Sunwal-Hakui Substation Subproject: Draft Environmental and Social Management Plan
Sunwal-Hakui Substation Subproject: Draft Environmental and Social Management Plan
Sunwal-Hakui Substation Subproject: Draft Environmental and Social Management Plan
PLAN
SUNWAL-HAKUI SUBSTATION
SUBPROJECT
Parasi District, Lumbini Province
CONSULTANT
NEA ENGINEERING COMPANY LIMITED
TRADE TOWER, THAPATHALI, KATHMANDU
NEPAL
AUGUST 2022
TABLE OF CONTENT
TABLE OF CONTENT.............................................................................I
LIST OF TABLES..................................................................................II
LIST OF FIGURES................................................................................II
LIST OF ANNEXES...............................................................................II
ACRONYMS AND ABBREVIATIONS.......................................................III
EXECUTIVE SUMMARY.........................................................................V
1. INTRODUCTION.......................................................................1
1.1 Project Background........................................................1
1.2 Scope of ESMP...............................................................1
1.3 Objectives of ESMP.........................................................1
1.4 Description of Subproject...............................................2
1.5 Legal Requirement for ESMP...........................................6
1.6 Methodology and Approaches of ESMP Preparation..........6
1.7 Classification of Impact Area...........................................9
2. EXISTING ENVIRONMENTAL CONDITIONS................................10
2.1 Physical Environment...................................................10
2.2 Biological Environment.................................................13
2.3 Socio-Economic, and Cultural Environment....................14
3. POTENTIAL ENVIRONMENTAL AND SOCIAL IMPACTS, AND
MITIGATION MEASURES....................................................................15
3.1 Beneficial Impacts........................................................15
3.2 Potential Adverse Impacts............................................16
3.3 Management Specifications for the Construction and
Operational Phases...............................................................24
3.4 Livelihood Support Activities.........................................30
3.5 Institutional Arrangement.............................................31
3.6 Grievance Redress Mechanism......................................31
3.7 Compliance with Environmental Laws and Regulations. . .35
4. MONITORING AND REPORTING MECHANISM............................36
4.1 Environmental and Social Monitoring.............................36
4.2 ESMP Implementation and Monitoring Cost....................40
5. CONCLUSION........................................................................41
REFERENCES....................................................................................42
ANNEXES.........................................................................................43
LIST OF TABLES
LIST OF FIGURES
LIST OF ANNEXES
The primary environment and social issues identified from the study are as
follows:
i. The substation land lies in the Terai region's flat plain area, which is slightly
depressed and adjoining the seasonal Turiya Khola. An estimated 85,203 cum
of spoil is necessary for filling the depressed substation land as a part of land
preparation for construction.
ii. During construction phase, issues of dust, noise and solid waste will arise but
the impact expected is minimal.
iii. There are no significant biological issues within the Subproject footprint area.
iv. NEA owns the proposed substation land. However, previous titleholders are
still cultivating the land and the crops might be affected by construction
activities.
i. Local people will be prioritized for employment and construction materials will
be purchased from the local market as far as possible.
ii. Boundary wall, retaining wall and embankment work adjoining to Turiya Khola,
compaction of spoil, adequate drainage system along Parasi Road and
sediment control traps and ditches will be constructed to control erosion and
inundation.
iii. Income restoration activities (skill development training) along with additional
assistance will be provided to the existing land users.
iv. Advance notice of one month will be given to the land users to harvest their
crops.
v. Loss of standing crops will be compensated.
vi. Additional financial assistance will be given to the previous titleholders.
vii. Avoidance of child labor, provision of equal wages for men and women, and
employment priority to socially backward community are advised.
viii. Preparation and execution of Environmental, health and safety plan by the
Contractor is recommended to address occupational hazard and safety related
issues.
ix. Use of insulation, guarding, grounding, electrical protective devices, and
industry-standard safe work practices are advised.
1. INTRODUCTION
1.1 Project Background
The proposed Distribution System Upgrade and Expansion Project (DSUEP) is
expected to enhance and expand the electricity distribution system to improve
the reliability (voltage level and reduction in power loss) and coverage of
electricity supply in the Sudhurpaschim, Karnali and Lumbini Provinces.
Upgradation of system efficiency and expansion of coverage area will improve
quality of life in the region, enhance economic activities, and reduce dependency
on petroleum and wood fuel. DSUEP will expand distribution lines of 33kV and
11kV in the three provinces as part of Government of Nepal (GoN)’s program “to
achieve affordable electricity fulfilling the demands at the local levels for all the
households by 2022”.
