IStructE Notes - Design Appraisal
IStructE Notes - Design Appraisal
IStructE Notes - Design Appraisal
1. Introduction
A new [x] storey height building [with a basement] is to be designed. [Site Location] + [Site
Condition] + [Site Restriction].
Two distinct and viable solutions will be proposed. One of the schemes will be recommended in
view of its function, safety and aesthetic.
2. Design Appraisal
With regard to the client requirement and site conditions, the following factors will govern the design:
Structural Consideration
1. Minimum Column a. Column grids should be designed to (x.xx m) c/c min
spacing specified
2. No of story? a. Progressive failure has to be considered if more than 5 story
3. Lift or staircase core a. The core wall is used for resisting gravity and lateral wind load
exist?
4. Length of building? a. Construction joint/ Expansion joint/ Movement joint/ Shrinkage strip may required
6. Gravity Load? a. Assume nominal superimposed DL as follows:
Finish Service Partition LL
Office 1.2 0.7 1
Residential 1.2 0.3 1
Roof 3.5 0.3 -
Carpark 1.2 0.6 -
Programme
1. Fast construction a. Pre-fabricated structural elements i.e steel, precast concrete
programme b. Have basement? Top-Down Basement construction
Design Appraisal
Performance Requirement
Provision of Joint
Torsion effect i.e asymmetrical arrangement of corewall
Durability i.e the design life
Exposure Condition
FRP i.e Size and minimum cover to reinforcement
1. F.R.P. Rating a. Provide sufficient concrete cover to BS8110 or fire proofing material to steel
elements (RC structures are preferred to long hour F.R.P.
f. Robustness
> 5 Stories
(Robustness – Since the building is of five stories (more than 5 stories) in height, it should be detailed so that
any vertical load-bearing element other than a key element can be removed without causing the collapse of
more than a limited portion close to the element in question. This can be achieved by:
1) Design the building to resist a minimum horizontal force.
2) Provision of tie (horizontal and vertical)
main beam and secondary beam can serve as a horizontal tie
Column & wall can serve as vertical tie
3) An alternative load path
Alternative load path is provided by the adjacent beams and columns
< 5 Stories
(Robustness – Since the building is of four stories (less than 5 stories) in height, the progressive collapse is
not critical in according to BS8110, but effective horizontal and vertical ties should be provided to ensure the
robustness.
For a properly designed and well detailed insitu reinforcement concrete structure, the tying requirements laid
down in BS 8110 are normally satisfied and progressive collapse will not occur.
All key elements and its connection should be designed to withstand an ultimate load of 34kN/m sq. from any
direction.
g. Other Consideration
1) Provision of Joint
2) Torsion Effect – Torsion effect due to the eccentricity of core walls will be considered in detailed design
stage
3) Durability
4) Basement (if any)
if underground water exists, special water proofing may be provided depend on the required level
of water proofing
If underground water do not exist, no additional waterproofing required.
2. Scheme Recommendation
In general, both schemes can satisfy the client’s requirements and site condition. However, considering the
following points, scheme [A] / [B] – “Scheme Title” is recommended.
3. Foundation Scheme
[Foundation Type] is chosen as the foundation for this project because of the following advantages:
must be taken.
4. The use of rock chisel to break the boulders will cause a slight settlement of the surrounding soil.
3. Basement Scheme
1) Basement wall
Lateral Load acting on Basement wall
a. Soil Pressure + Water Pressure
b. Surcharge (Road = 10kPa)
c. Ko value of
1) Sand =0.5
SURCHARGE SOIL
2) Clay =1
3) Normally consolidation clay = 0.75
4) Clay due to overburden of the gravel overlying the clay = 0.18
d. For simply supported, [ w in unit of kN/m ]
Maximum moment of triangular load
= 0.064wl2 per meter run
Maximum moment of uniform load
=0.5wl2 per meter run
2) Basement Slab
Uplift Pressure
a. Provide under drainage layer to release the water pressure
b. Design the basement slab to resist the uplift pressure
Ground Heave
a. Undercroft , 400 to 500mm to allow the heaving of clay
3) Water-Proofing (Depends usage of basement)
a. External Tanking (Can only be used under open cut construction)
b. Drain Cavity Wall (Expensive and Efficient)
c. Drain Cavity Slab (Expensive and Efficient)
d. Water bars (Must be provided in construction joint)
4) Construction and Temporary Retaining System
a. Construction: Bottom up construction vs Top Down construction
b. Temporary Retaining System
1)Open cut excavation
2)Soil berm + raking struts
3)Sheet-pile wall + king post + Flying shoring
4)Diaphragm wall
5) Overall Stability
a. How to resist the unbalance soil pressure?
b. How to resist the uplift water pressure?
