Method Statement For Installation For Curtain Wall (Unitized)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 38
At a glance
Powered by AI
The document describes the method statement for installing hotel curtain walls, aluminium cladding and GRC cladding from level 36 to the roof.

The scope of work includes specification references, interfaces with other parties and outlines of the curtain wall, cladding and GRC panel installations.

The methodology describes the sequence, location, resources, training and provision of information for the installation work. It involves using a monorail system and gondola for accessing high levels.

Page : 1 of 24

Doc. No. : VHCM/MS/RF/001


Issue : 001
Date : 31-Aug-2006

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

METHOD STATEMENT

FOR

HOTEL CURTAIN WALL/GLAZING & ALUMINIUM CLADDING


AND GRC CLADDING INSTALLATION
FOR L36 ~ ROOF

FOR
PACKAGE 2120/3110 HOTEL CURTAIN WALL/GLAZING &
ALUMINIUM CLADDING AND GRC CLADDING INSTALLATION

FOR

VENETIAN MACAU

IN

COTAI, MACAU

Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

Page : 2 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

CONTENTS
1.

SCOPE OF WORK
1.1
1.2

2.

WORK METHODOLOGY
2.1
2.2
2.3

2.4
3.

5
5
5
5
7
7
8
9

Personnel ....
Plant ...
Material ..
Specialist Services .....
Supervision ....

10
11
12
12
12

ASSESSMENT OF SIGNIFICANT RISKS


4.1
4.2
4.3
4.4
4.5
4.6

5.

Time
Duration ..........................
Sequence .....
2.3.1
Curtain Wall Installation .....
2.3.2
Monorail Installation at Roof parapet....
2.3.3
Aluminium Cladding Installation ...
2.3.4
GRC Cladding Installation .
Location ......

RESOURCE REQUIRED
3.1
3.2
3.3
3.4
3.5

4.

Specification Reference 4
Third Party Interfaces ... 4

Access/Egress .....
Place of Work ....
Others at Risk .
Competence for Key Activities ....
Dangerous Goods, Noise, Manual Handling, etc. ..
Environmental Impacts ...

13
13
13
14
14
14

CONTROL MEASURES TO BE USED


5.1
5.2
5.3
5.4
5.5
5.6
5.7

Emergency Arrangements ..
Security ...
Third Party Liaison .
Work Instructions and Field Controls
Permits
Personal Protective Equipments .
Specialist Training ..

15
15
15
16
16
16
18
Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

6.

PROVISION OF INFORMATION
6.1
6.2
6.3

7.

Changes to Information .. 19
Confirmation of Emergency Arrangements/Drills . 19
Employee and Third Party Briefings .. 19

VERIFICATION RECORDS
7.1
7.2
7.3
7.4

8.

Page : 3 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

Initial Records Requirements .....


Records to be Taken During Construction .....
Completion Certificate Package .....
Filing Arrangements ...

20
20
20
20

APPENDICES
8.1

Hazard Identification Sheet

8.2

Risk Assessment Sheet 22

8.3

Sketches ..
A.
B.
C.

8.4

21

23

Sketch No. 2 Hoisting of Curtain Wall Unit


Sketch No. 2 Hoisting of Curtain Wall Unit
Sketch No. 2 Hoisting of Curtain Wall Unit

Evercrete Method Statement for Waterproofing Application ..

24

Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

1.

Page : 4 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

SCOPE OF WORK
1.1

Specification Reference
1.1.1 Design
1.1.2 Fabrication

- Technical Specification Clause 6.2


- Technical Specification Clause 6.3
- Technical Specification Clause 8
1.1.3 Material
- Technical Specification Clause 7
1.1.4 Workmanship - Technical Specification Clause 9
1.1.5 Galvanizing
- Technical Specification Clause 7.24.1
1.1.6 Site Testing - Technical Specification Clause 6.9, 10.3, 10.4, 10.7, 10.8
& 10.10 & 10.11
1.1.7 Safety
- Hong Kong Factories and Industrial Undertakings
Regulation, Code of Practice for Scaffolding Safety (HK)
and The Charters of Construction Safety and Hygiene
(Macau)

1.2

Third Party Interfaces


The curtain wall, aluminium cladding and GRC cladding installation for this project
is independently installed externally as a external faade system and will have no
direct interface with other trade except for internal finishing.

Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

2.

Page : 5 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

WORK METHODOLOGY
2.1

Time
The external facade system for L36 ~ Roof will be installed under normal working
hours. Night shift for installation will be required subject to the available of Tower
Crane and actual site progress.

2.2

Duration
The external facade system for L36 ~ Roof will be installed according to approved
installation programme.

2.3

Sequence
2.3.1

Curtain Wall Installation

2.3.1.1 Cast-in Embed


a.
b.

c.

d.

e.

Curtain wall insert placing to be carried out in accordance with


approved embed layout plan.
Check and inspect the installed inserts are in the correct location before
concrete pouring. Any inserts that are beyond the allowable tolerance
shall be rectified prior to concreting. FEA will issue inspection record
to Major Trade Contractor before each casting.
Survey and inspect the inserts after removal of formwork. Any inserts
that are out of tolerances will be highlighted and submitted to Major
Trade Contractor for record.
Any curtain wall insert which is out of nominal position by a
dimension greater than +/- 15mm in any direction due to concrete out
of tolerance shall be recorded, and submitted for consultant's review.
Any remedial works must be approved by consultant prior to execution.

2.3.1.2 Setting Out


a.

b.

c.

