 Placing Warm Mix Asphalt

310.07.06.01 General

Subsection 310.07.06.01 is deleted in its entirety and replaced with the following:

The Contractor shall provide notice of intent to pave in writing to the Contract Administrator a minimum of
7 Days prior to placing the WMA.

The WMA technology supplier‘s recommendations for placing the WMA mix shall be followed.

The temperature of the WMA immediately after spreading shall be within the limits identified in Table 11.

Prior to roller compaction, obvious defects in the WMA material placed shall be corrected. Irregularities in
the alignment and grade along the outside edges shall be corrected.

A through lane paving course shall be completed prior to the placement of adjacent side roads, speed
change lanes, and other paved areas. For all courses, each adjacent lane shall be completed to
approximately the same location at the end of each day’s paving.

At the end of each completed portion and prior to opening the lanes to traffic, the completed sections of
WMA course shall be ramped transversely to the existing pavement to a maximum of 30H:1V. In all cases,
the ramps shall not form part of the permanent asphalt pavement and shall be removed prior to continuing
paving operations.

310.08 QUALITY ASSURANCE

310.08.01 General

Clause 310.08.01of OPSS 310 is amended by the addition of the following:

When the selected WMA technology requires that additives be added to the asphalt cement, acceptance
of the asphalt cement shall be based on the samples that contain the WMA additive. Acceptance of WMA
emulsion shall be based on testing the asphalt cement residue obtained from the WMA emulsion.

November 2017 Page 29 of 30 OPSS.MUNI 310


Appendix 310-C

310.10 BASIS OF PAYMENT

Subsection 310.10.01 is deleted in its entirety and replaced with the following:

310.10.01 Warm Mix HL ("type") - Item


Warm Mix HL ("type") Patching - Item
Heavy Duty Binder Course Warm Mix - Item
Medium Duty Binder Course Warm Mix - Item
Dense Friction Course Warm Mix - Item
Superpave Warm Mix ("type") - Item
Superpave Warm Mix ("type") Patching - Item
SMA Warm Mix

Payment at the Contract price for the above tender items shall be full compensation for all labour,
Equipment, and Material to do the work.

Removal and replacement of the following shall be at no extra cost to the Owner:

a) Defective areas of WMA, including but not limited to those due to flushing, bleeding, segregation, fat
spots, surface damage, and surface contamination.

b) WMA that does not meet the requirements of the Contract Documents.

Referee testing undertaken to resolve a dispute shall be at no extra cost to the Owner if the referee test
results confirm that the WMA does not the minimum requirements of Table 8 or is deemed borderline or
rejectable according to Table 9.

A coring and testing program undertaken to resolve a dispute shall be at no extra cost to the Owner if the
mix compaction is confirmed to be below the minimum specified compaction.

No additional payment shall be made for any delays or costs attributed to verification of the gross mass and
tare mass of trucks requested by the Contract Administrator.

Table 11 is added:

TABLE 11
Allowable Limits for WMA Paving Temperature

Minimum Allowable Maximum Allowable


WMA Paving Temperature WMA Paving Temperature

The higher of 60 °C and the minimum The lower of 125 °C and the maximum
temperature recommended by the WMA temperature recommended by the WMA
technology supplier. technology supplier.

November 2017 Page 30 of 30 OPSS.MUNI 310

You might also like