The document outlines the piping design philosophy for the expansion of the Vadinar Refinery. It describes the scope, responsibilities, applicable codes and standards, design package requirements, design conditions and limitations, material selection, piping layout requirements, pipe support design, and testing and inspection criteria.
The document outlines the piping design philosophy for the expansion of the Vadinar Refinery. It describes the scope, responsibilities, applicable codes and standards, design package requirements, design conditions and limitations, material selection, piping layout requirements, pipe support design, and testing and inspection criteria.
The document outlines the piping design philosophy for the expansion of the Vadinar Refinery. It describes the scope, responsibilities, applicable codes and standards, design package requirements, design conditions and limitations, material selection, piping layout requirements, pipe support design, and testing and inspection criteria.
The document outlines the piping design philosophy for the expansion of the Vadinar Refinery. It describes the scope, responsibilities, applicable codes and standards, design package requirements, design conditions and limitations, material selection, piping layout requirements, pipe support design, and testing and inspection criteria.
PIPING DESIGN PHILOSOPHY PROJECT DOCUMENT NO. u a C .- 0 s X a d a .- E u- 8 a u g e a a - 0 K - - '5 6 5 C - C a E e 0) rn U) U) 3 U) i 0 5 a 5 C 0 1 t 1 PIPING DESIGN PHILOSOPHY ESSAR ENGINEERING CENTRE, MUMBAI T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 2 of 20 G E N - 0 0 4 - R 1
pppppppyu
DETAILS OF REVISION REV NO 23/04/07 ISSUED FOR REVIEW 00 07/05/07 ISSUED FOR DESIGN 01 03/09/07 ISSUED IN REVISED FORMAT 02 11/10/07 CABLE ROUTING PHILOSOPHY IN PIPE RACK INCORPORATED 03
T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 3 of 20 G E N - 0 0 4 - R 1
pppppppyu Contents 1. Scope........................................................................................................4 2. Conflicts and Deviations .............................................................................................4 3. Reference Documents................................................................................................4 4. Responsibilities ......................................................................................................4 5. Applicable Codes and Standards ...............................................................................5 6. Design Package..........................................................................................................5 7. Design Condition and Limitations...............................................................................5 8. Material Selection for Piping Components .................................................................8 9. Limitations on Pipe Sizes and Thickness...................................................................9 10. Piping Layout............................................................................................................10 11. Lines Spacing Requirements....................................................................................12 12. Underground Piping..................................................................................................12 13. Pipe Supports Design...............................................................................................13 14. Anchors and Guides .................................................................................................15 15. Non-Pressured Welded Attachments .......................................................................15 16. Instrument Piping......................................................................................................16 17. Plant Utility Piping System........................................................................................16 18. Utility-Process Connections......................................................................................17 19. Chemical Cleaning Line Identification......................................................................19 20. Testing and Inspection..............................................................................................19
T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 4 of 20 G E N - 0 0 4 - R 1
pppppppyu 1. SCOPE
This specification supplements ASME B31 codes and defines additional minimum design requirements For pressure piping located within plant areas.
2. CONFLICTS AND DEVIATIONS 2.1 Any conflicts between this specification and other applicable Engineering Specifications, Standard Drawings, or industry standards, codes, and forms shall be resolved in writing with the Company. 2.2 Direct all requests to deviate from this Specification in writing to the Company.
3. REFERENCE DOCUMENTS The selection of material and equipment, and the design, construction, maintenance, and repair of equipment and facilities covered by this specification shall comply with the latest edition of the references listed below, unless otherwise noted. 3.1. INDUSTRY CODES AND STANDARDS American Society of Mechanical Engineers ASME B31.1 Power Piping ASME B31.3 Process Piping ASME B31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids ASME B31.8 Gas Transmission and Distribution Piping Systems 3.2. ENGINEERING SPECIFICATIONS EECS-20-102-001 Piping Material Specification EECS-20-102-003 Technical supply conditions for pipes & pipe fittings. EECS-20-100-002 Piping Fabrication EECS-20-100-003 Piping Erection and Pressure Testing. EECS-20-102-006 Piping Flexibility Analysis EECS-20-102-011 Codes & Standards for Pressure Piping.
