12 Chapter 8 Environmental and Social Management Plan

Download as pdf or txt
Download as pdf or txt
You are on page 1of 41
At a glance
Powered by AI
The document discusses Lydian's plans and systems for managing environmental and social impacts of the Amulsar Gold Mine Project over its lifetime.

The ESMP outlines Lydian's plans and commitments for managing environmental and social impacts during construction, operation and closure of the mine.

The ESMS includes policies, objectives, plans and procedures for managing impacts, stakeholder engagement, a commitment register and implementation plans.

 

Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 
CONTENTS 
GLOSSARY .......................................................................................................................................... iii 
8  ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN .......................................................... 8.1 
8.1  Introduction ......................................................................................................................... 8.1 
8.2  Objectives ............................................................................................................................. 8.2 
8.3  Project Overview .................................................................................................................. 8.3 
8.3.1  Project Execution .......................................................................................................... 8.4 
8.3.2  Project Design .............................................................................................................. 8.5 
8.3.3  Construction ................................................................................................................. 8.5 
8.3.4  Operations and Closure .............................................................................................. 8.10 
8.3.5  Preliminary Life of Mine – Closure and Rehabilitation Schedule ................................ 8.11 
8.4  Corporate ESH&S Policies .................................................................................................. 8.12 
8.5  Stakeholder Engagement ................................................................................................... 8.13 
8.6  Organisation for ESMP Compliance ................................................................................... 8.14 
8.6.1  Corporate and Group Functions ................................................................................. 8.17 
8.6.2  Lydian HSEC Functions ............................................................................................... 8.17 
8.7  Development of the ESMS ................................................................................................. 8.24 
8.7.1  Current Status of Management System ..................................................................... 8.24 
8.7.2  ESMS Objectives ......................................................................................................... 8.24 
8.7.3  Implementation of the ESMS ..................................................................................... 8.25 
8.8  Occupational Health and Safety Management System ..................................................... 8.28 
8.9  Commitments Register ...................................................................................................... 8.30 
8.10  ESMP Implementation ....................................................................................................... 8.30 
8.11  Contractor Management Framework ................................................................................ 8.34 
8.12  Lenders Environmental and Social Action Plan .................................................................. 8.36 
 
 
FIGURES 
Figure 8.1: Project Schedule (as of April, 2016) ................................................................................... 8.8 
Figure 8.2: Project Site Layout ............................................................................................................. 8.9 
Figure 8.3: Proposed Lydian Organisation in 2016 ............................................................................ 8.15 
Figure 8.4 Environmental team structure .......................................................................................... 8.20 
Figure 8.4: Basis of HSEC Management System................................................................................. 8.26 
Figure 8.5: Environmental and Social Management Activities .......................................................... 8.27 
Figure 8.6: Framework for Occupational, Health & Safety Management System ............................. 8.28 
Figure 8.7: Structure of ESMS ............................................................................................................ 8.32 
 
 
ZT520088  Version 10  Page i 
May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 
APPENDICES 
Appendix 8.1  Environment Policy 
Appendix 8.2  Social Policy 
Appendix 8.3   Occupational Health and Safety Policy 
Appendix 8.4  Human Resources Policy 
Appendix 8.5  ESIA Public Commitments Register (PCR) 
Appendix 8.6  Stakeholder Engagement Plan (SEP) 
Appendix 8.7  Occupational Health and Safety Management Plan (OHSMP) 
Appendix 8.8  Footprint Management Plan (FMP) 
Appendix 8.9  Emergency Preparedness and Response Plan (EPRP) 
Appendix 8.10  Transport Management Plan (TMP) 
Appendix 8.11  Cyanide Management Plan (CMP) 
Appendix 8.12  Environmental Monitoring Plan (EMP) 
Appendix 8.13  Integrated Waste Management Plan (IWMP) 
Appendix 8.14  Air Quality, Noise and Vibration Management Plan (AQNVMP) 
Appendix 8.15  Community, Health and Safety Plan (CHSP) 
Appendix 8.16  Community Development Plan (CDP) 
Appendix 8.17  Cultural Heritage Management Plan (CHMP) 
Appendix 8.18  Preliminary Mine Reclamation, Closure and Rehabilitation Plan (pMRCRP) 
Appendix 8.19  Acid Rock Drainage Management Plan (ARDMP) 
Appendix 8.20  Biodiversity Action Plan (BAP), including Appendix 1 ‐ Species Action Plan for 
Potentilla  porphyrantha,  Appendix  2  ‐  Species  Action  Plan  for  Brown  Bear 
Ursos arctos, and Appendix 3 ‐ Biodiversity Offset Strategy (BOS) 
Appendix 8.21  Biodiversity Management Plan (BMP) 
Appendix 8.22  Surface Water Management Plan (SWMP) 
Appendix 8.23  Land Access and Livelihood Restoration Plan (LALRP) and Addendum 
Appendix 8.24  Carbon and Energy Management Plan (CEMP) 
Appendix 8.25  Worker Accommodation Management Plan (WAMP) 
Appendix 8.26  Contractor Management Plan (CMP) 
 
 

ZT520088  Version 10  Page ii 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 
GLOSSARY 
   
ADR  Adsorption Desorption and Recovery. 
AIC  Amulsar Information Centre. 
AIDS  Acquired Immune Deficiency Syndrome. 
BRSF  Barren Rock Storage Facility. 
CBG  Cambridge Botanical Gardens. 
CEO  Chief Executive Officer. 
CLC  Community Liaison Committee. 
E&S  Environmental and Social. 
EBRD   European Bank for Reconstruction and Development. 
EHS   Environmental, Health and Safety. 
EIA  Environmental Impact Assessment. 
EITI  Extractive Industries Transparency Initiative. 
EMP  Environmental Monitoring Plan. 
EPC  Engineering, Procurement and Construction. 
ESAP  Environmental and Social Action Plan. 
ESIA  Environmental and Social Impact Assessment. 
ESMP  Environmental and Social Management Plan. 
FEED  Front End Engineering Design. 
FS  Feasibility Study. 
H&S  Health and Safety. 
HCS  Hazardous chemical substances. 
HIV  Human Immunodeficiency Virus. 
HLF  Heap Leach Facility. 
HSEC  Health, Safety Environmental and Community/Social. 
ICMC   International Cyanide Management Code. 
IESC  Independent Environmental and Social Consultant. 
IFC   International Finance Corporation. 
IFI  International Financing Institution. 
LOM  Life of Mine. 
LTI  Lost Time Injury. 
MENR  Ministry of Energy and Natural Resources (of Republic of 
Armenia). 
MF  Management Framework. 

ZT520088  Version 10  Page iii 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 
MNP  Ministry of Nature Protection (of Republic of Armenia). 
MTAES  Minister of Territorial Administration and Emergency 
Situations (of Republic of Armenia). 
MTPA  Millions of tonnes per annum 
MUD  Ministry of Urban Development (of Republic of Armenia). 
PAG  Potentially Acid‐Generating. 
PEP  Project Execution Plan. 
PMS  Project Master Schedule. 
PPE  Personal Protective Equipment. 
PVA  Project Value Assessment. 
RoA  Republic of Armenia. 
ROM  Run of Mine. 
SCG  Social Capital Group. 
SEP  Stakeholder Engagement Plan. 
STI  Sexually transmitted infections. 
TEC  Treweek Environmental Consultants. 
VPS  Vice President for Sustainability 
VPSHR  Voluntary Principles on Security and Human Rights. 
 
 

ZT520088  Version 10  Page iv 


May 2016 
 
 

 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 
8 ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN 
8.1 Introduction 
The  Environmental  and  Social  Management  Plan  (ESMP)  has  been  prepared  for  the 
construction, operation and closure (including rehabilitation and aftercare) of the Amulsar 
Gold  Project,  to  be  carried  out  by  Lydian  International  Ltd  (Lydian)  and  its  fully  owned 
subsidiary Geoteam CJSC (Geoteam).  The ESMP was prepared based on the environmental 
and social issues identified during the environmental and social evaluation. 
 
The ESMP contains plans, programmes, specifications and guidelines designed to control and 
manage the potential environmental and social impacts that were identified in the ESIA. The 
geographical,  social,  cultural  and  environmental  dynamics  have  been  taken  into 
consideration.  The ESMP is an integral part of the ESIA as it is a policy setting document for 
Lydian  and  its  contractors.    This  document  represents  a  commitment  by  Lydian  to 
environmental and social sustainability, and applies to the Project’s entire life cycle. 
 