A set of reference grid lines and level datum to be provided by the


Major Trade Contractor. Accuracy verified by joint surveying between
FEA surveyor and Major Trade Contractor's building surveyor.
The setting out of the curtain wall floor by floor, will be carried out in
accordance with the agreed set of reference gridlines and level datum
throughout the whole building.
Assign a set up floor for every five floors where optical laser surveying
instrument will be engaged to layout the reference lines of the curtain
wall.

Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

d.

Page : 6 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

Curtain wall reference and anchor locations at intermediate floors will


be set out with the aid of wires tensioned between set up floors. (Level
reference on all floors will be transferred by optical level).

2.3.1.3 Bracket Installation


a.
b.

c.
d.
e.
f.
g.

Clean the top face of pre-cast imbed by wire brush to remove dust and
cement slag.
Major Trade Contractor to make-good any uneven concrete surface at
insert location to achieve a smooth bearing surface prior to bracket
installation.
Install the bracket onto the embed by fixing.
Set the bracket in accurate in and out position and tighten the anchor
bolts.
Set the aluminium serrated plate on accurate level and tighten the
anchor bolts.
Double check the set curtain wall anchors for accuracy.
Torque check of bolts on fixing (As per ITP plan).

2.3.1.4 Curtain Wall & Aluminium Cladding Installation :


a.
b.
c.
d.

e.
f.

g.

h.
i.

j.

Curtain wall units are unloaded onto the Loading Platform on 38/F as
for temporary storage until they are required for installation.
During storage on site, the units will be covered with plastic sheet.
A special custom made double track monorail system will be used and
set up on top of roof parapet wall.
An electric chain block of SWL 1.0 will be mounted onto the steel
monorail track. The complete system shall undergo safety load test by
an independent qualified party and test reports/statutory forms are then
submitted to Main Contractor for record.
To install fire insulation according to approved shop drawing at top part
of concrete beam surface prior to curtain wall installation.
Curtain wall units are then hoisted up from the Loading Platform by
means of this monorail and electric chain block and place in position at
floor edge for fixing to the pre-installed anchor brackets.
Upon final adjustment of the units by means of dummy level,
theodolite, and torque checking (as ITP plan), tightening the fixing
bolts to its correct torque by torque check test on site with RE / MTC &
SSC relevant QA personnel to witness of inspection.
Proceed with next curtain wall unit installation and seal all gutters as
per approved shop drawings details.
A 100% flood test to the gutters shall be carried out by Factory for a
period of no less than 24 hours without water seepage. Take record and
send to site together with unit delivery for site reference.
Install EPDM flashing and seal up the curtain wall system as a
waterproof barrier.
Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

k.

l.

Page : 7 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

Install thermal, acoustic insulation to the curtain wall. Inspection to be


carried out by TCs QA personnel (as per ITP plan) and witnessed by
relevant RE/MTC personnel for the satisfactory of the pre-installed fire
insulation prior to the g.m.s. smoke seal installation.
Workers will install the curtain wall unit mainly inside the building
except for the two End Wall and blind wall which will be carried out by
using gondolas.

2.3.2 Monorail Installation at Roof Parapet


a.
b.
c.
d.
e.
f.

2.3.3

Design Drawing and Calculation will be submitted for approval prior


for work execution.
The monorail system will be pre-fabricated and assembled in
individual support frame.
The pre-assembled monorail support frame and tracks will be hoisted
up and be installed using Tower Crane on top of roof parapet.
To fix the connection between monorail and separate tracks and ensure
the bolts are tightened.
Repeat Step c d to complete installation of remaining of monorail
system.
The monorail will be inspected by RPE with valid certificate before
use.

Aluminium Cladding Installation

2.3.3.1 Cast-in Embed


Refer to 2.3.1.1
2.3.3.2 Setting Out
Refer to 2.3.1.2
2.3.3.3 Apply Water Proofing
Please refer to Appendix - Evercrete's Method Statement. And the survey
concrete surface to be carried out. And make good action by MTC (if any)
to the satisfactory of the consultant before waterproofing.

2.3.3.4 Aluminium Cladding Installation


a.
b.

Carry out remedial works to cast-in embed where necessary.


Apply waterproofing onto concrete surface before any fixing of
brackets. No installation should proceed without inspection by MTC.
Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

c.
d.
e.
f.

g.
h.
i.
2.3.4
a.

Page : 8 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

Fix S/S brackets to pre-cast channel by bolts and nuts or welding.


Set the brackets in accurate in and out position and tightening the
anchor bolts.
Torque checking to ensure the sufficient strengthening of bolts (as per
ITP plan).
Adjust the vertical plumbing, alignment and leveling for the hook on
brackets in accordance with setting out line and approved shop
drawings.
Hoist and install aluminium cladding panels.
Apply caulking sealant to joints where applicable as shown in
approved shop drawings.
Final cleaning to be carried out upon instruction received.
GRC Cladding Installation
Cast-in Embed
l These permanent GRC cast-in-embeds are to be supplied by the
specialist GRC supplier to the MTC for installation in accordance with
the approved layout shop drawings and required delivery schedule.
l These installed cast-in-embeds will be inspected against the correct
location jointly by GRC supplier and MTC prior to concreting, in
accordance with the GRC suppliers approved shop drawings.
l Survey and re-inspect cast-in-embeds after removal of form work by
the GRC supplier.
l Should any embeds be found cast with excessive tolerances, the GRC
supplier should submit remedial method statement and must be
approved by MTC/ Consultant Team prior to commencement of
remedial works by MTC.
l The curtain wall and aluminium cladding sub-contractor to commence
water proofing works to concrete surface.

b.

Setting Out
Refer to 2.3.1.2

c.

Apply Water Proofing


Please refer to Appendix - Evercrete's Method Statement. And the
survey concrete surface to be carried out. And make good action by
MTC (if any) to the satisfactory of the consultant before waterproofing.

d.