4. RESPONSIBILITIES 4.1. It is the responsibility of the design consultants to design pressure piping systems that meets the requirements of the applicable Code and relevant Standards, Specifications and Procedures as a minimum. 4.2. Strict application of minimum standards does not prohibit nor alleviate the design agency from using good engineering practices and from producing innovative ideas. T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 5 of 20 G E N - 0 0 4 - R 1
pppppppyu
5. APPLICABLE CODES AND STANDARDS In addition to referenced Codes and Standards, the applicable Codes and Standards in accordance with EECS-20-102-011 shall apply.
6. DESIGN PACKAGE The design of pressure piping located inside plant areas shall include the preparation of the documents listed below. These documents shall be given drawing numbers and become permanent plant records: Process Flow Diagram (PFD) & Utility Flow Diagram (UFD) Piping and Instrument Diagrams (P&ID) Line Designation Table. Calculation sheets supporting major flow data and pressure drop data shown on the Piping Designation Table. Equipment Layouts General Arrangement Drawings (Piping) Piping Section Drawings and details. Piping Isometric Drawings. Material Take Offs. Piping flexibility calculations. Hydrostatic Test Diagram / Recorded data. Pipe support and foundation location drawing. Special Online Items. Material Requisions Datasheets for Piping Elements like Pipe, Flanges, Valves, Gaskets etc. Any other document if specifically required. Design Consultants shall submit all the above documents time to time for review/approval.
T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 6 of 20 G E N - 0 0 4 - R 1
pppppppyu 7. DESIGN CONDITION AND LIMITATIONS 7.1. Design consultants shall establish and/or verify that the design conditions are realistic and fulfil the targeted operational and design capacity. 7.2. The design Consultants may specify design conditions exceeding immediate design requirements if there are long term economical justifications for future capacity increase. 7.3. Design Factors & Allowable Stresses 7.3.1. Plant piping designed in accordance with ASME B31.1 or ASME B31.3 shall follow stress given in the codes. 7.3.2. Maximum Stresses The calculated maximum principal stress due to test conditions shall not exceed the allowable stresses given in the codes. 7.3.3. Unexpected Loads and Pressure Variation For design conditions which include unexpected loads such as wind, earthquake, or External hydrodynamic forces, or occasional short-term pressure variation above the normal maximum, the pressure rating of components and/or the allowable stress may be increased as permitted by the applicable. Codes for such conditions without additional restrictions. 7.4. DESIGN PRESSURE 7.4.1. Piping systems designed in accordance to ASME B31.1 or ASME B31.3 shall be designed to withstand the most severe combination of pressure and temperature. 7.4.2. The variation allowance by the Code in the internal pressure should be taken as an Advantage for a cost effective design. 7.5. DESIGN TEMPERATURE 7.5.1. The design consultants shall specify the design temperature that matches the actual process conditions. Specific temperature conditions are addressed below. 7.5.2. Pipe Temperature For the purpose to specify piping material, the metal temperature of the pipe and piping components shall be the same as the bulk temperature of the fluid transported by the piping system No credit should be given for ambient heat losses unless such losses can be demonstrated to have significant cost advantage. 7.5.3. Ambient Range For fluid temperatures at or above ambient, the design temperature shall not be less than the maximum expected actual fluid temperature at design flow rate and design pressure. 7.5.4. Refrigerated Services T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 7 of 20 G E N - 0 0 4 - R 1
pppppppyu For the purpose of determining impact testing requirements, the design minimum temperature shall be established for piping carrying fluids which have been refrigerated below ambient temperature, based on process design conditions. 7.5.5. Auto-refrigeration For systems normally at or above ambient temperature which can occasionally be exposed to lower temperatures due to a sudden reduction in pressure (including causes such as leaks or ruptures) or due to blow down of equipment, the design minimum temperature shall be the coincidental temperature as may be encountered actually subjected to minimum when the pressure of 25% of the design pressure. 7.5.6. Thermal Radiation Effects All above ground piping systems shall be evaluated for pressure build up due to the effects of solar radiation, ambient temperature, and other heat sources such as a flare, heaters, blowers or combination of these effects. 7.6. DYNAMIC EFFECT The effects of dynamic forces external and internal dynamic forces shall be analyzed and the final design shall be suitable to accommodate such forces. Examples of such forces are earthquake, slug forces, pressure surge forces, steam & water hammer, Safety valve thrust force, etc. T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 8 of 20 G E N - 0 0 4 - R 1
