ESTIMATE FOR FIXING STEEL ROD FENCING AT COMMISIONAR OFFICE PARK MORENA

SN ITEM QTY. RATE UNIT AMOUNT


.
1

2X70X0.30X0.30=12.60
2X16X0.30X0.30=2.88 15.48 116 cum 1796
15.48
2

2X70X0.30X0.60=25.20
2X16X0.30X0.60=5.76 30.96 4024 cum 124583
=30.96
3

16mmdia bar
4442.76 54.45 kg 241908
[email protected]/m=4442.76
4

2x70x1.50=210
249 527 sqm 131223
2x13x1.5=39
=249
2x2x70x0.40=112
2x2x16x0.40=25.60 137.60 1322 sqm 18907
=137.60

=681417.00
Add12%GST=81770.00
Total=763187.00
Say Rs.=7.64Lac

SUB ENGINEER SUB DIVISIONAL OFFICER EXECUTIVE ENGINEER


P W D MORENA P W D SUB DIV. MORENA P W D DIV. MORENA