Mobilization:
- GRC panels will be hoisted up from Ground Level to podium roof
by means of the 280 Ton jib crane (by others) situated at South-East
corner of the building.
Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

Page : 9 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

- Once landed on podium, the GRC panel will then be hoisted by Roof
tower crane to the roof level.
- Once landed on tower Roof, the Roof tower crane will help to
distribute the panel to the appropriate location.
- All GRC will be installed by using of Tower Crane from interior of
the parapet wall to the exterior of parapet wall, and drop down for
installation.
e.

Installation procedure:
l Inspect water proofing on concrete surface.
l Install fully pre-assembled steel sub frame and bracket in correct
position by using the monorail on top of roof parapet.
l Torque checking to ensure the sufficient strengthening of bolts (as per
ITP plan.
l To remove the monorail tracks prior for GRC installation.
l Install GRC panels by means of Tower Crane with workers working on
gondola in zig-zac side set arrangement.
l Banksman will co-ordinate with tower crane operator during
installation.

2.4

Location
The curtain wall, aluminium cladding and GRC cladding installation will be carry
throughout the whole external faade of the Hotel building from L36 to R/F.

Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

3.

Page : 10 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

RESOURCE REQUIRED
3.1

Personnel
a.

Deputy Project Director (one no.)


He will overall monitor and responsible for the project.

b.

Project Manager (one no.)


He will overall monitor the project for the progress as well as site
safety.

c.

Assistant Project Manager (one no.)


He will assist project manger to monitor site progress as well as site
safety.

d.

Designer Engineer (one no.)


He will be responsible for the design of the monorail to comply with
all requirement.

e.

Site Manger (one no.)


He will overall monitor the site team members for the execution of site
work.

f.

QA Officer (one no.)


He will responsible to ensure all the quality of the site works including
installation and materials to match with the required standard.

g.

Safety Supervisor (three nos.)


He will be responsible for site safety to ensure all working procedures
are in a safe working environment.

h.

Surveyor (three teams three nos./team)


They will layout all required reference lines for the installation of
monorail system prior work commencement.

i.

Supervisor (three nos.)


They will be responsible for site work execution and ensure all works
are properly done according to approved shop drawing.

j.

Logistic Supervisor (one no.)


He will be fully responsible for all materials transportation either from
factory/supplier to off-site storage or from off-site storage to site.

k.

Storekeeper (one no.)


He will be fully responsible for all materials and equipments/tools
stored at site store house.
Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

3.2

Page : 11 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

l.

Banksman (eight nos.)


They will be fully responsible for the co-ordinations with Tower Crane
operator and other lifting appliances operator for material hoisting,
loading and unloading.

m.

Rigger (five teams 6 nos./team)


They will be fully responsible and co-ordinate with banksman for the
hoisting, loading and unloading of all materials.

n.

Ganger (five teams 2 nos./team)


He will be the team leader of installers team to lead their team
members to install the works according to approved shop drawing.

o.

Installer (five teams 4 nos./team)


They will install the following works according to approved shop
drawing.

p.

Waterproofing Applicator (four teams 2 nos./team)


They will carry out the waterproofing works to external wall.

q.

Electrician (two nos.)


They will carry out all the installation, frequent checking and
maintenance of electrical equipments.

r.

Caulker (six teams 2 nos./team)


They will carry out all the sealant application works.

s.

General Labour (five teams 4 nos./team)


They will carry out all the miscellaneous works on site such as
housekeeping, distribution of parts, protection to installed faade,
safety facilities set up and etc.

Plant
a.
b.
c.
d.
e.
f.

Tower Crane (provided by Major Trade Contractor)


280 Ton jib crane (by others)
Double Track Monorail System on top of roof parapet
Electric Chain Hoist: SWL 1.0 MT
16 sets
Temporary Gondola
36 sets
Lorry Crane (Inland Transportation) 2 lorries.

Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

3.3

Page : 12 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

Materials
All materials to be used will be clearly stated in our approved shop drawing.

3.4

Specialist Services
Not applicable for this Method Statement.

3.5

Supervision
a.

Our site manger will carry out a briefing to all team members to explain all
working procedures as well as site safety prior to work commencement.
b. Our supervisor will full time supervise the work to ensure all works are done
according to approved shop drawing.
c. Our Safety Supervisor will check the work at the following stages:
i) Stage 1 before work commencement
l To ensure all workers are equipped with proper personal protective
equipments.
l To ensure the workplace is in a safe working environment with proper
access.
l To ensure all scaffolding and loading platform to be obtained with
valid certificate.
l To ensure all lifting appliances and gears are in a safe order with valid
certificate.
ii) Stage 2 during working
l To check all workers are wearing proper personal protective
equipments.
l To check all workers are working in a safe manner.
iii) Stage 3 after work completion
l To ensure all debris are clear off.
l No oil / grease remained in the workplace.
l No fire source left on the workplace.

Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

4.

Page : 13 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

ASSESSMENT OF SIGNIFICANT RISKS


Our Assistant Project Manager and Site Manager together with our Safety Supervisor will
carry out risk assessment to identify the effective procedures and practices and the possible
situations where the plant or associated systems of work may pose hazards.
Risk assessment will be recorded with detailed precautions. It should be used to formulate
clear instructions for all persons involved.
Foreseeable hazardous operations associated with this project are summarized as follows:
4.1

Access/Egress
l
l
l
l

4.2

Place of Work
l

l
l

4.3

All access/egress to be kept clear without any obstructions.