pppppppyu 7.7. SUSTAINED LOADS 7.7.1. Sustained load shall include effects of internal design pressure, weight effects of pipe, components, contents, and any external weights like insulation. 7.7.2. Traffic loads on buried piping shall be considered. 7.8. MECHANICAL LOADINGS: 7.8.1. Wind and earthquake loads shall be determined in accordance with the governing Code(s), standard(s) and the data specified in the UOP Project Specifications. 7.8.2. Pipe supports shall be capable of supporting pipe full of water at ambient temperature. 7.8.3. Where free draining requirements are specified they shall be met under all conditions, taking into account piping deflections. 7.8.4. Stress, deflection, and fatigue shall be evaluated for the applicable loading conditions. 7.8.5. The piping system evaluation shall include operating, start-up, shutdown, and steam out conditions. 7.8.6. The piping system shall be properly designed to avoid severe cyclic conditions. 7.8.7. Piping associated with compressors requires that the amplitude and the spectral frequency distribution of pulsation be accommodated. 7.8.8. Pipe supports shall be designed to withstand all loading combinations including any factional forces due to the sliding of supports. 7.9. ROAD CROSSINGS 7.9.1. Where ever road crossings are encouraged either pipe rack above the roads or culverts.
7.10. DESIGN FLOW VELOCITY 7.10.1. Limitation on flow velocities inside piping systems shall apply. 7.10.2. Higher velocities may be permitted if there are technical and economical justifications. 7.10.3. Piping systems shall be designed with considerations to avoid and/or minimize the potentials of noise and piping vibration due to high velocities, slug flow, two-phase flow, acoustic fatigue, etc. 7.10.4. Piping systems in gas service operating intermittently with high velocities shall be designed with following considerations: Excessive noise and severe vibration shall be avoided. Pipe intersections should be at 45 degree inclination rather than 90 degrees. Pipe bends shall be of the long radius type with minimum 3 diameters. T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 9 of 20 G E N - 0 0 4 - R 1
pppppppyu Lead-lines upstream of & flow element shall have sufficient length to allow for flow development. A minimum length of 15 times diameter upstream and 5 times diameter downstream is recommended.
8. MATERIAL SELECTION FOR PIPING COMPONENTS 8.1.All pressure piping components shall comply with Standards specified in the paragraphs listed below. However, it is the design consultants responsibility to ensure selected material is adequate to the intended service. 8.1.1. The selection of material in general shall be as given below- a) Carbon Steel, for temperature less than or equal to 425 0 C. b) Low temperature Carbon Steel, for temperature less than -29 0 C to -45 0 C. c) Stainless Steel, for temperature below -45 0 C. d) Alloy steel, for temperature greater than 425 0 C. e) For corrosive fluids, process licensor recommendations should be followed. f) Material procurement of pipes, fittings, valves and gaskets shall be in compliance with approved vendor list. 8.1.2. Material specification & line classes shall be in accordance with EECS-20-102-001 8.1.3. Valves selection for piping systems shall be in accordance with EECS-20-102-017 8.1.4. Flanges, bolts and gasket shall be in compliance with EECS-20-102-018 8.2.All non-metallic piping system shall be designed and constructed in accordance with the applicable ASME B31 Code. 8.3.Items specified by brand names or proprietary names are not intended to exclude equivalent items offered by other manufacturers.
9. LIMITATIONS ON PIPE SIZES AND THICKNESS 9.1.SIZES OF PIPES AND FITTINGS 9.2.The outside diameter of steel pipe shall be in accordance with applicable standards. Intermediate sizes and the sizes: 8 1 , , 8 3 , 1, 2, 3, and 5 inches shall not be used except when necessary to match equipment connections. In this case a suitable transition shall be made as close as practical to the equipment. Mating flanges can be treated as special items. 9.3.Pipe (excluding stainless steel tubing) smaller than -inch nominal size shall not be used for hazardous services (including vents and drains) except for instrument connections and on Vendor- T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 10 of 20 G E N - 0 0 4 - R 1
pppppppyu supplied skid-mounted equipment or other applications where the pipe is adequately protected against mechanical damage. 9.4.The wall thickness of the pipe and piping components shall meet the requirements of the applicable Code as a minimum. 9.5.Piping wall thickness selection shall be governed by greater of minimum calculated code thickness including corrosion allowance or the minimum structural thickness provided in Table 1. Table 1 Minimum Structural Pipe Wall Thickness (T s ) Nominal Pipe Size (Inch) Wall Thickness (Inches) (mm) Thru 1 0.09 2.25 2 Thru 3 0.09 2.25 4 Thru 12 0.10 2.54 13 Thru 18 0.12 3.0 18 Thru 30 0.15 3.8 32 Thru 48 0.180 5.08 50 and up 0.250 6.35
9.6.For carbon steel piping, the minimum nominal wall thickness shall not be less than the values listed in Table 2.
