Reliability Analysis Applied On Centrifugal Pumps
Reliability Analysis Applied On Centrifugal Pumps
Reliability Analysis Applied On Centrifugal Pumps
t
t
Eq.1
e
t
t R
) (
Eq.2
Where:
R(t): Reliability value
(t): Failure rate
t: Mission time (hours)
: Shape parameter
: Scale parameter (hours)
Figure-3. Bath curve
For this particular analysis of mechanical seal failure, data from mechanical seal failure were collected from
CMMS system to determine the time to failure for every mechanical seal and then to be computed in a specific
software for Weibull Analysis (Reliasoft). Table 1 shows the result of Weibull analysis for mechanical seal of
NGL pumps.
Table-1. Weibull analysis results
Equipment BETA ETA(hours)
NGL Pump A 1,13 4866,5
NGL Pump B 0,84 6513
Graphing equations 1 and 2 with Weibull results for 17520 hours (see figure 4 and 5).
4
Figure-4. Mechanical seal Reliability curve at 17520 hours
Figure-5. Mechanical seal Failure rate curve at 17520 hours
From the Weibull analysis performed on mechanical seal, Pump A is failing in a random way (could be caused
due to the variation of process parameters) and Pump B is failing on infant mortality zone of the bath curve
(could be caused by a combination of variable process condition i.e. pressure and temperature, lack of
maintenance procedures and or a poor mechanical condition of shaft seal).
Making comparison between Weibull parameters from the mechanical seal of both pumps against a typical
mechanical seal in Oil&Gas industry, it is clear that the life of mechanical seal analyzed in this paper is
significantly lower than a typical mechanical seal (Beta=1,4 and Eta=25.000hours).
Calculating MTTF (Mean Time To Failure) for mechanical seals:
=
0
). ( dt t R MTTF
Eq.3
)
1
1 (
+ = MTTF Eq.4
Use Table-2 To evaluate Gamma function
5
Table-2.
Example for NGL Pump A
horas MTTF
Function tableGamma
MTTF
hours
MTTF
PumpA
PumpA
PumpA
4661 5 , 4866 * 9578 , 0
9578 , 0
5 , 4866
13 , 1
)
1
1 (
= =
=
=
=
+ =
Table-3. MTTF values for mechanical seals
Pump
MTTF/
MTTF(hours)
Pump A 0,9578 4661,134 4866,5 1,13
Pump B 1,1 7164,3 6513 0,84
Where:
(1+1/): Gamma Function
: Characteristic Life (hours)
: Weibull Shape parameter
MTTF: Mean Time To Failure (hours)
Reliability Analysis for the NGL pumps system
Because of the NGL recovery gas plant would not stop for the next two years it was necessary to get the
reliability parameters of the NGL centrifugal pumps system with the objective to know the risk of to continue
operating the pumps system in these conditions.
The NGL centrifugal pumps units are arranged in parallel mode, being part of a Standby system with passive
redundancy (one pump is operating and the other is waiting in stand-by mode for a failure of first pump).More
specifically, the system contains a total of k+1 units, and as soon as the operating unit fails, the operator
replace the failed unit with one of the standby unit. Figure 6 shows the block diagram of standby system.
6
Figura-6. Standby system diagram
For a system with two pumps with two different failure rates the equation to calculate the reliability value is
Eq.5:
( )
e e e
t t
sw
t
SB
R R
2 1 1
1 2
1
+ =
Eq.5
Where:
RSB: Reliability Standby system
RSW: Reliability of switch mechanism (100%)
1 = Global Failure rate operating unit 1
2 = Global Failure rate operating unit 2
t = Mission time (hours)
Most of the times some pieces of equipment failure rates are not available (because they never failed).
Because of this to establish the global failure rates the use of international standards database like API,
OREDA or others are required. The failure tree for the NGL centrifugal pump is shown in figure 7.
Figure 7. Failure Tree for NGL pump A
Considering to all failure modes are statistically independents and a failure of any component breakdown the
pump, the global failure rate is the sum of all independent failure rates. For Pump A and B is the same
Operating Pump A
Stand-by Unit Pump B
7
procedure, the great difference in the failure rate are the values for mechanical seal (calculated in Weibull
Analysis). In table 4 the failure rate for both pump are shown.
e e e
System
SB
R
e
Bt
e
At
A B
A
e
At
System
SB
R
Calculating MTTF using equation 3 and the Availability (A) of the Pump System:
MTTF MTTR
MTTF
A
dt e MTTF
dt t R MTTF
t
+
=
=
=
0
0
.