Report to Major Trade Contractor for any obstructions/unsafe condition in
main road access.
To ensure a proper access to allow workers to get in/out from working
platform and scaffolding.
To frequent check all access/egress to be maintained in a clear access free
from obstruction.

All work areas must be kept clean and orderly. Rubbish, debris, waste and
useless material constitute a fire hazard, as well as a potential tripping
hazard on the job, and must be removed from work areas as fast as they
accumulate. Areas for temporary accumulation to be provided by Major
Trade Contractor for dumping of debris.
All work areas must be kept clean and free from loose material and trash.
Storage and stacking areas must be kept in an orderly condition to allow
safe access to the materials. Access road to site office and site store must be
kept clear and clean.
Stacking of materials shall be properly arranged and not placed at access
and egress.
All management and supervisory personnel are required to carry out
continual health and safety surveillance and take immediate steps to remedy
defects or unsafe practices they observed.

Others at Risk
l
l
l

To establish a scheme for precaution for working or work suspension during


Tropical Cyclones and Heavy Rainstorm.
To notify and monitor all visitors including driver & labour of material
transportation to wear proper personal protective equipments.
To notify and monitor all drivers of all vehicles will be in possession of a
valid license for the class of vehicle they drive.

Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

4.4

Page : 14 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

Competence for Key Activities


All competent person and workers to be recorded in a List of Competence of Work
as per Major Trade Contractors standard form and be submitted to Major Trade
Contractor for Record. The List shall include the following works;
l
l
l
l
l
l
l
l
l

4.5

Safety Supervisor
Scaffolding erection and dismantle
Welding Works
Gondola regular inspection
Fork Lift Driver License
Abrasive wheel
Cartridge operation
Test Laboratory for Weld Test/Embed Test
RPE for checking of Lifting Appliances and Gears

Dangerous Goods, Noise, Manual Handling, etc.


Netfortune will establish and maintain procedures designed to control risks arising
from handling, storage, use and disposal of substances hazardous to health
The procedures will be based on a requirement contained in the respective
procurement process for every supplier of a hazardous substance to provide the
relevant substance hazard information
Netfortune will supervise and monitor the implementation of the procedures which
will include, but may not be limited to:
l
l
l
l

4.6

establishing an inventory of all hazardous substance.


maintaining a file of relevant supplier hazard data information.
carrying out an assessment of the proposed handling, storage and use of the
hazardous substance and completion of an assessment report detailing the
hazards and any necessary precautions.
ensuring that personnel exposed to hazardous substances are provided with
written safety and health instructions, training where appropriate, and
observe the precautions therein.

Environmental Impacts
l
l
l
l

All work areas must be kept clean and orderly.


To keep the work place free from oil/grease.
To ensure workers to wear ear protector for drilling, hacking and etc that
works would cause noise exposure.
Apply permit to work for any works carried out at night.

Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

5.

Page : 15 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

CONTROL MEASURES TO BE USED


5.1

Emergency Arrangements
l

l
l

l
l

5.2

Security
l
l

5.3

The Company will follow the Major Trade Contractors emergency


procedures and participate in drills for emergency situations, including
rescue operations. The foreseeable emergencies would include, but may not
be limited to fire, persons falling from height, falling object onto persons,
persons injured and/or stranded aloft.
The Companys Site Safety Supervisor shall be also act as emergency
coordinator and shall keep close contact to Major Trade Contractors
appointed Emergency Coordinator.
In case of emergency on site such as fire, flooding or collapse of equipment
plant, all employees at the workplace shall stop the work immediately and
inform our Site Safety Supervisor or directly report to the Major Trade
Contractors Emergency Coordinator and follow their arrangements and
instructions. In the meantime our Site Safety Supervisor will also report to
our Project Manager for details of the emergency incident.
Incident Report will be prepared by our Project Manager with assist of Site
Safety Supervisor and be submitted to Major Trade Contractor within 24
hours.
Our Project Manager should debrief the site personnel and instruct how to
prevent the similar recurrence.

All security services/facilities to be provided by Construction Manager /


Major Trade Contractor to maintain a clean and ordered site condition.
To follow all in-house rules established by Construction Manager / Major
Trade Contractor.

Third Party Liaison


All sorts of communication including work instruction and documents will be sent /
received through Major Trade Contractor and Major Trade Contractor will further
distribute / collect to the associated parties.
All co-ordination with other trades will be arranged by Major Trade Contractor for
all interfaced works.
Attend all required meetings with appropriate persons held by Major Trade
Contractor.
Both Netfortune, Major Trade Contractor and associated parties should keep a fast
and close communication to reflect / report all the site conditions such as unsafe
working condition, incidents or accidents to maintain a safe working environment.
Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

5.4

Page : 16 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

Work Instructions and Field Controls


Work instruction and field control briefing will be carried out to all team leaders by
our Site Manager to explain all the working procedures, installation method,
precautions during working and associated site safety prior to work commencement.
The briefing shall be included for all sequence of work, document / permit required,
special training for particular work, plant & machineries to be used, any dangerous
substances involved, key environment control, significant health & safety hazard
and controls. This briefing shall be acknowledged by all team leaders to realize the
actual site condition and working process as well as site safety in order to ensure all
works to be carried out in a smooth and safe condition.