Table 2 Minimum Pipe Wall Thickness for Carbon Steel Pipes Nominal Size (Inches) Hydrocarbon Service Low Pressure Utility Service
1 1/2 and smaller SCH 80 SCH 40 2 through 10 SCH 40 SCH 40 12 through 32 6.3 mm 6.3 mm 34 and larger D/135 D/135 Notes: T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 11 of 20 G E N - 0 0 4 - R 1
pppppppyu "D" is the pipe outside diameter. A stress analysis is required to confirm that the combined longitudinal stress and bending stress does not exceed the code allowable limit based on factors such as pipe support spacing, allowable stress, design pressure, etc. This note applies to the both Table 1 & 2.
10. PIPING LAYOUT 10.1. GENERAL The design consultant is responsible to provide piping layout that is economic and follows sound engineering practices. The piping layout shall assure safe operation, ease of construction, provide adequate access for maintenance activities, minimize consequence due to fire, and avoid congestion. 10.2. Hydraulic considerations 10.2.1. The pipe size, layout and supports shall be designed such that all hydraulic requirements are met in terms of pressure drop and required through analysis. 10.2.2. Piping systems shall be designed with considerations to avoid and/or minimize the potentials of noise and piping vibration due to high velocities, slug flow, two- phase flow, acoustic fatigue, etc. 10.2.3. Piping systems in high gas velocities operating intermittently shall be designed with following considerations: Excessive noise and vibration are avoided due to high gas velocities and pressure drop. Smooth transitions at flow intersections by means of laterals and long radius bends. Pressure drop at intersections. Lead-lines upstream & flow element shall have sufficient length to allow for flow development. A minimum length of 15 times diameter upstream and 5 times diameter downstream is recommended.
10.3. CORROSION CONSIDERATIONS The piping layout shall be designed in a way to minimize corrosion in the piping systems due to presence of water pockets, dead legs, and any other situation leading to internal or external corrosion. In general minimum corrosion allowance of 1mm is considered for carbon steel piping & 0mm of stainless steel piping. 10.4. DEAD LEGS Dead legs leading to internal corrosion shall be avoided at the design stage. A dead leg is created mainly by flow stagnation. T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 12 of 20 G E N - 0 0 4 - R 1
pppppppyu A section of a piping system meeting the following criteria is considered a dead leg: When a pipe section is connected to a flowing stream where it is not self draining and is not normally flowing. The piping material has the potential for corrosion in service. 10.5. PIPING FLEXIBILITY 10.5.1. The piping configuration shall be analyzed for adequate flexibility. 10.5.2. The piping system shall not be too flexible to the point that it becomes subject to piping Expansion J oints 10.5.2.1. Swivel joints, expansion joints, flexible pipe (metallic or non-metallic), hoses or similar devices shall not be used to reduce the stiffness of the piping system or to reduce load on equipment nozzles in flammable, toxic and hazardous services. 10.5.2.2. They may be used for category D fluid service as defined in ASME B31.3. 10.6. PIPE RACKS 10.6.1. Above grade plant piping between plant equipments or between separate units within a plant area shall be designed and installed within pipe rack boundaries as indicated on Plot Plans and Piping Plans. 10.6.2. The Plot Plans and Piping Plans shall be laid out such that they shall provide the necessary access to all areas for operations and maintenance .The elevations of intersecting pipe racks shall normally be at different levels to allow for future piping. 10.6.3. When designing off-plot pipe racks for process plants, consideration shall be given to providing extra rack space for future expansion. 10.6.4 Electrical and Instrumentation cables : Following concepts shall be adopted for routing of electrical and instrumentation cables throughout the refinery complex. i) Electrical HT cables shall be laid underground in trench with slab cover in ISBL and OSBL including tankage area. ii) Electrical LT cables shall be laid above ground on top tier of pipe rack in ISBL and OSBL area. iii) Instrument cables shall be taken above ground on top tier of pipe rack in ISBL and OSBL area. iv) Instrument fiber optic cables shall be taken under ground through conduit in ISBL and OSBL area. v) Flange guards shall be used for hydrocarbon lines located near the cable trays in pipe Rack.