The European Investment Bank (EIB) has provided loan finance to 13 Subprojects
under DSUEP. Of these 13 Subprojects, based on the geographical locations, NEA
has clustered nine Subprojects in six districts of Lumbini Province, and five
Subprojects in three districts of Sudhurpaschim Province. The project will
construct 13 new 33/11kV substations, and 133 km long 33kV distribution lines
along with the installation of transformers.
Substation
The proposed substation 33/11 kV is of capacity 24 MVA. The major component
of the substation is power transformer, which is supported by the switchgear
components and Civil Structures. Map, layout, pictures of substation components
and other facilities are shown in ANNEX 1.
The substation land proposed (2.565ha) has already been acquired by NEA
(refer to ANNEX 2 for land ownership certificate).
During the implementation of Subproject, nearly 41 people will be
deployed for construction works on daily basis.
The major equipment used are Excavator (1), Roller (1), Drilling Machine
(1), and Crane (1).
For construction power, 1 Grid Supply- 120kVA Distribution Transformer
and 2 Diesel Generators (50kVA each) as alternate supply will be required.
The construction schedule is estimated to be 24 Months after awarding the
tender.
ii. Construction phase: The activities to be carried out during the construction
phase are:
Transportation of construction materials
Leveling of land area for the proposed substation
Construction of substation structures
Installation of equipment
iii. Operation phase: The activities to be carried out during the operation phase
are:
Operation of the Substation
Maintenance of Substation facilities and equipment.
1. Review of Literature:
The study started with the review of previous relevant reports, EIB’s
Environmental and Social Safeguard documents, ESMF for DSUEP and SES
(NEA), feasibility study reports, and relevant social safeguard documents
prepared by the NEA and consultant.
2. Site Inspection and Field Visit:
After approval of inception and screening report, ESMP study team visited the
site (refer to ANNEX 3 for field photographs) from 2078/06/05 to 2078/06/12
(21-28 September 2021). The necessary baseline data/information of physical,
biological, socio-economic, and cultural environment was collected through site
observation, testing (air/noise/water1), walk-through survey, consultative
meeting/discussion with concerned stakeholders within the Subproject footprint
area.
3. Stakeholder Identification:
Prior to stakeholder consultation, stakeholder identification and analysis were
done. The identified stakeholders are categorized in following three groups (
).
1
The air quality data was monitored by Temtop Airing-1000 PM Detector, noise by UNI-T UT 353 Mini Sound Meter (dB) and
water quality by EXTECH ExStik II DO600.
4. Public Consultation:
Local level stakeholders including the land users were notified through a notice
(ANNEX 4) from NEA consisting of objectives of consultation, venue, and time
requesting their presence in the consultation meeting. The notice was pasted in
Ward office and proposed substation area. The proof of notice pasting is
attached in ANNEX 5. The consultation meeting was conducted at the
Bakenawa, Ramgram Municipality-16 on 2078/06/07 (23 September 2021).
Hard copies of Subproject features and activities in Nepali language were
shared at the time of consultation. Each of the components, activities and
possible environmental-social issues during Subproject implementation was
briefed. The views/consent, concerns, recommendations/suggestions, and
demands of the participants were documented in the form of minutes. The
summary of consultation meeting minutes is given in table below and the copy
of minutes is attached in ANNEX 6.
Table 1-2: Summary of Issues, Comments and Suggestions Received
Dat Participan
Location Points from the Minutes
e ts
Ramgra Stakeholde The experts from NEA Engineering Company briefed us
m Mun. rs about the Subproject.
2078-06-07 (23rd
2
Referenced Meaningful stakeholder engagement: a joint publication of the MFI working group on environmental and social
standards / Reidar Kvam, PP-19, 2019. (Retrieved from
https://publications.iadb.org/publications/english/document/Meaningful_Stakeholder_Engagement_A_Joint_Publication_of_the
_MFI_Working_Group_on_Environmental_and_Social_Standards_en.pdf, January 2022) for stakeholder mapping process.
S
We inform that there will not be any negative impact
e
to the culture and livelihood of Tharu/Chaudhary,
p
Muslims, Janajati and other community by the
t
construction of the Subproject.
e
m
b
Source: Field Study, 2021
3
Ward is the bottom level unit under Government of Nepal. The Ward Chairman is an elected representative of ward
responsible for planning and budgeting at ward level, collecting and maintaining data of households, maintaining records of
public property, conducting child and environment-friendly programs, carrying out market monitoring and ensuring smooth
8. Report Preparation:
The draft report was prepared after incorporating all the comments and
suggestions obtained from local stakeholders based on field assessment,
impact identification, prediction and evaluation.