5.5

Permits
The followings shall be obtained permit from Major Trade Contractor /
Construction Manager according to their rules:
l
l
l
l
l

5.6

All welding / gas cutting works


Working at night
All vehicles in / out of the site
Material in / out of the site
All persons in / out of the site

Personal Protective Equipments


Adequate supplies of suitable PPE will be maintained by the Company and his SubContractors, who will each ensure that the appropriate PPE is issued to and used by
their respective project personnel and authorized visitors. The provision of PPE
will be in accordance with the relevant statutory requirements contained within, but
not necessarily limited to: *
*
*
*
*
*

The Factories and Industrial Undertakings Regulations


The Factories and Industrial Undertakings (Confined Spaces) Regulations
The Factories and Industrial Undertakings (Protection of Eyes) Regulations
The Construction Sites (Safety) Regulations
The Noise Control Ordinance
Charters of Construction Safety and Hygiene

Where reasonably practicable, consideration will be given to the individuals


preference on the selection of P.P.E. including its comfort factor.
The Company and each of his Sub Contractors will establish suitable procedures to
record the issue of each item of PPE to an individual. Every person, including
visitors, issued with an item of PPE will be required to sign a receipt, a copy of
which will be retained in a dedicated file by the Company.
Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

Page : 17 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

The Company will provide secure, adequate and sanitary facilities for the storage of
PPE both before and after issue to their respective personnel.
All personnel will be informed at the time of issue, of the need to maintain the
equipment properly and hygienically and to immediately report any defect or
damage of the PPE. They will also be provided with instruction on the proper use
and maintenance of the equipment where appropriate.
Depending on the work activity of each Sub Contractor and their respective
personnel, the types of PPE that will require to be issued on the project will include
but may not be limited to: Safety helmets:

With the exception of site office compounds, the whole site


is regarded as a hard hat area and the wearing of helmets is
therefore mandatory. All helmets will comply with British
Standard BS 5240 or an equivalent Hong Kong standard
acceptable to the Factory Inspectorate. Where personnel are
exposed to windy conditions their helmets will be fitted with
chin straps.

Safety belts:

All personnel working at height where it is impracticable to


provide a working platform will wear a full body harness,
secured to an adequate anchor point by a suitable lanyard.
Safety harnesses will be manufactured and tested in
accordance with British Standard BS 1397 or an equivalent
Hong Kong standard acceptable to the Factory Inspectorate.
Lanyards manufactured and tested in accordance with the
foregoing standards will be used in conjunction with the
body harnesses specified above. When connected directly to
a static anchor point a lanyard of up to but no longer than 2
meters may be used. When connected to inertia reel block or
running line a lanyard of up to but no longer than 0.6 meters
may be used
Inertia reel blocks may be used in combination with a body
harness and 0.6 meter long lanyard. If an inertia reel block is
to be used it will be securely fixed to a suitable anchor point.
Where fall arrest equipment is issued, its use, examination,
maintenance and replacement will be in accordance with the
manufacturers recommendations. Personnel issued with
such equipment will inspect it daily to ensure its continued
serviceability and report any defects immediately to their
supervisor. The equipment will be examined by a competent
person at intervals specified by the manufacturer. A record
Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

Page : 18 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

of such examinations will be made and kept in a dedicated


file.
Protective Boots:

All personnel in construction and works areas will be


required to wear stout footwear, preferably with steel toecaps
and midsoles.

Gloves:

All personnel will be provided with suitable protective


gloves to prevent injury from handling sharp, abrasive, toxic
or other hazardous materials of substances.

Reflective Waistcoats: All personnel will be provided with high visibility reflective
waistcoats, vests or belt for the importance that they are
easily seen while working beside the roads. Each holder to
ensure their continued high visibility will regularly clean the
waistcoats.
Every person issued with PPE is initially responsible for using & maintaining the
equipment and inspecting it regularly to ensure that it remains fit for its intended
use. The Company will also ensure that his sub-contractors regularly monitor the
use and condition of PPE issued to project personnel.
The failure of any individual to use the PPE provided as directed by their employer
is subject to disciplinary action, which may result in the offenders dismissal from
the site.

5.7

Specialist Training
Not applicable for this Method Statement.

Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

6.

Page : 19 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

PROVISION OF INFORMATION
6.1

Changes to Information
All changes of information to be received will be recorded in 1st priority and be
filed & registered in an independent file. Such kind of information will be distribute
to all concerned team leaders and QA personnel at once to ensure all the
information they kept to be up-to-date.
A meeting / discussion will be held as soon as possible to review the change of
information and be explained by our Project Manager / Assistant Manager to ensure
all team leaders and QA personnel are fully understand the contents of change.
The relevant information of changing will immediately inform to MTC and get
approval of relevant parties involved.

6.2

Confirmation of Emergency Arrangements/Drills


Any emergency arrangement / drills received from Major Trade Contractor will be
recorded at once.
Our Site Manager will directly inform all team leaders for such arrangement during
daily briefing and instruct all team members to participate the arrangement on time
and that arrangement will also be announced in our site notice board to recall all
team members.

6.3

Employee and Third Party Briefings


Any particular briefing held by third party will be announced by our Site Manager
to all team leaders during daily briefing and be recorded in our site notice board to
recall all team members to participate the briefing on time.

Rev. 0

Page : 20 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

7.

VERIFICATION RECORDS
7.1

Initial Records Requirements


The following records will be classified in independent file for future checking and
submission:
l
l
l
l
l
l
l
l

7.2

Request for Inspection


Site Test Reports
Mill Certificates
Material Delivery Notes
Welders Certificate
Approved Shop Drawing
Approved Changing Record of Shop Drawing
Approved Revise Method Statement.

Records to be Taken During Construction


Inspection Checklist (Appendix).

7.3

Completion Certificate Package


The following certificate will be submitted in package after work completion:
l
l
l
l
l
l
l
l
l

7.4

Site Test Reports


Mill Certificates
Welders Certificate
As-Build Shop Drawing
Gondola Certificate
Monorail Test Report
Hoisting Machine Certificate
Pull Out Test Report
Water Test Report

Filing Arrangements
a. All documents will be classified and be kept in different files.
b. Originals will be sent back to our main office for master filing.
c. Project documentation and records shall be maintained until the completion of
the project.