). (
Where:
A: Failure rate for Pump A
B: Failure rate for Pump B
MTTF: Mean Time To Failure (hours)
MTTR: Mean Time To Repair (hours)
A: Availability
In table-5 are summarized the reliability analysis for the NGL pump system
Parameter NGL Pumps System
R
(17520)
0,1220
Average failure rate 0,000120
Expected Failure in 2 years 2,1035
MTTF 8329,0194
MTTR 21,0349
A (availability) 0,9975
8
It is well appreciated that the reliability value for the system a 17520 hours is too low with high chances to
suffer a failure. However, availability value remain high (that is a typical figure in Oil&Gas industry due to the
high redundancy on equipments). The cost of unreliability is the main cause of goes down gross margin in
most industry, due to high frequency of failure, wasting time, labor hours and spending money in spare parts.
High availability provides the opportunity to make money because the plant is ready to respond. Low reliability
provides the opportunity to incur outages which cost money.
Cost Analysis
Cost analysis is the most important section of any reliability analysis. The main goal of this section is to turn
the reliability numbers into money, money that will be used by Plant Maintenance Manager to justify
improvements or to make right decision and avoid to loss the gross margin of the company. Clearly it is the
responsibility of engineering departments to define the equipment failure rates and the consequences of
engineering practices on the life equipment. Also it is the responsibility of engineers to convert the results of
equipment life and failures into a financial format for clearly communicating within the organization.
This NGL pumps system expect 2,1 failures for the next two years which causes a cost of unreliability (COU)
of USD 590.450. The cost of unreliability is divided in:
Cost of spare parts
Cost of labor hours per reparation
Cost of loss production
tion lossproduc labor Spareparts
Cost Cost Cost COU + + =
Cost of mechanical seal failures = 7.000 USD (per seal) x 8 (number of mechanical seal failures in
both pumps A and B)= USD56.000
Cost per mechanical seal reparation: MTTR= 10 hr * 2 technician * 21USD (cost of labor hour) *8
(number of mechanical seal failures)= 3.360USD
Cost of loss production = 2,1 (number of failures) * 90 NGL Tons/h * 281 US$/Ton * 21hours (10
hours * 2,1 failures)= 531.090 USD
450 . 590 $ 090 . 531 $ 360 . 3 $ 000 . 56 $ = + + = COU
The cost of unreliability is 590.450USD. The RCFA (The Root Cause Failure Analysis) and Weibull analysis
have demonstrated that the mechanical seal of the centrifugal pumps is the main reason of high value of
COU.
Technical Proposal
With financial figures, the technical proposal to make improvements in the NGL pumps system has been
made.
1. To purchase one new pump
2. Replace the less reliable pump (pump A) with new one and the send to factory to recover the
original shaft size
3. To Modify the currently API plan to become independent of process variables
9
In Table-6 it is summarized the total cost of technical proposal to improve reliability figures and reduce the
COU.
Table-6.Techincal proposal cost
Proposal Cost in USD
Purchase a new pump 220.000
Repair an old pump 15.000
API plan modification 82.000
Total Cost 317.000
The cost of unreliability for the NGL pumps system is $590.450, clearly an investment of $317.000 is well
justified for improve reliability figures increasing the gross margin of the company.
CONCLUSIONS
From the failure analysis of mechanical seal several factor are the cause of pumps breakdowns, one is the
process condition variable making to the seal face a dry run, other cause is the poor mechanical condition
(wear) on the pump shaft due to the bad condition of the start up of the plant (dust in pipes run). The Weibull
analysis has confirmed the early failures of the seal due to the causes mentioned before. An API plan
modification is required to isolate the seal face lubrication from the process condition and the shaft pump
restoration is required as well.
The reliability analysis shows that an improvement in the NGL centrifugal pumps system is required, if an
immediately action is not taken the gross margin is going down year by year. The cost analysis is indicating
that an investment in this system is well justified to improve the reliability figures.
Tracking the reliability values keeping the availability indicator in the monthly report is an action required to
implement as soon as possible. In Oil&Gas industry is very common to find high availability numbers but low
reliability figures, for this reason most companies could not advertise the loss money due to unreliability (high
frequency failures). The cost of unreliability index is a simple and practical reliability tool for converting failure
data into cost, helping to managers and the entire the organization to understand the problem within a piece of
paper.
This paper shows how important is the Reliability Engineering applied. Those companies that start to
implement this kind of tool in their sites will take several advantages against their competence.
BIBLIOGRAPHY
[1] Eugene A.Avallone, Marks Standard Handbook for Mechanical Engineers, 10
th
edn. Mc Graw-
Hill, New York, 1999, p.61.
[2] A.Birollini, Reliability Engineering-Theory and Practice, Washington, D.C, April 1999.
[3] Weibull Database-Barringer & Associates Inc
[4] Dr David J Smith, Reliability, Maintainability and Risk,7
th
edn. Elseiver Butterworth-Heinemann,
Oxford, 2005.