The ESMP establishes the Lydian policies, commitments, and resources that are needed to 
allow  effective  implementation  and  continuation  of  the  programmes  and  procedures  to 
manage and mitigate the predicted impacts of the Project.  Implementation of the ESMP will 
fulfil the requirements established by the environmental laws and regulations of Armenia, 
governed  by  the  MNP,  MUD,  MTAES  and  MENR,  as  well  as  other  technical  and  legal 
instruments that apply. The Project will also comply with World Bank Group EHS Guidelines, 
IFC Performance Standards and EBRD Performance Requirements.  
 
The implementation of the ESMP’s commitments will be subject to supervision and internal 
and  external  auditing.  Supervision  of  the  implementation  of,  and  compliance  with, 
commitments set in the ESMP will be overseen permanently by RA Environmental Inspection 
and an Independent Engineer appointed by Lenders during the life of the loans.  
 
In mid‐2015, a Value Engineering (VE) and Optimization process was initiated, with Lydian 
commissioning  Samuel  Engineering  Inc.  (Samuel)  and  other  consultants  to  develop 
engineering design on several identified VE and Optimization concepts.  The objective was to 
reduce  capital  expenditure  without  increasing  operating  costs  with  no  net  change  on 
environmental  and  social  impacts.    The  results  from  this  work  done  in  2015,  which  were 
published in the NI “43‐101 Technical Report: Amulsar Value Engineering and Optimization” 
in November 2015, included reduced capital and operational costs, making the Project more 

ZT520088  Version 10  Page 8.1 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 
viable in a challenging economic environment.  Based on the Technical Report, this version of 
the ESIA (v10) is the basis against which the ESMP monitors and continuously improves.  The 
Project Execution Plan (PEP) is being developed and is to be implemented in accordance with 
this ESMP.   
 
8.2 Objectives 
The principal objective of the ESMP is to “operationalise” the commitments to environmental 
and  social  (as  well  as  occupational  health  and  safety)  management  and  mitigation  as 
identified by the ESIA.  This should ensure that the Project (including construction, operation, 
closure and post‐closure phases) is undertaken in a manner which maximizes the benefits to, 
and  minimises  the  negative  impacts  on,  the  physical,  biological,  social  and  archaeological 
environments in the Project‐affected area. 
 
Specific objectives include: 
 Achieving zero lost time injuries (LTI’s) during construction and operation; 
 Establishing upfront during construction a culture for safety, productivity, efficiency and 
flexibility to be subsequently maintained by Amulsar operations; 
 Implementing appropriate prevention and mitigation measures to reduce the incidence 
of  negative  environmental  impacts  and  promote  favourable  conditions  during  the 
construction, operation and closure phases; 
 Creating an effective environmental monitoring and supervision plan that allows for the 
monitoring of the proposed activities and environmental variables during the Project; 
 Establishing  participation  mechanisms  for  the  Project  stakeholders  to  keep  them 
informed about Project activities and how they may affect their daily activities; 
 Elaborating procedures that will allow effective and timely response to emergencies, and 
enable the reporting of events that may arise; 
 Safeguarding biodiversity and ecosystems and making special provision for habitats and 
species of conservation importance at the national and international levels; 
 Performing adequate management of solid residues as required by applicable laws and 
IFC/EBRD requirements; 
 Monitoring the ongoing land acquisition and economic displacement activities; 
 Restoring livelihoods impacted by economic displacement caused by the Project; 
 Preserving  the  archaeological  heritage  identified  in  the  Project’s  area  of  influence  as 
defined by applicable laws;  
 Establishing  and  maintaining  communication  channels  among  Lydian,  the  appropriate 

ZT520088  Version 10  Page 8.2 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 
authorities and stakeholders associated with the Project;  
 Having zero equipment loss or damage during importation, transportation and storage, 
installation, commissioning and ramp‐up phases; and 
 Ensuring that the high level commitments made by Lydian (EITI, ICMC & VPSHR) are met. 
 
8.3 Project Overview 
The Amulsar project consists of the mine and the processing facilities, including the open pits, 
the  barren  rock  storage  facility  (BRSF),  the  crushing  and  screening  plant,  the  overland 
conveyor and truck load‐out facility, the heap leach pad and solution ponds, the Adsorption, 
Desorption and Recovery (ADR) Plant, and the infrastructure that supports the mining and 
processing  facilities.  The  non‐processing  infrastructure  components  include,  but  are  not 
limited to, a 110kV main electrical substation & 35kV secondary power distribution network, 
mine workshop and warehouse facilities, administration and ancillary buildings, surface water 
control  structures  (ponds,  piping,  etc.)  for  contact  and  non‐contact  surface  water 
management, raw water make‐up system from the Arpa River, site access and haul roads, and 
temporary construction infrastructure. 
 
The Project’s construction phase will last for two years.  During the 10 years of operations 
(including pre‐production during the construction phase), the Artavazdes, Tigranes and Erato 
ore bodies will be mined using conventional open pit mining methods.  Precious metals will 
be recovered from low‐grade material by heap leaching.  To prepare the ore for leaching, a 
10.5 million tons per annum (MTPA) crushing and screening plant will reduce the ore to a 
nominal 19 mm size.  The crushed ore will be conveyed approximately 5.6 km with a covered 
overland conveyor and discharged to a crushed ore stockpile. Crushed ore will be loaded into 
trucks  and  stacked  on  the  heap  in  8  m  lifts.  The  ore  will  be  leached  with  a  dilute  cyanide 
solution  in  the  conventional  manner.  Precious  metals  will  be  recovered  from  the  leach 
solution by adsorption on activated carbon.  The precious metals will be periodically desorbed 
from  the  activated  carbon  and  the  stripped  carbon  will  be  acid  washed  and  reactivated.  
Precious  metals  will  be  recovered  from  the  strip  solution  using  a  Merrill‐Crowe  zinc 
precipitation process.  The precipitate will be dried, retorted for removal of any mercury and 
smelted to produce doré bullion that will be shipped from the site to refiners. 
 
The primary objective of the Project is to design, construct, and operate the gold and silver 
production facilities with due consideration for the economic, social, environmental, health 
and  safety  (occupational  as  well  as  community)  risks  of  the  Project  and  with  a  strong 

ZT520088  Version 10  Page 8.3 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 
commitment  to  the  sustainable  development  of  Project‐affected  communities  and  the 
environment.   
 
The physical footprint of the Project’s facilities will cover 599 ha, and a further 323 ha in areas 
that are likely to be disturbed by the mining operations. The total disturbed are will be 922 ha. 
Further  buffer  zones  will  experience  effects  of  noise,  dust  deposition,  and  limits  to  access 
resulting from fencing, or proximity to Project infrastructure. These buffer zones amount to 
an additional 854 ha. 
 
Of this overall total of approximately 1,767ha, about 152ha comprise 274 privately‐owned 
plots that Lydian will gain access to through a land acquisition process (see Appendix 8.23): 
 
 Heap leach facility (HLF) area: 252 private land plots consisting of approximately 139 ha 
of  arable  land,  22ha  of  orchards  and  14ha  of  pasture/hay  land,  to  be  acquired 
permanently for the Project; and 
 Conveyor  and  haul  roads:  22  private  land  plots  to  be  rented  for  the  construction  and 
operation phases, covering a total surface under the conveyor of 13 ha. 
 
The closure and rehabilitation phase of the mine is an important component of the Project 
that  will  take  place  when  the  economic  resource  is  exhausted  and  mining  and  processing 
completed. Further details are provided in the plan prepared to that  effect (see Appendix 
8.18).  
 
8.3.1 Project Execution 
The Environmental Impact Assessment (EIA) approval for the Project was received by Lydian 
in October 2014, and the Mining Right (MR) in November 2014.  Changes to the Project design 
as a result of the VE and Optimization work have resulted in the need to prepare a revision to 
the EIA and amend the ESIA completed and disclosed in April 2015. Lydian is in the process of 
preparing a new EIA and applying to government for a new MR. The granting of the amended 
MR, anticipated by mid 2016, will allow full construction to start within the parameters of the 
Mining Code and the EIA Law. Some early works that are consistent with the already granted 
permits may take place from June 2016 onwards. In parallel a number of permits required for 
the construction and operation phase by Armenian regulations will be determined during Q1 
and Q2 of 2016.     
 

ZT520088  Version 10  Page 8.4 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 
The  preliminary  Project  Execution  Plan  (PEP)  has  been  produced.  The  PEP  describes  the 
execution of required optimization studies, Basic and Detail Engineering, procurement and 
construction, commissioning, operations planning and initial operations through to project 
completion.  The Project milestones include: 
 Early Works construction to start in Q2/Q3 2016; 
 Land acquisition to be completed by end of Q2 2016; 
 Detailed engineering design to be completed by end 2016; 
 Start of mining Q4 2017;  
 First gold in Q1 2018; and 
 Commercial production by end of Q2 2018. 
 