4. Letter to Clients
Design Appraisal
5. Design Calculation
The main purposes of the following design calculations are to justify the section size, estimate required
reinforcement quantity for QS to estimate the cost.
Design Data:
Material:
Concrete (For Superstructure / For Foundation):
Grade : [35D/20] / [40D/20]
Strength : (fcu = 35N/mm2)
Density : 24kN/m2
Reinforcement:
Type : High yield deformed bar to BS 4449
Grade : 460
Strength : (fy = 460N/mm2)
Steelworks
Grade : 43A
Strength : (fy = 275N/mm2) For thickness =< 16mm
(fy = 265N/mm2) For thickness >= 40mm
Performance Requirement:
Design Appraisal
A) Durability
B) FRP
C) Concrete covers
Design Load
A) Loading Schedule (Finishes, Services, Partition and Live Load)
B) Wind Load
Choice of materials
1) Reinforced Concrete
Reinforced concrete is selected as the construction material for the sche me [A] / [B] because of the
following advantages:
Factors Concrete Advantages
Strength 1. Reinforced concrete system provides a high strength/low cost structure with good
rigidity and robustness.
Durability 1. R.C. is durable and provides a good resistance to weather and chemical attack.
Maintenance cost is low.
2. Good fire resistance is easily achieved by the cover requirement.
3. It is easily to apply waterproofing material to achieve different degree of
waterproofing.
4. It is easily to resist sulphate attack in substructures by specifying sulphate
resistance cement.
Insulation 1. R.C. has good sound and thermal insulation behavior.
Construability 1. R.C. is easy in construction and requires less skilled labors locally.
Availability 1. Both concrete and reinforcements are readily available locally, no procurement
period is required and hence more flexibility to accommodate late design changes.
Cost ($$) 1. In situ concrete is the cheaper construction material than [precast concrete] /
[steelwork]. The maintenance cost especially in leakage problem for in-situ
construction is lowest.
Programme 1. In-situ concrete construction is a convention method. It is readily available of
labour and materials on site. Moreover, the availability of experience R.C. designer
and detailer will shorten the overall design period which is still the shortest
comparatively. Besides, and latest design changes can be accommodated on site
easily. In practice, table form, pumping concrete.
Safety 1. In-situ concrete construction is easily to obtain its robustness. But, [steelwork
construction] & [precast concrete construction] are relied on proper detail and skill
of labours. Therefore, the workmanship and supervision must be highly controlled.
2) Steelworks
Structural steel is selected as the construction material for the scheme [A] / [B] because of the following
advantages:
Factors Structural Steel Advantages
Strength 1. High strength. High strength to weight ratio, suitable for long span structure.
Construability 1. Simplicity of assembly, all elements are prefabricated & delivered to site. Only
site welding or bolting will be required.
Cost ($$) 1. Steel construction can produce a light weight structure. (This is important in
some area where ground condition is poor. Therefore, shallow foundation can be
used and the foundation cost is reduced.
2. Overall economy may be achieved primary by reduction in erection time.
Programme 1. Fast construction, erection of steel structure can be relatively independent of
weather condition. Installation of flooring can keep pace with the remaining steel
structure. Floor construction may also be carried out at several levels
simultaneously using un-propped corrugated steel decking as permanent
formwork.
Safety -
Constructability 1. Skillful labours are required for fabrication, erection and welding.
2. Large area on site is required for storage of structural member prior to erection.
3. Fabrication needs heavy plant and crane operation.
Properties 1. Steel structure are sensitive to temperature change and vibration
Design Appraisal
2. Steel members will deflect appreciable under total load, needs pre-cambering.
Properties 1. Steel structure are sensitive to temperature change and vibration
2. Steel members will deflect appreciable under total load, needs pre-cambering.