Demountable Partition Installation - Method Statement
Demountable Partition Installation - Method Statement
Method Statement
Revision 01
12-Aug-2018
1|Page
TABLE OF CONTENTS
2|Page
3|Page
1.0 SCOPE OF WORK:
This Method Statement covers the process of Installation of SNAP Standard Partition Wall
System for Olympic Committee Apartments.
Work shall consider health and safety, and include working area preparation, precautionary
measures application, finishing, cleaning, and inspection & testing.
2.0 Purpose:
Purpose of this Method Statement is to describe and cover measures and ways of
Installation of SNAP Standard Partition Wall System
3.0 DEFINITION:
MS - Method Statement
ADPI - The Engineer/Consultant
BLUU – BLUU Qatar
ITP - Inspection and Test Plan
PPE - Personal Protective Equipment.
4.0 RESPONSIBLITIES:
4.1 Project Manager
Over all responsible for implementation of approved method statement, specifications,
drawings and other contract specified requirements
4|Page
4.5 Site Engineer
Responsible to carry out work as per approved method statement, specifications, drawings
and other contract specified requirements, with coordination with QA/QC Engineer,
Subcontractor and other operatives. In charge of site planning and preparation for specific
work.
4.6 Foreman
Distribute and supervise workforce for construction activities. And prepare all required
machines or tools for the site works.
5.0 RESOURCES:
4.1 Man Power
Project Manager
QA/QC Engineer
Site Engineer
Foreman
Skilled Installer
Labor
Manufacturer’s Representative (If any)
4.2 Equipment / Tools
a. Preparation and Cleaning Equipment / Tools
Ladder for installation (Fixed)
Cloth for installation.
Warning tape for protection
Fork Lift to download the material from trucks
5|Page
6.0 MATERIAL:
Profiles
Door Frame
Door Leaf
Door Accessories
Wooden Panels
Partition Accessories
6|Page
7.3 General Work Instructions
7.3.1 Starting instructions will be given by the supervisors at the start of each
activity to explain the methodology of works and to communicate safe
working procedures to the operatives. These talks are structured in a
way to highlight to major risks involved in the activity and the various
control measures required in order to minimize the risk.
7.4 Environmental Issues
7.4.1 An environmental aspect can be defined as an element of an
organizations activities, products and/or services that can interact with
the environmental
7.4.2 All chemical wastes shall be disposed as per MSDS and legal
requirement.
7|Page
8.3.9 Vertical side aluminum will be installed between the ceiling and the floor aluminum
(leaser machine will be used to make sure the vertical level is adjusted) by screw in the
existing walls.
8.3.10 Prepare the door frames and adjusted to be in right position by using Leaser level
machine then fix it to profiles.
8.4 Wooden Panels Installation
8.4.1 Arrange the wooden panels as per the approved modulation layouts for each wall.
8.4.2 Before Installing clips to wooden panels, check the arc accessory in vertical profiles
then install the clips according to them.
8.4.3 Fixed the first phase of wooden panels using rapper hammer, to attach the clips to arc
accessory.
8.4.4 Install rock wool as heat, and sound, isolation.
8.4.5 Fixed the second phase of wooden panels using rubber hammer, to attach the clips to
arc accessory.
8.4.6 Install the joint 6 mm thickness rubber between each two wooden panels.
9.0 APPENDICES:
9.1 HSE Risk Assessment
9.2 Prepare As Built Demountable Partition Shop Drawings.
8|Page