8.3.2 Project Design 
For  the  Project  design  phase,  the  PEP  envisages  a  “mixed  contract”  strategy,  whereby 
specialist international companies will be employed to design process facilities, the HLF, the 
Barren  Rock  Storage  Facility  (BRSF)  and  high/medium  power  supply  infrastructure;  and 
Armenian  engineering  and  construction  firms  will  be  employed  for  other  infrastructure 
including  roads,  the  construction  camp,  potable  and  wastewater  treatment,  power  supply 
and distribution, storm water impoundment structures and water pumping systems, as well 
as for completing the requisite in‐country process for obtaining construction permits.   
 
8.3.3 Construction  
The  PEP  envisages  a  “mixed  contract”  approach  to  construction  of  the  Project,  using  a 
combination of Project Construction Management (PCM) contracts, Construction Contracts, 
Engineering/Supply and Engineer‐Procure‐Construct (EPC) contracts for the majority of the 
work.  The “mixed contract” approach presents challenges in terms of the integration and 
coordination  of  contractors,  in  particular  on  Health,  Safety,  Environmental  and 
Community/Social HSEC management; and this challenge will also apply with regard to the 
implementation  of  the  ESMP.    The  implications  for  ESMP  implementation  are  discussed 
further in Section 8.10. The provisional construction schedule is provided in Figure 8.1. 
 
The Early Works activities are permitting, engineering and weather dependent. Site elevation 
differences  enable  work  to  continue  efficiently  at  lower  elevations,  but  work  at  or  above 
2600 m above sea level may be suspended if extreme weather conditions prevail.  The focus 
will  be  on  critical  path  activities  to  the  extent  possible  as  early  as  possible  in  the  2016 
earthworks construction season; this focus will generally be in the HLF and ADR plant areas, 

ZT520088  Version 10  Page 8.5 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 
although pioneer earthworks will be made at higher elevations, weather permitting.   
 
Early Works currently planned include: 
 Critical  sedimentation  and  drainage  control  structures  to  capture  runoff  from  initial 
earthworks; 
 Upgrade or development of access roads into Project work areas; 
 Establishment of a platform for construction offices, temporary warehouse, equipment 
parking and servicing near the proposed ADR facility; 
 Temporary construction utilities for water, power and sewage;  
 Installation of access control guard stations to Project work areas; 
 Temporary  water  intake  at  the  Arpa  for  early  construction  activities;  mainly  dust 
suppression and compaction at the HLF site;  
 Tentatively  in  the  spring,  relocation  of  the  irrigation  pipeline  that  runs  across  the 
bottom of the HLF site (tie‐in, install vales and install new pipe), and removal of the 
power line; and 
 Initial archaeological clearances including excavations in the HLF area.  
 
The facilities and infrastructure to be developed during the main construction phase includes: 
 Open pits; 
 BRSF; 
 Crushing and screening plant; 
 Run of mine (ROM) ore stockpile; 
 Topsoil stockpiles; 
 Surface water management network; 
 Temporary construction infrastructure; 
 Haul and access roads; 
 Overland conveyor and truck load‐out area; 
 HLF including: 
o Heap leach pad;  
o Process pond and storm ponds;  
o Contact water pond and surface water diversion channel; 
o ADR plant; and 
o Administration offices; 
 Passive Water Treatment  System (PWTS); 
 Maintenance workshops and offices; 

ZT520088  Version 10  Page 8.6 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 
 Domestic waste water treatment facilities; 
 Landfill for non‐hazardous waste;  
 Contained storage cell for transfer of hazardous wastes 
 Electrical power and water supply infrastructure;  
 Explosives magazine; 
 Reagents storage facility; 
 Cyanide storage facility; 
 Analytical and metallurgical test laboratory at ADR facility; and 
 Hotel accommodation in Jermuk for Lydian construction and operations staff, with the 
potential  to  build  a  temporary  camp  that  would  be  removed  following  the  peak 
construction work force requirements.  
 
The current Project site layout is shown in Figure 8.2. 
 
Access to the mine, crushing facilities, and BRSF will be via a 10 km partially paved road that 
links to the H‐42 connecting Gndevaz and Jermuk (see Figure 8.2).  Since the HLF is also close 
to the existing H‐42 leading from Gndevaz to Jermuk, a 100 m access road will be constructed 
for the construction, operation, and maintenance of the HLF and ADR gold and silver recovery 
plant.  An access road along the conveyor corridor to the crusher will be also constructed, for 
maintenance / monitoring of the conveyor as well as access to the crusher and production 
infrastructure at the top of the mountain.  Fibre‐optic lines, water and power lines will also 
be  located  in  this  corridor  to  minimize  land  disturbance  and  provide  easy  access  for 
maintenance.   The existing power lines, which run along the western edge of the mine site, 
will  be  used  to  provide  site  power  and  a  new  110kV  substation  will  be  built.  Only  mine 
employees and contractors/vendors with approved mine business will be allowed to drive on 
these access roads 
 

ZT520088  Version 10  Page 8.7 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 

   
Figure 8.1: Project Schedule (as of April, 2016) 
ZT520088  Version 10  Page 8.8 
May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8       
 

 
Figure 8.2: Project Site Layout
ZT520088  Version 10  Page 8.9 
May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
The location of the BRSF will be on the northeast side of Amulsar Mountain, approximately 
2.8  km  from  Tigranes  pit  and  1.1  km  north  of  Erato.    The  BRSF  will  include  a  barren  rock 
storage pad and a toe pond connected via pipeline to the passive water treatment system 
(PWTS) at the HLF.  Post‐closure the PWTS could be relocated down‐gradient of the barren 
rock  storage  pad  if  necessary.    The  BRSF  will  be  constructed  with  a  low‐permeability 
compacted clay liner consisting of re‐compacted subsoil.  Non‐acid‐generating (NAG) barren 
rock  will  be  placed  over  the  compacted  soil  liner.    From  year  5  of  operations,  any  water 
emanating through the foundation of the BRSF (from potential seeps and springs) will travel 
through this layer to the toe pond and via a gravity fed pipe to the PTS before being discharged 
as treated water in the Arpa River (see Appendix 3.1).  Some of the barren rock at Amulsar 
has the potential to produce acid rock drainage (ARD) if managed improperly.  Potentially acid 
generating  rocks  will  be  segregated  and  encapsulated  within  the  BRSF  to  mitigate  the 
potential formation of ARD and runoff. 
 
8.3.4 Operations and Closure 
Mining  of  the  Amulsar  deposit  is  planned  to  use  conventional  open‐pit  methods  for  the 
operational phase of 10 years.  The Artavazdes and Tigranes areas will be mined ahead of the 
Erato  area,  which  requires  more  rock  stripping  to  expose  the  ore.    Barren  rock  from  the 
Tigranes and Artavazdes deposits will be managed in the BRSF and the barren rock from the 
Erato area will be used to partially backfill the Tigranes and Artavazdes areas in the later part 
of the mining operation. 
 
Located approximately 0.8 km north of the Erato pit the crushing and screening facility will be 
located within a building and connects to the overland conveyor. Other mine facilities include 
the maintenance workshops, mine office building, and other smaller facilities to assist in the 
operation  of  the  Project.    Crushed  ore  will  be  transported  approximately  5.6  km  by  the 
covered overland conveyor.  Ore will be loaded into haul trucks at the western end of the 
conveyor for distribution and stacking in the HLF.   
 
The HLF will be located on the western side of Amulsar Mountain, approximately 1 km south 
of Gndevaz at its closest point, and approximately 6.1 km in a direct line from the open pits.  
The HLF will be located in a valley fill area and is anticipated to have a design capacity of 104 
Mt.  The HLF is located within the Arpa River catchment and downstream of Kechut Reservoir.  
It includes collection and process ponds and the ADR gold recovery plant adjacent to the pad.   
 

ZT520088  Version 10  Page 8.10 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
At  closure  the  PTS,  which  would  have  been  operational  since  year  5  of  operations  is  the 
preferred option to mitigate the potential formation of ARD from the BRSF. Passive water 
treatment systems do not require continuous chemical inputs and take advantage of naturally 
occurring chemical and biological processes to treat ARD (see Appendix 3.1). After the BRSF 
outflow water has passed through the PTS, the water will collected and monitored prior to 
discharge  into  the  natural  environment.    The  PTS  output  will  comply  with  RA,  IFC  and 
European Union water discharge standards. 
 
Closure  and  rehabilitation  include  the  reclamation  of  the  open  pits,  barren  rock  storage 
facility,  and  heap  leach  pad / ponds,  together  with  the  dismantling  of  infrastructure  and 
restoration of these and other disturbed areas to grasslands that support habitats similar to 
those currently present within the Project. 
 