END
Rev. 0

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

8.

Page : 21 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

APPENDICES
8.1 Hazard Identification Sheet

Rev. 0

Hazard Identification Sheet

Netfortune Engineering (FEA) Macau Limited


01

Review No.
Project :
Work Package :

Date

31 Aug, 2006

J3039 Venetian Macau in Cotai, Macau


3110 Hotel Curtain Wall/Glazing & Aluminium Cladding And GRC Cladding Installation

Item

Job Task

Loading, unloading and


distribution of materials

People Affected
Rigger, Labourer

Hazard

Cause of Hazard

Injury caused by
manual handling

Improper Manual
handling Method

Falling objects due


to lifting failure

Improper Lifting
method

Worst Harm Due to


Hazard
Back and Hand
injury

Fatality

Existing Control Measures


-

Cast-in embed checking

Surveyor

Fall from height


while working on
formwork platform

Working at height

Fall from height


while working on
gondola

Working at height

Fatality

Fatality

Falling objects from


platform/gondola

Working at height

Fatality

Page 1 of 4

Analysis by : Yeung Ka Wah / Ricky Ip

Ref. : VHCM/HI/RF 001

Activity : Curtain Wall, Aluminium Cladding And GRC


Cladding Installation for L36 ~ Roof

Keep the working area tidy


Working with proper manual lifting method
Wears appropriate PPE e.g. safety shoes
Supervision frequently
Ensure loading platforms are examined by
RPE
Ensure all LA & LG are examined by RPE
Inspection of the lifting chain and sling are
free of patent defect before commencing of
work
Assign qualified operator and banksman and
use walkie-talkie for communication.
Ensure the formwork platform is examined
by RPE
Wear safety harness and ensure safety belt to
be securely fixed to anchorage point
Ensure the monorail system and gondola are
examined by RPE
Regular inspection of gondola by competent
person with valid certificate
Only competent workers can be worked on
gondola
Wears appropriate PPE and ensure the fallarrest safety device to be properly used
Specific training, tool box talk
All handy tools to have safety loop and tied
to workers hand/firm support during
operation

Remark

Hazard Identification Sheet

Netfortune Engineering (FEA) Macau Limited


01

Review No.
Item

Job Task

To layout reference
lines and level datum for
setting out

Date
People Affected
Surveyor

31 Aug, 2006
Hazard

Cause of Hazard

Fall from height


while working near
floor edge

Working at height

Fall from height


while working on
gondola

Working at height

Worst Harm Due to


Hazard
Fatality

Existing Control Measures


-

Fatality

External works for


application of
waterproofing, external
flashing fixing, fire
insulation fixing, final
cleaning, water testing,
bracket & sub-frame
installation

Applicator,
Installer, Caulker

Falling objects from


gondola

Working at height

Fatality

Fall from height


while working on
gondola

Working at height

Fatality

Falling objects from


gondola

Ref. : VHCM/HI/RF 001

Activity : Curtain Wall, Aluminium Cladding And GRC


Cladding Installation for L36 ~ Roof

Working at height

Fatality

Provide proper platform with adequate guardrail


Wear safety harness and ensure safety belt to
be securely fixed to anchorage point
Ensure the monorail system and gondola are
examined by RPE
Regular inspection of gondola by competent
person with valid certificate
Only competent workers can be worked on
gondola
Wears appropriate PPE and ensure the fallarrest safety device to be properly used
Specific training, tool box talk
All handy tools to have safety loop and tied
to workers hand/firm support during
operation
Ensure the monorail system and gondola are
examined by RPE
Regular inspection of gondola by competent
person with valid certificate
Only competent workers can be worked on
gondola
Wears appropriate PPE and ensure the fallarrest safety device to be properly used
Specific training, tool box talk
All handy tools to have safety loop and tied
to workers hand/firm support during
operation

Page 2 of 4
Remark

Hazard Identification Sheet

Netfortune Engineering (FEA) Macau Limited


01

Review No.
Item

Job Task

Curtain wall installation

Date
People Affected
Installer. Rigger,
Labourer

31 Aug, 2006
Hazard
Falling objects due
to lifting failure

Cause of Hazard
Improper Lifting
method

Worst Harm Due to


Hazard
Fatality

Existing Control Measures


-

Internal works for


thermal and acoustic
insulation installation

Installer, Labourer

Fall from height


while working near
floor edge
Falling objects
while working near
floor edge
Fall from height
while working on
working platform

Ref. : VHCM/HI/RF 001

Activity : Curtain Wall, Aluminium Cladding And GRC


Cladding Installation for L36 ~ Roof

Working at height

Fatality

Working at height

Fatality

Working at height

Fatality

Ensure the loading platform, monorail system


and chain hoist are examined by RPE
Ensure all LA & LG are examined by RPE
Inspection of the lifting chain and sling are
free of patent defect before commencing of
work
Only trained workers can operate the chain
hoist
Specific training, tool box talk
Supervision frequently
Wear safety harness and ensure safety belt to
be securely fixed to anchorage point
All handy tools to have safety loop and tied
to workers hand/firm support during
operation
Ensure the working platform is erected by
competent worker and be inspected by
competent person with valid certificate
Regular inspection of working platform by
competent person
Wear safety harness and ensure safety belt to
be securely fixed to anchorage point