9. Disclosure of ESMP Report:
The final ESMP report will be disclosed on NEA and EIB’s web portal. At affected
local level, ESMP reports will be shared with concerned local level (municipality)
along with Ward office for disclosure to the authorities and stakeholders.
supply of essential goods and services, issuing letter of recommendation and certifying various documents related to personal
incidents, land, house, citizenship, etc.
The adjoining seasonal river Turiya Khola is meandering and seasonal in nature.
The proposed site is depressed with respect to Turiya Khola and the road.
Therefore, there is a high chance of flooding during the monsoon.
3. Climatic Condition
The proposed Subproject area belongs to the lower-tropical climatic zone. As
there is no meteorological station within the Subproject area, data recorded at
the nearest station, i.e., Bhairahawa Airport was taken as reference. The
minimum temperature recorded is 8.88 oC in January, while the maximum
4
https://un.info.np/Net/NeoDocs/View/6759, Retrieved on 29/05/2021.
The water quality of the Turiya Khola (stream) was found to be within the limit of
acceptance for the aquatic life in the stream as per Nepal Water Quality
Guidelines for the Protection of Aquatic Ecosystem.
5
National Indoor Air Quality Standard, 2009
6
National Ambient Sound Quality Standard, 2012
7
Nepal Water Quality Guidelines for the Protection of Aquatic Ecosystem, 2019
Proposed
Site
Figure 2-8: Seismic Hazard Map of Nepal Showing Proposed Project Site 9
The proposed Substation lies in semi-urban area. The waste was found littered in
front of houses, shops and business area near substation and Ramgram Bazar
8
Department of Survey (DoS) 2020
9
Department of Mines, and Geology, http://seismonepal.gov.np/publications, Retrieved on 2078/03/06(6/20/2021)
Figure 2-9: Location of Subproject area with respect to Nearby Protected Areas
During field visit, ten species of birds were recorded at project site, and its
peripheral area.
Table 2-6: List of Birds recorded within the Project Area
S.N Common/ Local
Scientific Name GoN IUCN CITES
. Name
1. Ghar Kaag (House Corvus splendens LC
Crow)
2. Dangre (Jungle Myna) Acridotheres fuscus LC
3. Gauthali (Swallow) Hirundo rustica LC
4. Dhukur (Spotted Dove) Streptopelia chinensis LC
5. Chil (Black Kite) Milvus migrans LC II
6. Bhangera (House Passer domesticus LC
sparrow)
7. Jureli (Black Bulbul) Hypsipetes LC
leucocephalus
A total of seven species of herpetofauna were recorded during field visit, which
includes five species of reptiles, and two species of amphibian.
Table 2-7: List of Herpetofauna Found in the Project Area
S.N Common/ Local
Scientific Name GoN IUCN CITES
. Name
1. Karet sarpa Bungarus caeruleus LC
(Common Krait)
2. Chhipkali (Common Hemidactylus frenatus LC
House Gecko)
3. Goman (Indian Naja naja LC
II
Cobra)
4. Chheparo (Oriental Calotes versicolor LC
Garden Lizard)
5. Paani sarpa/ Xenochrophis LC
Water Snake sanctijohannis
6. Bhyaguta (Asian Duttaphrynus
LC
Common Toad) melanostictus
7. Bhyaguta (Indian Hoplobatrachus LC II
Bullfrog) tigerinus
Source: Field Visit, 2021
Note: Least Concern (LC), and Appendix II lists species that are not necessarily now
threatened with extinction but that may become so unless trade is closely controlled.
The major health issues found are headache, Backache, Upper Respiratory Tract
Infection (URTI), Presumed Non-Infectious Diarrhea, Fungal Infection, Gastritis,
10
https://ramgrammun.gov.np/en/node/40, Retrieved on 2077/01/21 (04/05/2021).
The Substation area is under NEA entitlement and it does not consist of private
or public property, which needs relocation. Nevertheless, still, previous
titleholders (from whom NEA purchased the land) are cultivating the land. There
will be chance of loss of agricultural crops. However, the users have agreed to
stop cultivating crops (Table 1-2 and ANNEX 6) once the Substation construction
starts. The physical activities proposed for the Subproject (substation)
construction will not require land acquisition and resettlement.