8.3.5 Preliminary Life of Mine – Closure and Rehabilitation Schedule 
An approximate Life of Mine (LOM) and Closure and Rehabilitation schedule is as follows: 
 
 Years ‐2 and ‐1:    Mine construction. 
 Years 1 through 9:    Mining operational phase. 
 Years 9 through 10:    Removal and processing of low‐grade ore from BRSF 
 Years 0 through 10:     Develop and monitor instrumented re‐vegetation test  
plots  and  closure  cover  test  plots  and  optimize  the 
closure and rehabilitation plan. 
 Years 1 through 3:    Progressive rehabilitation of pipeline disturbance areas  
and road embankments. 
Pilot test for the PWTS to demonstrate adequacy. 
 Years 1 through 6:     Placement of barren rock in BRSF (Phases 1 through 3). 
 Years 1 through 5:     Placement of low‐grade ore in BRSF. 
 Year 1 through 4:  Progress  feasibility  studies  to  field  trials  and  the 
construction  of  a  passive  treatment  system  for 
treatment of contact water including BRSF seepage. 
 Year 5:       Treatment of contact water from BRSF will commence 
in PTS  
 Years 3 through 7:     Progressive reclamation of BRSF starting from northern  
toe  of  facility  (excluding  low‐grade  ore  area)  including 
regrading, recontouring, and cover construction. 
ZT520088  Version 10  Page 8.11 
May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
 Years 3 through 9:     Progressive backfill of Tigranes and Artavazdes Pits.  
 Years 7 through 11:    Progressive reclamation of pit backfill and resource  
areas including cover construction. 
 Years 10 through 11:     Reclamation of south facing BRSF slopes following  
removal  of  low‐  grade  ore  including  regrading, 
recontouring, and cover construction. 
 Years 11 through 13:    Neutralisation / rinsing of HLF. 
 Years 11 through 13:    Progressive removal of infrastructure, including 
        crushing  facility,  structures  non‐essential  to  closure, 
        conveyor  system  and  final  rehabilitation  of  BRSF,  haul 
        roads, platforms and securing the pits. 
 Years 13 through 14:    HLF closure activities including regrading, cover  
placement  and  surface  water  controls  (six‐month 
construction period for closure and rehabilitation) after 
neutralisation / rinsing. 
Year 14:  Construct drainage and convert storm water ponds to 
a wetland system to direct contact water to HLF PTS. 
 Year 14+       Passive treatment of HLF draindown solution. 
 Years 14 through 19:     Post‐closure period. 
 Monitoring of rehabilitated areas – minimum of five years. 
 Final closure of remaining facilities (6 to 12 month decommissioning phase). 
It is anticipated that the closure and rehabilitation schedule will last approximately 5 years.  
 
8.4 Corporate ESH&S Policies 
Lydian  and  its  controlled  affiliates  promote  sustainable  development  outcomes  and  are 
committed to the integration of environmental, social, health and safety considerations into 
their procedures for Project development and operation at all stages. 
 
Lydian is committed to continuously improving the operational performance of the Project, 
to  achieve  zero  lost  time  injuries  (LTI’s),  to  establish  a  culture  for  safety,  productivity, 
efficiency  and  flexibility  to  enhance  the  Project’s  social  and  environmental  benefits  in 
Armenia, and to limit adverse impacts while maintaining a high level of environmental, social, 
and health and safety performance. 
 
Lydian has a policy framework as described in Section 2.3 of this ESIA.  It comprises the Code 
ZT520088  Version 10  Page 8.12 
May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
of Conduct and eight corporate policies: 
• Environment Policy (Appendix 8.1); 
• Social Policy (Appendix 8.2); 
• Occupational Health and Safety Policy (Appendix 8.3); 
• Human Resources Policy (Appendix 8.4); 
• Whistle Blower Policy; 
• Anti‐Corruption Policy; 
• Insider Training Policy; and 
• Disclosure and Confidentiality Policy.  
 
Lydian’s  corporate  policies  and  Code  of  Conduct,  available  on  the  Lydian  website,  are  all 
incorporated  in  the  Project  ESMP  (see  http://www.lydianinternational.co.uk/corporate‐
governance.htm) 
 
8.5 Stakeholder Engagement 
Stakeholder engagement is a core value of Lydian. During the exploration, pre‐feasibility and 
feasibility phases, the main aim of stakeholder engagement has been to establish two‐way 
communication between Geoteam and stakeholders at national, regional and local levels to 
ensure  stakeholder  views  are  incorporated  into  the  ESIA  and  Project  design.  Good 
relationships  with  local  communities  have  supported  the  development  of  exploration 
activities. 
 
The Stakeholder Engagement Plan (SEP) prepared in January 2016 (see Appendix 8.6) presents 
the  disclosure,  information  and  consultation  activities  proposed  during  construction  and 
operation. It includes but is not limited to: 
 Post ESIA disclosure consultation; 
 Project information meetings and technical workshops; 
 Postings on the corporate Geoteam website; 
 Availability of the Amulsar Information Centre (AIC), with direct access to the Grievance 
Mechanism; 
 Community Liaison Committee (CLC) regular monthly meetings; 
 Message Boards and Newsletter; and 
 Media Advertisements and Press Releases. 
 
Lydian/Geoteam will organize meetings and workshops as needed to explain the construction 

ZT520088  Version 10  Page 8.13 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
activities  and  schedule  from  March  2016  until  mid  2018  in  the  Gndevaz  AIC  and  the 
municipality of each village (Jermuk, Saravan and Gorayk) as well as in Yerevan. 
 
The SEP will be updated periodically and in accordance with major Project changes to reflect 
engagement activities that may be required during the life of the Project. 
 
8.6 Organisation for ESMP Compliance 
Lydian International, with its wholly owned Armenian subsidiary, Geoteam CJSC, is managed 
as a single organisation with five principal departments reporting to its President and CEO: 
•  Chief Operating Officer / Country Manager; 
•  Finance; 
•  Operations; 
•  Government Relations & Business Development; and 
•  Project Implementation. 
 
The proposed Lydian organization chart for 2016 to include the construction phase is provided 
in Figure 8.3. 

ZT520088  Version 10  Page 8.14 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 

   
Figure 8.3: Proposed Lydian Organisation in 2016
ZT520088  Version 10  Page 8.15 
May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
Lydian’s Vice President for Sustainability (VPS) is responsible for developing and managing the 
OHSMS and ESMS, and the associated management plans.  In terms of implementation, the 
VPS  retains  overall  accountability  for  compliance  and  responsibility  for  ensuring  that  the 
health, safety, environmental and social commitments of the ESIA are met.   
 
During  construction,  the  environmental,  health  and  safety  teams  operating  on  site  will  be 
integrated into the construction team and will be directly accountable to the VPS, with an 
additional  communication  and  reporting  function  to  the  Project  Director.    Contractor 
compliance  management  approaches  will  be  defined  when  the  exact  composition  of  the 
“mixed contract” approach is understood (see Section 8.10).  It is anticipated that larger EPC 
contractors will provide their own social and environmental management resources, plans 
and compliance reports, whereas smaller contractors may fall directly under Lydian's OHSMS 
and ESMS.  However, Lydian's social and environmental performance requirements will be 
specified  in  all  contracts,  and  compliance  checks  and  audits  will  be  carried  out  by  Lydian 
personnel.  It  is  anticipated  that  there  will  be  a  significant  effort  related  to  training  of 
contractors, construction workforce and Geoteam staff before and during the construction 
phase.   To that effect the Social Capital Group (SCG) conducted, in January 2015, a nine‐day 
scoping visit to the Amulsar Project to provide advice on the design of a training programme 
to  benefit  local  residents  during  mine  construction  and  operation,  with  a  final  report 
completed in March 2015, which will remain an internal document.   
 
 

ZT520088  Version 10  Page 8.16 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
8.6.1 Corporate and Group Functions 
The functions of the Corporate and Group executives include overseeing the implementation 
of Lydian’s environmental and social policies.  The Lydian corporate level utilises supervision 
feedback, periodic meetings and audits to assess progress with the Social and Environment 
functions to ensure the proper implementation of the ESMP.  The Board of Directors is advised 
on social and environmental issues through the HSEC Committee, as described below: 
 
HSEC Committee 
The purpose of the HSEC Committee is to assist the Board of Directors of Lydian in its oversight 
of:  
(a) Health, safety, environment and community risks;  
(b) The  Corporation’s  compliance  with  applicable  legal  and  regulatory  requirements 
associated with health, safety, environmental and community matters;  
(c) The  Corporation’s  performance  in  relation  to  health,  safety,  environmental  and 
community matters;  
(d) The performance and leadership of the health, safety, environment and community 
function; and  
(e) The Corporation’s external communication and annual reporting in relation to health, 
safety, environmental and community matters.  
 