Page 3 of 4
Remark

Hazard Identification Sheet

Netfortune Engineering (FEA) Macau Limited


01

Review No.
Item
7

Job Task
Aluminium and GRC
Cladding Installation

Date
People Affected
Installer. Rigger,
Caulker, Labourer

31 Aug, 2006
Hazard
Falling objects due
to lifting failure

Cause of Hazard
Improper Lifting
method

Worst Harm Due to


Hazard
Fatality

Existing Control Measures


-

Fall from height


while working on
gondola

Working at height

Fatality

All works

All workers

Ref. : VHCM/HI/RF 001

Activity : Curtain Wall, Aluminium Cladding And GRC


Cladding Installation for L36 ~ Roof

Falling objects from


gondola

Working at height

Fatality

Heat stress
(Summer time)

Overheat of worker

Harmful to hearing

Ensure the loading platform, monorail system


and chain hoist are examined by RPE
Ensure all LA & LG are examined by RPE
Inspection of the lifting chain and sling are
free of patent defect before commencing of
work
Only trained workers can operate the chain
hoist
Specific training, tool box talk
Supervision frequently
Ensure the monorail system and gondola are
examined by RPE
Regular inspection of gondola by competent
person with valid certificate
Only competent workers can be worked on
gondola
Wears appropriate PPE and ensure the fallarrest safety device to be properly used
Specific training, tool box talk
All handy tools to have safety loop and tied
to workers hand/firm support during
operation
Considering worker's age and health
Drinking water provide

Page 4 of 4
Remark

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

8.

Page : 22 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

APPENDICES
8.2 Risk Assessment

Rev. 0

Risk Assessment Sheet

Netfortune Engineering (FEA) Macau Limited


Review No.

01

Work Package :

Risk
Injury caused by
manual handling

Falling objects due


to lifting failure

Fall from height


while working on
formwork platform
Fall from height
while working on
gondola

Falling objects from


platform/gondola

Note:

1.
2.
3.

Activity : Curtain Wall, Aluminium Cladding And GRC


Cladding Installation for L36 ~ Roof

Control Measures

31 Aug, 2006

J3039 Venetian Macau in Cotai, Macau


2120/3110 Hotel Curtain Wall/Glazing & Aluminium Cladding And GRC Cladding Installation

Project :

Item

Date

Keep the working area tidy


Working with proper manual lifting method
Wears appropriate PPE e.g. safety shoes
Supervision frequently
Ensure loading platforms are examined by RPE
Ensure all LA & LG are examined by RPE
Inspection of the lifting chain and sling are free of
patent defect before commencing of work
Assign qualified operator and banksman and use
walkie-talkie for communication.
Ensure the formwork platform is examined by RPE
Wear safety harness and ensure safety belt to be
securely fixed to anchorage point
Ensure the monorail system and gondola are
examined by RPE
Regular inspection of gondola by competent person
with valid certificate
Only competent workers can be worked on
gondola
Wears appropriate PPE and ensure the fall-arrest
safety device to be properly used
Specific training, tool box talk
All handy tools to have safety loop and tied to
workers hand/firm support during operation

Probability or Likelihood Rating:


Consequence Rating:
Risk Level:

Almost Certain (5)


Very High (5)
(RED)

Probable (4)
High (4)
(ORANGE)

Ref. : VHCM/RA/RF 001

Rating of Harm
Consequences2
Probability1
3
3

Risk Level3

Analysis by : Yeung Ka Wah / Ricky Ip

Recommended Action

9 (Yellow)

Regular inspection

9 (Yellow)

Provide specific training and close


supervision

6 (Yellow)

Provide tool box talk

6 (Yellow)

Provide specific training

6 (Yellow)

Provide specific training

Possible (3)
Medium (3)
(YELLOW)

Remote (2)
Low (2)
(GREEN)

Impossible (1)
Very Low (1)

Page 1 of 4

Remark

Risk Assessment Sheet

Netfortune Engineering (FEA) Macau Limited


Review No.

01

Date

Item

Risk

Fall from height


while working near
floor edge

Fall from height


while working on
gondola

Falling objects from


gondola
4

Fall from height


while working on
gondola

Falling objects from


gondola

Note:

1.
2.
3.

Provide proper platform with adequate


guard-rail
Wear safety harness and ensure safety
belt to be securely fixed to anchorage
point
Ensure the monorail system and gondola
are examined by RPE
Regular inspection of gondola by
competent person with valid certificate
Only competent workers can be worked
on gondola
Wears appropriate PPE and ensure the
fall-arrest safety device to be properly
used
Specific training, tool box talk
All handy tools to have safety loop and
tied to workers hand/firm support during
operation
Ensure the monorail system and gondola
are examined by RPE
Regular inspection of gondola by
competent person with valid certificate
Only competent workers can be worked
on gondola
Wears appropriate PPE and ensure the
fall-arrest safety device to be properly
used
Specific training, tool box talk
All handy tools to have safety loop and
tied to workers hand/firm support during
operation

Probability or Likelihood Rating:


Consequence Rating:
Risk Level:

Activity : Curtain Wall, Aluminium Cladding And GRC


Cladding Installation for L36 ~ Roof

31 Aug, 2006
Control Measures

Almost Certain (5)


Very High (5)
(RED)

Ref. : VHCM/RA/RF 001

Rating of Harm
Probability1
Consequences2
2
3

Probable (4)
High (4)
(ORANGE)

Risk Level3

Recommended Action

6 (Yellow)

Provide tool box talk

6 (Yellow)

Provide specific training

6 (Yellow)

Provide specific training

6 (Yellow)

Provide specific training

6 (Yellow)

Provide specific training

Possible (3)
Medium (3)
(YELLOW)

Remote (2)
Low (2)
(GREEN)

Impossible (1)
Very Low (1)

Page 2 of 4
Remark

Risk Assessment Sheet

Netfortune Engineering (FEA) Macau Limited


Review No.

