001B Method Statement Form - Internal Glazing
001B Method Statement Form - Internal Glazing
REVISION NO: : 00
REVIEWED BY: :
APPROVED BY: :
Main Contractor: AL TAYER STOCKS LLC
Subcontractor: M/s DELTA METAL WORK L.L.C
TABLE OF CONTENTS
02 References 3
03 Responsibilities/ Supervision 3
06 Manpower Requirement 4
07 Material Requirement 4
08 Housekeeping 4
10 Training 5
11 Required PPE 5
12 Documentation 5
13 Distribution 5
QR.N-25B/R-00
Main Contractor: AL TAYER STOCKS LLC
Subcontractor: M/s DELTA METAL WORK L.L.C
2.0 REFERENCES
Approved Shop Drawing
ATS-AUH-MDCA-55130-200-FRE-004
ATS-AUH-MDCA-55130-200-FRE-001
ATS-AUH-MDCA-55130-200-FRE-002
ATS-AUH-MDCA-55130-200-FRE-003
b) Project/ Site Engineer (Esper Riad Al Shammas)shall be responsible for monitoring of the day-to-
day activities on site, for materials, drawings, testing & commissioning and allocation of resources to
work areas on site. They shall report to the Project Manager.
c) Supervisors/ Charge Hands (Ibnu Subair) shall be directly responsible for the day-to-day job at site,
for coordinating of work with skilled and unskilled labor or any other staff assigned in his area.
d) QA/QC Department will be overseeing the quality requirements and quality control measures for the
project in coordination with Project/Site Engineer(s).
e) Safety officer shall be responsible for the health & safety aspects on site as per the Main contractor
and safety Manual. Safety Inspector will be present at all times of job execution.
QR.N-25B/R-00
Main Contractor: AL TAYER STOCKS LLC
Subcontractor: M/s DELTA METAL WORK L.L.C
4.2 INSTALLATION
Ensure that all opening size as per approved shop drawing.
Setting out shall be complete as per approved shop drawing.
Check the alignment with adjacent work before proceeding the Installation Work
Fin Glass to be fixed with the Existing fin Glass connection from Concrete Ceiling using spider
accessories.
Spider Accessories for the Glass Panel to be connected to the Fin Glass Using SS bolts and
Nuts.
Chain Hoist (Certification provided) to be hanged on the steel scaffolding.
Special additional support to be provided to the scaffolding for the Lifting purpose.
Glass Catcher to be fixed to the Glass Panel then using the nylon belt glass catcher & Chain
Host will be connected.
Slowly pull the chain to lift the glass to the up stair.
Glass Panel to be fixed the spider system using SS nut bolts.
Silicone will be applied after fixing the bolts.
Marking & cutting the area in floor to fix the Dorma Floor Machine.
Floor machine to be fixed with screws and cement.
Door Patches to be fixed to Glass Panel & Glass doors.
Connect the Glass using door patches and Floor Machines.
8.0 HOUSEKEEPING
Housekeeping will be done on daily basis, and scrap other wastage of demolitions and others will be
collected in containers, and disposed.
QR.N-25B/R-00
Main Contractor: AL TAYER STOCKS LLC
Subcontractor: M/s DELTA METAL WORK L.L.C
14.0 ATTACHMENT
Risk Assessment
Inspection and Test Plan (ITP)
Checklist
QR.N-25B/R-00
Main Contractor: AL TAYER STOCKS LLC
Subcontractor: M/s DELTA METAL WORK L.L.C
QR.N-25B/R-00
Main Contractor: AL TAYER STOCKS LLC
Subcontractor: M/s DELTA METAL WORK L.L.C
QR.N-25B/R-00