The corporate level will fulfil the following functions: 
 Assure that Lydian’s policy and guidelines are adhered to; 
 Coordinate the implementation of procedures established in the ESMP; 
 Liaise  with members  of  the  public, local  organisations,  and  governmental  and  non‐
governmental organisations on environmental issues; and 
 Inform the relevant authorities of any incidents that occur during the Project. 
 
8.6.2 Lydian HSEC Functions 
Lydian Vice President Sustainability 
The Lydian VPS reports directly to the Chief Operating Officer (COO) and presents social and 
environmental issues to the HSEC Board Committee.  The VPS has overall responsibility for 
the  social  and  environmental  management,  compliance,  training  and  performance  of  the 
Amulsar Project.  The management of all of the ESIA/ESMP commitments are organized under 
a single (non‐operational) management responsibility reporting directly to the COO. The VPS 
will lead the development of the ESMS and OHSMS required for construction and operation.  

ZT520088  Version 10  Page 8.17 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
Permitting and Sustainability Senior Manager 
The  Permitting  and  Sustainability  Senior  Manager  reports  directly  to  the  VPS  and  is 
responsible for tracking compliance with Armenian environmental permitting requirements, 
regular reporting, and oversight of social, environmental and training issues as required by 
RA regulations.  He/she is responsible for the management and  implementation of the legal 
register, and will work closely on environmental requirements with the Senior Manager HESS 
 
Senior Manager Health, Environmental, Safety & Security (HESS) 
The Senior Manager HESS is accountable for ensuring the development and implementation 
of the OHSMS and implementation of the ESMS together with responsibility for developing 
and ensuring training schedules to be implemented throughout the Company, in accordance 
with a training matrix. The Site Environment Manager (with a team of at least five reports), 
Site Safety and Health Manager (with a team of at least 7 assistants), and Security Manager 
(with a team of security officers) all report directly to the Senior Manager HESS. The Senior 
Manager  HESS  has  overall  accountability  for  environmental,  health,  safety  and  security 
management  on  site,  together  with  the  necessary  environmental  and  social  training 
requirements.  The  Senior  Manager  HESS  will  have  direct  accountability  to  the  VPS  and  a 
second communication and reporting function to the Project Director. He provides support 
to the Site Environment Manager, the Site Safety and Health Manager and the Site Security 
Manager in terms of implementing the OHSMS and ESMS.   
 
Environmental Roles: 
Site Environment Manager 
The  Site  Environment  Manager  is  responsible  for  environmental  management  during 
construction  and  operations  at  Amulsar.    Reporting  to  the  Senior  Manager  HESS,  he/she 
develops  the  necessary  procedures,  plans  and  training  requirements  for  on‐the‐ground 
implementation of Lydian environmental policy and the environmental commitments made 
in both the approved regulatory EIA and the ESIA undertaken to comply with international 
financing institutions' requirements. 
 
The Environment Manager’s functions include:  
 Day‐to‐day  water,  noise,  air  quality,  and  footprint  management,  including  compliance 
checking of contractor activities (as per the Compliance Assurance Plan; see Section 8.10); 
 Liaison with contractors' environmental staff; 
 Management of environmental monitoring and reporting; 

ZT520088  Version 10  Page 8.18 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
 Training of environmental staff and contractors;  
 Oversight of biodiversity initiatives; 
 Management of the Site Environment Advisors; and 
 Oversight of cultural heritage management.  
 
Senior Biodiversity Specialist 
The Senior Biodiversity Specialist reports to the Site Environment Manager and is responsible 
for  the  on‐site  implementation  of  Amulsar’s  biodiversity  initiatives.    This  includes  baseline 
data collection, monitoring, and implementation of the partnership work with the Institute of 
Botany (IoB) on the Potentilla Research Project and with Treweek Environmental Consultants 
(TEC) on development and implementation of the biodiversity offset and the management of 
the set‐aside.  
 
Site Environment Advisors 
The  Environment  Advisors  are  responsible  for  the  implementation  of  the  environmental 
components of the ESMP on site, and particularly the Environmental Monitoring Plan (EMP) 
which includes monitoring of surface water and groundwater, aquatic ecology, meteorology, 
and air quality. These officers report to the Site Environment Manager. 
 
The Environment Officers will also be responsible for day‐to‐day environmental observation 
and reporting as required by the various management plans. 
 

ZT520088  Version 10  Page 8.19 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 

Vice President 
Sustainability

Senior Manager  Senior Permitting 
HESS and Sustainability

Site Security  Site Engineering 
Site Safety Manager
Manager Manager

Site Envionmental 
Site Safey  Advisors
Security team Rehab / Closure
Superindent
(3 No.)

Safety advisors Clinic
Superindent Nurseries
(4 No.) Medical (2 No.)
Nurses (2 No.)

 
Figure 8.4 Environmental team structure 
 
Social Roles: 
Community Relations Manager 
The  Community  Relations  Manager  reports  directly  to  the  VPS  and  manages  the  social 
component of the ESMP and ESMS, local recruitment and training, stakeholder engagement 
and all community development programmes, together with responsibility for developing and 
ensuring training schedules to be implemented throughout the Company, in accordance with 
a training matrix.  The Community Relations Manager also manages the community grievance 
procedure. He/she is the Company's resource in strategic planning, providing social sector 
technical and training input and insights to the implementation of the corporate responsibility 
and social policy and strategy.   
 
The Community Relations Manager’s functions include:  
 Implementation and maintenance of the stakeholder engagement plan (SEP) and log 
(information  meetings,  public  hearings,  CLC  meetings,  other  meetings,  stakeholder 
contacts);  
 Oversight of the local recruitment processes and the local training programme; 
 Oversight of the local procurement initiatives; 
 Oversight of community health, safety and security; 

ZT520088  Version 10  Page 8.20 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
 Oversight  and  compliance  checking    (as  per  the  Compliance  Assurance  Plan;  see 
Section  8.10)  of  contractors'  activities  where  there  is  interaction  with  local 
communities; 
 Implementation of the Community Development Plan; 
 Managing the grievance mechanism and database;  
 Supervising the Amulsar Information Centre;  
 Preparing the annual "Issues & responses" report and respective database; 
 Participating in any emergency response in the event that an accident or emergency 
occurs and involves social issues;  
 Implementation of the livelihood restoration activities per the LALRP (see Appendix 
8.23); and 
 Managing the community field assistants and Community Liaison Officers. 
 
Social Development and Stakeholder Engagement Coordinator 
This Coordinator reports directly to the Community Relations Manager and is responsible for 
the implementation of the SEP and the social development programmes.  This roles includes 
the tracking of community grievances (both those raised through the Project’s community 
grievance mechanism and those received through Contractor grievance mechanisms, where 
applicable).  
 
Site Community Liaison Officer 
The Site Community Liaison Officer is responsible for interfacing with the local stakeholders.  
Before  the  Project  begins,  the  Community  Liaison  Officer  will  develop  a  tracking  and 
documentation system to monitor this process. 
 
The Community Liaison Officer’s functions include: 
 Maintain  an  open  line  of  communication  with  the  environment,  health  and  safety, 
construction, operations, and human resources functions (including contractors); 
 Monitor Project activities that may affect  the local population; 
 Create  and  implement  a  directed,  systematic  communications  strategy  to  help 
coordinate with local stakeholders; 
 Consult with, and provide appropriate information to, all local stakeholders;  
 Coordinate  with  construction  personnel  to  provide  information  to  community 
stakeholders during local meetings where the project’s activities are discussed; and 
 Report  any  incident  that  takes  place  during  the  Project  to  the  Permitting  and 

ZT520088  Version 10  Page 8.21 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
Sustainability Senior Manager and Community Relations Manager.  
 
Environment Advisors and Community Field Assistants 
The Environment Advisors and Community Field Assistants will supervise, monitor and track 
the implementation of the environmental and social commitments established in the ESMP. 
The  teams  will  consist  of  a  number  of  environment  and  social  professionals  reporting  to, 
respectively, the Site Environment Manager and the Site Community Relations Manager. 
 
Land Access Lead 
Currently  land  access  is  placed  under  the  direct  responsibility  of  the  Geoteam  Managing 
Director (Land Access Lead), with compliance oversight provided by senior executives.   
 