01

Item

Risk

Falling objects due


to lifting failure

Date

Fall from height


while working near
floor edge
Falling objects
while working near
floor edge
Fall from height
while working on
working platform

Note:

1.
2.
3.

Ensure the loading platform, monorail


system and chain hoist are examined by
RPE
Ensure all LA & LG are examined by
RPE
Inspection of the lifting chain and sling
are free of patent defect before
commencing of work
Only trained workers can operate the
chain hoist
Specific training, tool box talk
Supervision frequently
Wear safety harness and ensure safety
belt to be securely fixed to anchorage
point
All handy tools to have safety loop and
tied to workers hand/firm support during
operation
Ensure the working platform is erected
by competent worker and be inspected by
competent person with valid certificate
Regular inspection of working platform
by competent person
Wear safety harness and ensure safety
belt to be securely fixed to anchorage
point

Probability or Likelihood Rating:


Consequence Rating:
Risk Level:

Activity : Curtain Wall, Aluminium Cladding And GRC


Cladding Installation for L36 ~ Roof

31 Aug, 2006
Control Measures

Almost Certain (5)


Very High (5)
(RED)

Ref. : VHCM/RA/RF 001

Rating of Harm
Probability1
Consequences2
2
3

Probable (4)
High (4)
(ORANGE)

Risk Level3

Recommended Action

6 (Yellow)

Provide training and close supervision

6 (Yellow)

Provide tool box talk

6 (Yellow)

Provide tool box talk

6 (Yellow)

Provide tool box talk

Possible (3)
Medium (3)
(YELLOW)

Remote (2)
Low (2)
(GREEN)

Impossible (1)
Very Low (1)

Page 3 of 4
Remark

Risk Assessment Sheet

Netfortune Engineering (FEA) Macau Limited


Review No.

01

Item

Risk

Falling objects due


to lifting failure

Date

Fall from height


while working on
gondola

Falling objects from


gondola
8

Note:

Heat stress
(Summer time)

1.
2.
3.

Ensure the loading platform, monorail


system and chain hoist are examined by
RPE
Ensure all LA & LG are examined by
RPE
Inspection of the lifting chain and sling
are free of patent defect before
commencing of work
Only trained workers can operate the
chain hoist
Specific training, tool box talk
Supervision frequently
Ensure the monorail system and gondola
are examined by RPE
Regular inspection of gondola by
competent person with valid certificate
Only competent workers can be worked
on gondola
Wears appropriate PPE and ensure the
fall-arrest safety device to be properly
used
Specific training, tool box talk
All handy tools to have safety loop and
tied to workers hand/firm support during
operation
Considering worker's age and health
Drinking water provide

Probability or Likelihood Rating:


Consequence Rating:
Risk Level:

Activity : Curtain Wall, Aluminium Cladding And GRC


Cladding Installation for L36 ~ Roof

31 Aug, 2006
Control Measures

Almost Certain (5)


Very High (5)
(RED)

Ref. : VHCM/RA/RF 001

Rating of Harm
Probability1
Consequences2
3
3

Probable (4)
High (4)
(ORANGE)

Risk Level3

Recommended Action

9 (Yellow)

Regular inspection

6 (Yellow)

Provide specific training

6 (Yellow)

Provide specific training

4 (Green)

Provide tool box talk

Possible (3)
Medium (3)
(YELLOW)

Remote (2)
Low (2)
(GREEN)

Impossible (1)
Very Low (1)

Page 4 of 4
Remark

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

8.

Page : 23 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

APPENDICES
8.3 Sketches
A.

Sketch No. 29 GRC Cladding Installation (Stage 1)

B.

Sketch No. 30 GRC Cladding Installation (Stage 2)

C.

Sketch No. 31 GRC Cladding Installation (Stage 2) Zig-zac Side Set Gondola

Rev. 0

Venetian Hotel in Cotai, Macau


SKETCH 29

Workage Package : 2120/3110 Curtain Wall,


Aluminium Cladding & GRC Cladding Installation

GRC Cladding Installation at L36 ~ R/F (Stage 1)


Track for Gondola

Track for Chain Hoist

Support Frame
(with Two Tracks)

Bearing Wall

Roof Parapet Wall


GRC Bracket Installation

Roof

Installed Curtain Wall

L39

L38

L37

L36

Venetian Hotel in Cotai, Macau


SKETCH 30

Workage Package : 2120/3110 Curtain Wall,


Aluminium Cladding & GRC Cladding Installation

GRC Cladding Installation at L36 ~ R/F (Stage 2)


GRC Panel to be Installed by Tower Crane

Support Frame
(Tracks Removed)

Bearing Wall

Gondola Wire
Roof Parapet Wall

Roof

Wire Sling connected to Tower Crane

Zig-zac Side Set Gondola

GRC Column

L39

L38

L37

L36

Venetian Hotel in Cotai, Macau


SKETCH 31

Workage Package : 2120/3110 Curtain Wall,


Aluminium Cladding & GRC Cladding Installation

GRC Cladding Installation at L36 ~ R/F (Stage 2)

Support Frame

Roof Parapet Wall

GRC Column under Installation

Temporary Gondola

Temporary Gondola

Zig-zac Side Set Gondola

Netfortune Engineering (FEA) Macau Limited


Method Statement for Hotel Curtain Wall/Glazing &
Aluminium Cladding And GRC Cladding
Installation for L36 ~ Roof

8.

Page : 24 of 24
Doc. No. : VHCM/MS/RF/001
Issue : 001
Date : 31-Aug-2006

APPENDICES
8.4 Evercrete Method Statement for Waterproofing
Application

Rev. 0

You might also like