This chapter identifies the possible environmental and social impacts in the
Subproject site that will arise during the construction and operation phase. All
the relevant environmental and social impacts associated with this Subproject
are sequentially illustrated in subsequent sub-headings along with their
mitigation measures.
B. Operation Phase
1. Enhancement in Rural Electrification
Impacts
Intermittent tripping and voltage drop problem nearby the area will be reduced.
The local economy will benefit through improved reliability of electricity supply,
B. Operation Phase
1. Issues Related to Electric and Fire Hazard
Impacts
Employees performing servicing or maintenance of substations may be exposed
to electric shock, burns and injuries from unexpected energization or release of
energy stored in the equipment.
Impact Rating: Significant (Table 3-1)
Mitigation/Enhancement Measures
• Shutdown shall be taken during maintenance work.
• Use of insulation, guarding, grounding, electrical protective devices, and
safe work practices is advised.
• Boundary walls and security fences around substation are must to prevent
unauthorized access.
B. Operation Phase
1. Bird Electrocution and Collision
Impacts
The Subproject area is located in semi-urban area and there is no presence of
important habitat of avian fauna. Although the electrocution can cause a risk to
bird species which perch on power line infrastructures (Substation).
Impact Rating: Insignificant (Table 3-1)
Mitigation/Enhancement Measures
• Provision of bird guards above the poles and white spirals in the
conductors to improve visibility (refer to ANNEX 1 for sample pictures).
A. Construction Phase
1. Impacts Associated with Transformation of Land
Impacts
The Subproject requires about 2.565ha of land for the placement of the
substation. The land belongs to NEA. The construction activities of the subproject
will not involve any private land instead could loss the standing crops cultivated
by the previous land users. There will be no land acquisition, and thus no
resettlement issues.
Impact Rating: Insignificant (Table 3-1)
Mitigation/Enhancement Measures
• Proper demarcation of the Substation area shall be done before initiating
construction activities to avoid potential conflict with local people.
• Advance notice of three month will be provided to users’ to harvest their
crops.
• Loss compensation of standing crops will be provided based on market
rate.
• Special assistance for income restoration activities will be conducted.
2. Issues Related to Child Labor and Gender
Impacts
During the Subproject construction, people will be employed on daily/monthly
wages for excavation, transportation of construction materials, and other
construction-related works. There might be discrimination on women and
vulnerable groups while hiring the worker and they might be provided less wage
11
E.g., at a distance of 10 meters from a single distribution line or conductor, electrical flux density drops to 1%
of the field strength at a distance of 1 meter from the conductor: 1/ (10*10) = 1%. Likewise, the magnetic field
drops to 0.1% of the field strength at the conductor: 1/ (10*10*10) = 0.1%.
Note: Direct (D), Indirect (I), High (H), Moderate (M), Low (L), Regional (R), Local (L), Site Specific (SS), Long Term (LT), Medium Term
(MT), Short Term (ST), Insignificant Impact (II), Significant Impact (SI), Very Significant Impact (VSI)
Institutional
Environmental Mitigation Costs Responsibility
Mitigation and Management Measures
Issues (NRs.) Implementat Supervisi
ion on
1. Beneficial Augmentation Measures
A. Construction Phase
1. Increased
Economic • Local people within the Subproject area will be prioritized Embedded within
Opportunitie based on qualification and skills. Construction NEA/PIU
Contract
s for Local • Construction materials, if available, shall be bought from the Contractor (DSUEP)
Document
People locally available legally operating market near Ramgram.
B. Operation Phase
NEA
Transmission
1. Enhancemen Operations
t in Rural • Proper and timely maintenance of the Substation will be done
- units and -
Electrificatio to maintain reliable power supply.
Distribution
n
Service
Center(s)
2. Reduction in
Green House • Proper and timely maintenance of the Substation will be done
NEA/PIU
Gas (GHG) to maintain reliable power supply so that people can continue - -
(DSUEP)
emissions the use of electricity.
Note: The provision of environment and social management cost should be included in the project cost making each item
visible in BOQ of bidding document for the safeguard compliance by the construction contractor.
12
NEA, 2019: Environment and Social Management Framework (ESMF) for Distribution System Upgrade &
Expansion Project (DSUEP), Kathmandu, Nepal; “Annexure 3 Entitlement Matrices”.