The Land Access Lead’s tasks include the following: 
 Coordinates  and  allocates  all  activities,  and  ensure  that  they  are  delivered  on  time, 
particularly with regards to external contractors (valuer, notary, and potentially others); 
 Liaises with mayors and other external parties; 
 Coordinates grievance management (allocation of tasks with regards to grievance review 
and resolution) and overall accountability for grievance management; 
 Participates personally in difficult negotiations (with the other staff identified below);  
 Ensures  quality  control,  particularly  where  tasks  are  outsourced,  and  ensures  that  all 
documentation is consistently gathered, stored, and processed; 
 Checks, validates and signs all legal agreements pertaining to the land access process; 
 Prepares  monthly  reports  per  the  format  indicated  in  the  Land  Access  and  Livelihood 
Restoration  Plan  (LALRP,  see  Appendix  8.23)  and  provides  all  information  required  for 
compliance monitoring; and  
 Reports to Lydian Senior Management on a regular basis (weekly and monthly).  
 
Most of the land acquisition for the Project has been completed, and the Land Access Lead's 
responsibilities will diminish as the Project moves to implementation, although he will have a 
role in dealing with any residual issues or additional land acquisition, if required. 
 
Other Land Acquisition Staff 
Land Access Manager:  
 Coordinates  negotiation  activities  (including  signature  with  notaries),  establishment  of 
schedules,  verification  of  agreements,  coordination  of  registration  at  cadastral  offices, 

ZT520088  Version 10  Page 8.22 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
coordination  of  identification  of  absentee  co‐owners,  perform  regular  documentary 
audits; 
 Coordinates  the  development  of  replacement  land  (irrigation  works)  and  its  further 
allocation to affected households; 
 Coordinates activities pertaining to vulnerable peoples’ identification and assistance; 
 Participates in difficult negotiations and general engagement; 
 Triggers compensation payments with sign‐off from the Land Access Lead; 
 Liaises with absentee co‐owners; 
 Triggers the involvement of the Legal Services Provider where warranted. 
 Coordinates social surveys and monitoring; 
 Coordinates livelihood restoration initiatives (and other Geoteam social programmes); 
 Coordinates activities pertaining to herders; 
 Supervises and audits information management. 
   
Negotiation Coordinator: based in the field, this individual is responsible for coordinating all 
survey activities and organises further negotiations and agreements. 
 
Survey and Negotiation Agents (two): based in the field, these persons conduct negotiations 
and surveys and input data into the information management system; these persons were 
recruited in the community and are allocated full time to the land acquisition activity for the 
duration of the exercise.  
 
GIS/database Specialist: coordination of data entry, quality insurance and verification (part 
time), generation of quantitative reports.  
 
Land  Acquisition  Lawyer:  liaise  with  the  Cadastre  and  notaries,  help  with  legal  matters, 
prepare and keep records of negotiation visits and meetings. 
 
Finance: coordination of payments (by financial director and existing collaborators within his 
department, part‐time). 
   

ZT520088  Version 10  Page 8.23 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
8.7 Development of the ESMS 
Lydian currently has in place separate management systems addressing the Environment / 
Social  and  Occupational  Health  /  Safety  disciplines.  It  is  the  intention  of  the  company  to 
integrate the ESMS with the OHSMS to conform to ISO 45001 DIS, as the project development 
advances, during the operational phase. Generally the two separate systems are well aligned 
and  follow  international  best  practices  for  management  system  implementation.    Lydian 
believes that having a management system framework in place is critical to ensuring effective 
Health, Safety, Environment and Community (HSEC) performance and management of the 
associated risks. 
 
8.7.1 Current Status of Management System  
The  initial  ESMS  was  developed  for  exploration  activities  in  line  with  International 
Organization  for  Standardization  ISO  14001:2004  Environmental  Management  Systems  – 
Requirements  with  Guidance  for  Use.    The  existing  ESMS  takes  into  account  the  legal  and 
administrative  requirements  of  Armenia,  the  IFC  Performance  Standards  and  the  EBRD 
Performance Requirements.   
 
Work is underway during 2016 to develop a revised ESMS that aligns with the more current 
version of ISO 14001:2015. During the construction phase the ESMS and OHSMS will remain 
separate  and  operate  under  ISO  14001:  2015  and  OHSAS  18001:2007  respectively.    The 
management plans, procedures, training matrixes and requirements have been developed for 
early works of the construction phase. 
 
The revised Lydian ESMS will also align with expectations outlined in ISO 26000: Guidance on 
Social Responsibility, and will address activities for the construction and operational phases 
of the Project.   
 
8.7.2 ESMS Objectives 
The objectives of the ESMS are to: 
 Establish environmental and social management standards that comply with or surpass 
statutory, industry, and reasonable community expectations;   
 Continually  review  and,  where  appropriate,  amend,  performance  criteria  to  reflect 
developments  in  technology,  statutory  requirements,  leading  industry  practice,  and 
social/community standards;   

ZT520088  Version 10  Page 8.24 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
 Facilitate  the  implementation  of  management  plans  as  defined  by  the  ESIA  for  the 
avoidance, minimisation and control of environmental and social impacts;  
 Inform Project personnel of their responsibilities with respect to environmental and social 
issues and to monitor the manner in which those responsibilities are implemented;  
 Train  Project  personnel,  contractors  and  community  representatives,  as  necessary,  in 
relevant environmental and social procedures, actions, and monitoring programmes; and 
 Audit business activities and working procedures and implement changes as needed to 
demonstrate that these objectives are being met. 
 
8.7.3 Implementation of the ESMS  
The ESMS establishes the framework that guides all environmental and social activities for 
the  Amulsar  Project.      As  required  by  IFC  PS1  and  EBRD  PR1,  the  ESMS  "is  a  dynamic  and 
continuous  process  initiated  and  supported  by  management,  and  involves  engagement 
between  the  client;  its  workers,  local  communities  directly  affected  by  the  project...  and, 
where appropriate, other stakeholders".   
 
The  ESMS  provides  a  methodological  approach  to  managing  the  environmental  and  social 
risks and impacts of the Project in a structured way on an ongoing basis.  The ESMS applies to 
all  Lydian  activities  in  the  Republic  of  Armenia,  including  the  Amulsar  Project  site,  any 
exploration activity elsewhere, and the Geoteam office located in Yerevan. Compliance with 
the ESMS is a requirement of all employees and contractors involved with Lydian, including 
its wholly‐owned subsidiary, Geoteam. 
 
Lydian’s ESMS is founded on the basic PLAN, DO, CHECK and ACT (PDCA) model, which is the 
foundation of most international management system standards for the past two decades, 
including  the  internationally  recognized  ISO  9001,  ISO  14001  and  OHSAS  18001  Standards 
(see Figure 8.5). 

ZT520088  Version 10  Page 8.25 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 

 
Figure 8.5: Basis of HSEC Management System 
 
The  ESMS  includes  17  elements  to  guide  environmental  and  social  management  activity 
(Figure  8.6).  Note  that  the  IFC  PS  and  EBRD  PR  are  embedded  within  the  Lydian  ESMS. 
Implementation of the ESMS is a means of ensuring that all commitments made in the EIA 
and ESIA are achieved (see Figure 8.6). 

ZT520088  Version 10  Page 8.26 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
STA 01 STA 02

HSEC Glossary of
Management System Terms and
Overview & Context Acronyms

LEADERSHIP
STA 03 STA 04

Leadership, Roles,
HSEC Policy Responsibility and
Authority

PLANNING
STA 05 STA 06 STA 07

Operational Management HSEC


Risk Management of Change Objectives

SUPPORT
STA 08 STA 09 STA 10 STA 11

Competance & HSEC Documented


Resources
Awareness Communication Information

OPERATION
STA 12 STA 13
Operational Emergency
Planning and Prepardness &
Control Response

PERFORMANCE EVALUATION
STA 14 STA 15 STA 16

Monitoring, Measurement, Internal Management


Analysis & Evaluation of
Compliance Audit Review

IMPROVEMENT
STA 17

Incident Investigation,
Nonconformity and
Corrective Action
 
Figure 8.6: Environmental and Social Management Activities 
 
The ESMS incorporates other documents of importance for ensuring that environmental and 
social risks are managed in a responsible manner and impacts are prevented or mitigated: 
 Environment Policy and Social Policy: Establishes the overall performance expectations. 
Commitments made in the Policies apply to all personnel in the organization, including 
contractors. 
 Environment and Social Objectives: Establishes specific areas of focus for improvement 
(all levels of the organization are involved in meeting the improvement expectations). 
 Registers: Serve as the means for documenting key areas of information such as risks and 
legal and other commitments. The Registers are administered by the Management Team 
and are updated on a regular basis as new information is obtained. 

ZT520088  Version 10  Page 8.27 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
 
The ESMS will be developed during the first and second quarters of 2016 and will be fully 
functioning and in place before early work commences on site in May 2016. 
 
8.8 Occupational Health and Safety Management System 
The Occupational Health and Safety Management System (OHSMS) is being developed on the 
basis  of  existing  Lydian  H&S  policies  and  the  Geoteam  Occupational  Health  and  Safety 
Management  Plan  (OHSMP)  in  accordance  with  the  elements  prescribed  in  OSHAS  18001.  
The OHSMS and OHSMP also embody the IFC & EBRD requirements (see Figure 8.7). 
 
OHSMS
OHS Glossary of Terms
Overview &
Management Plan and Acronyms
Introduction

1.0 POLICY
1.1

OHS
Policy

2.0 PLANNING

2.1 2.2 2.3 2.4

Operational Risk OHS Legal & Other Management


Management Objectives Requirements of Change

3.0 IMPLEMENTATION AND OPERATION


3.1 3.3 3.5 3.7

Resources, Roles, Competance Communication,


Responsibilities & Training & Participation & Documentation
Authority Awarness Consultation
3.2 3.4 3.6

Emergency
Control of Operational
Prepardness &
Documents Control
Response

4.0 CHECKING AND CORRECTIVE ACTION


4.1 4.2 4.3 4.4 4.5

Incident Investigation,
Monitoring & Evaluation
Nonconformity, Control of Records Internal Audit
Measurement of Compliance
Cor. & Prev. Action

5.0 REVIEW
5.1

Management
Review

Figure 8.7: Framework for Occupational, Health & Safety Management System 
ZT520088  Version 10  Page 8.28 
May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
It is important to understand that the OHSMS is a living document and that changes, additions 
and  deletion  in  the  plan,  Standards  and  Procedures  will  occur  on  a  regular  and  controlled 
basis. This includes the intention to combine the management systems under ISO45001 DIS, 
during the operational phase. 
 
The  purpose  of  the  OHSMS  is  to  provide  guidance,  Standards  &  Procedures  laying  out 
requirements for construction and operations to align with RA Laws, Lydian Policy, IFC PS, 
EBRD PR and GIIP. It will ensure Best Practice for the protection of staff, contractors, local 
communities, and the environment and culture. The OHSMS outlines the actions to be carried 
out  during  the  design,  supply,  manufacture,  construction,  installation  and  testing  of  the 
works, to ensure acceptable OH&S standards are maintained. 
 
The OHSMP sets out what needs to be done to accomplish our goal of ZERO HARM and will 
provide guidance to our behaviour‐based programme. 
 
The OHSMP will provide an overview of systems and processes that are focused on the goal 
of “Zero Harm”. It will outline the OH&S requirements for the Project Management Team and 
contractors associated with the project. 
 
It will further provide an opportunity for contractors with no established OH&S programmes 
to utilize this plan and its accompanying documents while working on the Project.  
 
The  OHSMS  will  be  designed  to  manage  and  mitigate  risk  exposure  levels  to  “As  Low  As 
Reasonably Practicable” (ALARP) throughout the Project. 
 
The  all‐encompassing  OHSMP  comprises  Management  Plans,  Standards,  Procedures  and 
training programmes that will be based on a combination of traditional safety & health and 
behaviour‐based health & safety allowing for a focused transition to more behaviour‐based 
aspects as the workforce development allows, while maintaining enough traditional systems 
to ensure compliance with the RA laws and other shareholders' requirements. More emphasis 
will be placed in 2016 on a “risk based system” approach to Lydian’s OHSMS, as behaviour‐
based systems are often criticised as too focused on “blame the worker” whenever things go 
wrong. 
 

ZT520088  Version 10  Page 8.29 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
A  new  standard  named  ISO  45001,  which  sets  requirements  for  occupational  health  and 
safety management systems, reached ISO Committee Draft stage in late 2014. It is anticipated 
that the final publication date of this new standard is set for late 2016. 
 
8.9 ESMP Development and Implementation 
8.9.1 Commitments Register 
Various environmental and social mitigation measures have been developed as part of the 
ESIA to manage and minimise potentially significant adverse effects to acceptable levels and 
to enhance Project benefits.   
 
These mitigation measures are collected and summarised in a Commitments Register (CR), 
which  lists  in  one  place  all  of  the  mitigation  and  management  actions  that  need  to  be 
undertaken by the Project with respect to environmental and social issues.  The CR enables 
Lydian to track its compliance with the ESIA.  However, the CR is not considered practical for 
public  issue,  because  it  includes  more  than  400  items,  some  of  which  reflect  relatively 
standard good mining industry practice.  Therefore, the ESIA includes (as Appendix 8.5) an 
abbreviated  version  of  the  CR:  the  Public  Commitments  Register  (PCR).    Commitments  on 
actions  to  be  undertaken  with  respect  to  detailed  engineering  design,  and  routine  on‐site 
management measures, are excluded from the PCR; the PCR includes only those items which 
are particular to the Amulsar Project and which will be of most interest to Project lenders, 
shareholders and stakeholders. The commitments will also include the permit conditions that 
relate to environmental performance of the Project, including: 
 Comply with construction normatives required by the Sevan Technical Committee for the 
protection of ground and surface waters; 
 Comply  with  the  requirements  for  the  translocation  of  Potentilla  porphyrantha,  as 
identified in the Permit application; and 
 Prior  to  2  years  before  mine  closure,  the  detailed  plans  for  plans  for  closure  and 
rehabilitation to be submitted. 
 
Lydian is committed to report annually on its HSEC performance, including on implementation 
and progress of the PCR.  
 
The full CR will be maintained as an internal document as part of the ESMS and will be used 
to  track  the  status  of  the  environmental  and  social  commitments.    It  can  be  organised  by 
Project  phase,  including  construction,  operations,  and  closure,  and  also  references  the 

ZT520088  Version 10  Page 8.30 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
location  within  the  ESIA  document  where  each  commitment  can  be  found,  for  contextual 
reference.  The intent is for the CR to be referred to constantly during all phases of Project 
implementation  and  environmental  and  social  training,  and  shared  with  contractors  as 
necessary.  It will be a live document that will cross‐reference other documents relevant to 
the Project as necessary (e.g. additional legal documents, requirements of lenders, and so 
forth).   
 
8.9.2 ESMP 
The Amulsar Project ESMP comprises a suite of discipline‐specific environmental and social 
management plans (Appendices 8.7 to 8.24).  Except in a small number of cases, each of the 
commitments listed in the CR (see above) which is also addressed within one or more of these 
management plans. The management plans describe how the commitments will be fulfilled, 
and how their fulfilment will be checked.   
 
A total of 20 management plans have been developed, including two health and safety plans, 
an  emergency  response  plan,  three  social  plans,  two  biodiversity  plans,  and  ten 
environmental  management  plans.  They  will  be  regularly  revised  as  required  and  in 
accordance with the ESMS & OHSMS standards.   
 
The  discipline‐specific  management  plans  which  comprise  the  Amulsar  ESMP  will  be 
implemented during construction and operation via the ESMS.  Linked to the plans will be 
operating  procedures  which  govern  how  the  plans'  requirements  are  implemented;  these 
may also include various forms, templates, checklists and work instructions.  This three‐tier 
arrangement is illustrated in Figure 8.8.   The three‐level structure is based on the premise 
that responsibility must be assigned to the individual or to the unit operation that controls or 
manages the operational procedures that can result in potential significant adverse effects.  
This individual or unit is therefore most able to respond and mitigate any occurrence requiring 
action. 
   