Contractor shall have the main responsibility to ensure the compliance. The
Contractor shall prepare an Environment, Health and Safety (EHS) report that
would be approved by DSUEP before field mobilization. They need to strictly
follow the EHS plan requirements. Contractor shall urgently comply with
corrective actions for any noncompliance as instructed by PIU. The ESMU of PIU
will provide safeguard and ESMP compliance orientation to all environment
monitors and safeguard team of the Contractor.
13
Grievance Redress Mechanism (GRM) Prepared for the sub-projects financed by European Investment Bank (EIB) under Distribution System Upgrade and Expansion
Project (DSUEP), Nepal Electricity Authority (NEA), August 2021.
The main objectives of the environmental monitoring plan are listed below,
To ensure that the Subproject baseline conditions were adequately
documented such that a comparative evaluation of the Subproject baseline
before, and after commencement of the Subproject could be made precisely
for impact evaluation.
To ensure that the mitigation commitments by the NEA for the minimization
of adverse impacts, and enhance the beneficial impacts, and the mitigation
measures, and enhancement program are complied, and implemented in
time, and with sincerity.
To confirm that the Subproject impacts are within the limits of the impact
prediction or not, and to minimize unpredicted impacts that occurred during
Subproject construction and operation.
14
Nepal Electricity Authority 2019: Environment, and Social Management Framework (ESMF) for Distribution System Upgrade & Expansion Project (DSUEP), Kathmandu.
15
Bennun, L., van Bochove, J., Ng, C., Fletcher, C., Wilson, D., Phair, N., Carbone, G. (2021). Mitigating biodiversity impacts associated with solar, and wind energy
development. Guidelines for project developers. Gland, Switzerland: IUCN, and Cambridge, UK: The Biodiversity Consultancy.
(https://portals.iucn.org/library/sites/library/files/documents/2021-004-En.pdf)
16
Calculated based on wage rate for unskilled worker (Man-days/Day) = NRs. 600.00 [Approved District Rate of
Nawalparasi (Bardaghat Susta West), DAO Nawalparasi, 2079 – Retrieved from
https://daonawalparasiwest.moha.gov.np/upload/ae46aadf6d62d202d6e69722dd0f2de5/files/
High_Quality_Jilla_Dar_Rate_FY079_80.pdf].
5. CONCLUSION
Potential environmental impacts of the Subproject are not diverse, mainly
relating to construction, and are all site-specific being confined to the Core
Project Area i.e., within the substation area. Civil works will cause temporary
impacts on air, noise and water, and occupational and community health and
safety, in particular related to working with electricity and crop losses. Key
impacts during operation and maintenance include safety risks related to the
presence of electricity infrastructure and associated risks at the substation. The
potential environmental impacts of the Subproject are identified and deemed to
be mitigated through adherence to national requirements and international good
practice measures and standards as specifically recommended in ESMP and DDR.
The implementation of ESMP and DDR is to be supervised and monitored by PIU,
supported by Project Supervision Consultant. The total ESMP and DDR cost
estimated for this Subproject is NRs. 71,18,870.00. This ESMP along with DDR is
considered sufficient to meet the environmental and social requirements for the
Subproject at present design conditions.
REFERENCES
Appendices
Appendix A: Pre-Start Information Pack, and Project Notification Approval
Appendix B: Sample health and safety plan format
Appendix C: Standard inspection, and report formats
Appendix D: Worksite safety checklists
Appendix E: Sample health, and safety signs
Appendix F: Site Drawing with Emergency Exit Layout
ANNEX 9: OCCUPATIONAL HEALTH AND SAFETY RELATED SIGNS
SIGNAL NOTICE
DANGER SIGNS
INSTRUCTION SIGNS
7. Soil and Soil and watershed conservation Act, 1982 expedient to make To do the works, which
Watershed legal provisions on the land and watershed conservation by can act, as causative
Conservation controlling natural calamities such as flood, landslide and soil factor of flood, landslide
Act, 2039 (1982 erosion and maintain convenience and economic interests of and soil erosion should
Relevancy with respect
SN Legislation Provisions
to Project
strictly be prohibited
AD)
the general public. during the construction of
this project.
Rationale of formulating and implementing this policy is to
create conducive environment that will self-motivate and
mobilize local institutions, rural energy user groups, non-
This project helps to
government organizations, cooperatives and private sector
Rural Energy improve the distribution
organization for the development and expansion of rural
8. Policy, 2006 and motivate to use the
energy resources. The government will facilitate and promote
electricity in rural areas of
to involve private development and expansion of new
western Nepal.
technologies. It has also envisioned subsidy provision for
promotion of such renewable energy technologies.
Child Labor
Child labor is strictly
(Prohibition and As per section 3 of this act, no child having not attained the age
10. prohibited in this project
Regulation) Act, of 14 years shall be engaged in works as a laborer.
and Contractor should
2056 (2000 AD)
follow this act.
11. Solid Waste This act has been formulated with a goal of minimizing solid This act provides the
Management Act, waste production from the target area by setting rules and overall framework to
2068 (2011 AD) regulation on solid waste management (SWM) in the country manage the solid waste
in order to develop better environment for the systematic and generated from
Relevancy with respect
SN Legislation Provisions
to Project
effective management of solid waste and to involve all the
concern stakeholders in SWM practice. The main features of
this act are discussion of 3R principle (Reduce, Reuse and
Recycle). 3R principle seems to be very beneficial as it not households to project
only increases the life of landfill site but also save the money, level. In addition, the
which could be used for other infrastructure development. proponent should manage
Section 4 of the act assign the local body to manage or use the waste generated
the solid waste discharged or dumped in collection center, during construction.
transfer station or treatment plant or collected during
cleaning.
I. PROJECT DESCRIPTION
A. Background
Distribution System Upgrade and Expansion Project (DSUEP), hereinafter referred
as “Project”) is expected to enhance and expand the electricity distribution
system to improve the reliability (voltage level and reduction in power loss) and
coverage of electricity supply in the Sudhurpaschim, Karnali and Lumbini
Provinces. The Government of Nepal (GoN) and Nepal Electricity Authority (NEA)
have agreed to receive loan financing from European Investment Bank (EIB) to
13 Subprojects under DSUEP. The Environmental and Social Management
Framework (ESMF) has provisioned that the Subprojects that are likely to have
environmental and social risks/impacts easily addressed through ESMP are
categorized as Category III Subprojects requiring Due Diligence Report (DDR)
along with ESMP report. The main objective of the E&S due diligence process is
to review any potential social issues and risks associated with the activities
related to the sub-projects. The Sunwal-Hakui Substation Subproject (hereafter
referred to as “Subproject”) is one of the 13 Subprojects being constructed under
DSUEP.
B. Subproject Component
This Subproject level environmental and social studies for DSUEP is focused on
the Component-I. In this Subproject, only one component is included.
a) 33kV Substation: The substation 33/11 kV of capacity 24MVA has been
proposed. The major component of the substation is Power Transformer of
ONAN/ONAF (Oil Natural Air Natural/Oil Natural Air Forced) cooling
mechanisms; which is supported by the switchgear (Circuit Breaker, Earth
Switch, Current Transformer, Potential Transformers) components and Civil
Structures like control building, guard house, staff quarter, switchyard,
boundary walls, internal access road, drainage and essentials.
V. SOCIAL IMPACTS
i. A 33kV substation is proposed in NEA’s land. At present, the previous land
titleholders are cultivating agriculture crops. The household income source
will be affected by the Subproject.
ii. No relocation impacts or impacts on structures and private land
acquisition are anticipated at any of the identified proposed Subproject
footprint area.
VI. ENTITLEMENT MATRIX
Capaci
Involuntary
ty/ Area Land Indigenous Proposed
Compone Resettleme
Lengt (Sq.m Owners People (IP) Mitigation
nts nt (IR)
Impacts
h with ) hip Impacts Measures
No.
The previous
titleholders are
from Tharu/
The land is
Chaudhary
owned by
community
NEA, which
cultivating
is
agriculture
cultivated
crops.
Construction of New Substation
by the
The users have
previous
given consent
titleholders. Appropriate
to use the
Of total financial
lands with an
land, only a assistance
advance notice
part will be and crop
Requir only.
used for loss
24 ed: No negative
NEA 33kV compensati
MVA/ 1 2.565h impact are
substation on will be
a envisaged on
constructio provided as
the religious
n. provisioned
sites,
No any in Table 3-
professions,
structures 10.
customary
are present
rights, religion
on the
and values of
proposed
Tharu/Chaudha
site.
A.
ry, Muslims,
No IR
and other
impacts are
community at
anticipated.
the time of
Subproject
construction.
IX. CONCLUSION
The due diligence study findings suggests that there are minimal social impacts
associated with the Subproject which will be addressed with minimal mitigation
measures. No relocation impacts or impacts on structures and private land
acquisition are anticipated at any of the identified proposed Subproject footprint
area except. NEA will address the total implementation cost as estimated in
Table 4-14.