ZT520088  Version 10  Page 8.31 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
The ESMS 
The  ESMS  establishes  policies,  responsibilities  and  adaptive  management  systems  under 
which the ESMP is implemented. 
Level 1 
ESMS 

Discipline‐Specific Management Plans (MPs) (see Appendices 8.6 to 8.24) 


Level 2 MPs define site‐specific and issue‐specific management processes: 
 
Stakeholder Engagement Plan (SEP) 
Occupational Health & Safety Plan (OHSP) 
Footprint Management Plan (FMP) 
Level 2  Emergency Preparedness and Response Plan (EPRP) 
Discipline‐Specific  Transport Plan (TP) 
Management Plans  Cyanide Management Plan (CMP) 
Environmental Monitoring Plan (EMP) 
Integrated Waste Management Plan (IWMP) 
Air Quality Noise and Vibration Management Plan (AQNVMP) 
Community Health & Safety Plan (CHSP) 
Community Development Plan (CDP) 
Cultural Heritage Management Plan (CHMP) 
Preliminary Mine Reclamation Closure and Rehabilitation Plan (pMRCRP) 
Biodiversity Management Plan (BMP) 
Land Acquisition and Livelihoods Restoration Plan (LALRP) plus addendum 
Acid Rock Drainage Management Plan (ARDMP) 
Surface Water Management Plan (SWMP) 
Carbon and Energy Management Plan (CEMP) 
Workers Accommodation Management Plan (WAMP) 
Contractor Management Plan (CMP) 
 
Project Implementation Plan 

Level 3  Standard Operating Procedures (SOPs) 
Standard Operating  As  necessary,  each  Level  2  plan  will  contain  SOPs  providing  detailed  procedures  for 
Procedures  accomplishing site‐specific tasks 

 
Figure 8.8: Structure of ESMS 
 
As  described  in  Section  8.3,  a  “mixed  contract”  approach  to  construction  of  the  Project  is 
envisaged, potentially using a number of different contractors operating under different types 
of contract.  This presents challenges for implementation of the ESMP (in comparison with a 
ZT520088  Version 10  Page 8.32 
May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
single‐contract  strategy),  since  the  commitments  will  need  to  be  communicated  to  each 
contractor involved in their implementation.  Although Lydian retains ultimate responsibility 
for ensuring implementation of the ESMP, Lydian will expect its contractors to align and abide 
with its provisions.  To facilitate this, Lydian will adopt the following strategy: 
 Potential contractors will undergo a pre‐qualification process which will assess their 
competence in environmental and social management; 
 The key environmental and social commitments associated with the Project will be 
communicated to potential contractors at the tendering stage, potentially in part as a 
series of “Project rules”;  
 The  tender  evaluation  process  will  conform  to  the  requirements  Contractor 
Management  Plan  (see  Appendix  8.26),  which  includes  the  validation  of  the 
contractor’s consideration of environmental and social issues as well as safety and the 
contractor’s  policy  and  resourcing  commitments  (this  aspect  will  be  appraised  by 
members of the environmental and social team, reporting to Senior Manager HESS; 
and 
 HSEC  training  modules  will  be  developed  for  contractors  in  line  with  the  Lydian 
Training Plan for construction activities. 
 
Safety,  social  and  environmental  performance requirements  will  be  specified  in  all  Project 
contracts.  Larger  contractors  will  be  expected  to  draw  up  their  own  appropriate 
environmental and social management plans that are compliant with the Project ESMP, and 
provide specialist safety, social and environmental management staff who will work with the 
equivalent  Lydian  personnel.    Smaller  contractors  may  work  under  the  Lydian  ESMS  and 
ESMP.  In all cases, contractor compliance with the Project ESMP will be checked by Lydian 
personnel.  Certain elements of the ESMP, including biodiversity management, environmental 
and  social  monitoring,  stakeholder  engagement,  land  access,  livelihood  restoration  and 
community relations, will be the full responsibility of Lydian, as will ultimate responsibility for 
successful implementation of the ESMP. 
 
Lydian  has an  existing Compliance Assurance  Plan,  which was  used  during  the  exploration 
phase  of  the  Project  to  manage  both  its  own  and  its  contractors'  compliance  with  the 
exploration phase ESMP.  The main elements used to check compliance are: 
 Daily assurance monitoring  of site; 
 Weekly inspections of specific areas, activities or facilities;  
 Internal audits of departments and overall operation; and 

ZT520088  Version 10  Page 8.33 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
 External  audits,  as  required  by  stakeholders,  authorities  and  other  third  parties  as 
required.  
 
Daily monitoring is a routine, ongoing activity that is conducted as a normal and integrated 
part of department supervisors' job duties, whereas the weekly inspections use a checklist 
and are more structured.  Internal and external audits are carried out less frequently than 
inspections but are more formal and also aim to identify the adequacy of the ESMS. 
 
The Compliance Assurance Plan will be adapted and revised for the construction (and later 
operation) phase of the Project once the contracting strategy and arrangements has been 
finalised.    
 
8.10 Contractor Management Plan (see Appendix 8.26)  
The purpose of this forthcoming management plan is to outline how contractor compliance 
with the requirements of the ESMP will be assured, including to: 
 Define roles and responsibilities of Lydian and the contractor; 
 Identify  how  Project  environmental  and  social  requirements  and  commitments  will  be 
communicated during the tendering process; 
 Define  how  consideration  of  the  contractor's  environmental  and  social  management 
capabilities will be used to determine preferred contractor; 
 Define how the Project's environmental and social requirements and commitments will 
be incorporated into contracts;  
 Demonstrate the arrangements for environmental and social management during Project 
implementation, including division of roles between Lydian and the contractor;    
 Define compliance monitoring and reporting plans, including Key Performance Indicators 
(KPIs); 
 Define training requirements; and  
 Any other arrangements necessary to assure effective implementation of the ESMP under 
the contractual arrangement.  
 
The CMP defines the details of the contractor’s engagement processes to be implemented by 
Lydian, although it will not supersede the conditions detailed in the General Conditions for 
Goods and Services. The CMP will be reviewed annually to determine whether any changes 
or  updates  are  required  to  the  plan  unless  a  more  frequent  update  is  required  to  reflect 
changing  Project  design  or  procedures.  The  process  for  contractor  procurement  will  come 

ZT520088  Version 10  Page 8.34 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
into  effect  in  time  for  early  construction  works.  The  updated  version  of  the  Stakeholder 
Engagement  Plan  has  been  publicly  disclosed  on  the  Geoteam  website  and  the  Amulsar 
Information Centre (AIC).  Armenian contractors will also be informed of project commercial 
activities  and  general  information  through  announcements  made  by  the  Commercial 
Department. The Geoteam website will contain a link to a Commercial Activities webpage that 
will advise local, national and international contractors of forthcoming contract packages; the 
preliminary scope and requirements for each contract package will be indicated.   
 
Contractors  that  are  interested  in  becoming  pre‐qualified  for  consideration  on  upcoming 
contract  tenders  will  be  able  to  download  and  follow  the  pre‐qualification 
instructions.     Contractors  that  do  not  demonstrate  sufficient  levels  of  proficiency  in  the 
various  Pre‐qualification  Checklist  categories  to  pre‐qualify  for  commercial  activity 
consideration  will  be  informed  of  their  deficiencies  and  how  to  correct  them  for  future 
consideration.   
 
Contractors  that  pre‐qualify  will  be  informed  of  their  eligibility  and  listed  for  future 
commercial activity opportunities with the Geoteam.  Pre‐qualified and eligible contractors 
will be able access the upcoming contract tender packages through a link to the individual 
contract  description  webpage.   A  similar  process  will  be  developed  to  inform  local  and 
national  providers  of  the  opportunity  to  become  pre‐qualified  for  participation  in  future 
Geoteam purchasing opportunities. 
 
All pre‐qualified contractors will be required to participate in a two day workshop to explain 
and train them in the Geoteam’s Environmental and Social Management Plan (ESMP), the 
Occupational  Health  and  Safety  Management  Plan  (OHSMP)  and  the  Contractor  Selection 
processes  including  contract  bidding,  adjudication  and  award,  hiring  of  local  labour  and 
community relations requirements. The contract appendices will identify the environmental, 
social, health and safety requirements will be clearly identified. 
 
The Senior Manager HESS, or representatives, will be involved in the procurement process at 
all  stages  from  prequalification.  The  tender  evaluation  will  require  a  detailed  input  with 
respect  to  environmental,  social,  health  and  safety  in  combination  with  the  technical  and 
commercial aspects of the proposal. 
   

ZT520088  Version 10  Page 8.35 


May 2016 
 
 
Amulsar Gold Mine Project 
Environmental and Social Impact Assessment, Chapter 8   
 
8.11 Lenders Environmental and Social Action Plan 
The  ESIA  has  been  prepared  as  part  of  Lydian  commitment  to  responsible  corporate 
citizenship, but also as a requirement for financial institutions that are funding the project. It 
meets international standards required by Project Finance lenders, as well as Lydian’s own 
high standards for addressing environmental and social impacts. 
 
As a result of a due diligence review of the Amulsar ESIA performed by the Project’s Lenders, 
further  actions  are  likely  to  be  recommended  to  address  the  Project’s  environmental  and 
social assessment commitments under IFC PS 1 and EBRD PR1.  These recommendations will 
be  in  the  form  of  an  Environmental  and  Social  Action  Plan  (ESAP)  that  will  be  completed 
following the completion of the independent review of the ESIA by the IESC, pending final 
approval by Lenders.  The activities specified in the ESAP will be added to the CR as specific 
time  bound  actions  and  all  necessary  changes  will  be  incorporated  into  the  ESMP,  where 
required. 
 
The first independent audit of ESIA compliance shall be published and publically released at 
the end of 2016, tracking compliance with the commitments made, in particular per the ESAP 
and CR. 
 
 

ZT520088  Version 10  Page 8.36 


May 2016 
 

You might also like