03 T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 13 of 20 G E N - 0 0 4 - R 1
pppppppyu
10.7. CLEARANCES AND ACCESSIBILITY 10.7.1. The minimum clearance required over roads, walkways, platforms, etc. shall be as follows: Railroads/railways: 7.0 meter Access roads, main roads, crane access: 7.0 meter Fire fighting equipment: As required by local authorities Plant roads within the unit: 4.5 meter Overhead within the unit area: 2.8 meter Fork lift truck access : 2.8 meter Above walkways and platforms: 2.1 meter 10.7.2. Valves 4 and above shall be installed with the operating device not higher than 1.5 meter above the operating level. Valves 3 and smaller, temperature indicators, level instruments, pressure indicators may be accessible from ladders. All battery limit valves shall be accessible fro grade or platform. 10.7.3. The minimum clearance over the actuator of a control valve shall be 180 mm and under the bottom of the valve clearance shall be minimum 300mm.
11. LINES SPACING REQUIREMENTS 11.1. The minimum spacing between lines supported on sleepers or pipe racks shall be as shown on standard drawing. In general minimum spacing shall be- a) 50mm pipe to pipe, pipe to insulation and insulation to insulation. b) 25 mm flange to pipe and flange to insulation.
11.2. Above-grade piping shall be supported to provide a minimum of 300 mm clearance between bottom of the pipe and the finished grade. 11.3. A minimum clearance of 50 mm shall be provided for inspection and freedom of pipe movement between above ground piping crossing with any structure (including pipe support structure). This clearance is also required for above ground piping crossing with another pipe. 11.4. Branch connections, 4 inch and smaller, including drain and vent valves and drip legs of all sizes, shall be located at a minimum horizontal distance of 610 mm (24 inches) from any fixed obstruction. This requirement does not apply to that part of the support which is attached directly to the piping, such as horizontal and vertical dummy extensions. T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 14 of 20 G E N - 0 0 4 - R 1
pppppppyu
12. UNDERGROUND PIPING 12.1. Underground pressure piping where permitted shall be subject to the following additional requirements:
12.2. No buried dead legs shall be allowed, including "effective" dead legs resulting from the buried portion of the line being frequently or normally valved off unless the line is designed to be self- draining and/or is internally coated. 12.3. The buried piping (including appurtenances) shall be cathodically protected with impressed-current or galvanic anodes system for soil resistivity less than 5000 Ohm-cm 12.4. The minimum cover over underground pressure piping shall be 450 mm in unpaved or paved areas and 1000 mm under paved roads, except under reinforced concrete slab or other protection. 12.5. Sleeves of suitable strength shall be provided at road crossing/ culverts. 12.6. The buried piping (including appurtenances) shall be externally coated with an approved coating.
13. PIPE SUPPORTS DESIGN 13.1. RESPONSIBILITIES It is the Design consultants responsibility to design the pipe supports to meet hydro testing, operational and emptying conditions requirements. 13.2. RIGID PIPE SUPPORTS 13.2.1. The rigid pipe supports should be utilized to maximum extent thus avoiding the use of spring supports and rod hangers wherever design permits. 13.2.2. The designer shall ensure that all pipe supports will be active during operation of the lines, i.e., the pipe will be in full contact with the support and carries the load. 13.3. HANGER RODS 13.3.1. Rod hangers shall not be used for lines 12" NPS and larger in liquid service or multi phase flow. 13.3.2. Rod hangers shall be subjected to tensile loading only. 13.3.3. Rod hanger assemblies shall be designed to allow for anticipated thermal movement. 13.3.4. The maximum swing angle due to horizontal pipe movement shall be four (4) degrees. 13.3.5. All hangers shall be provided with means for vertical adjustment. 13.3.6. Suitable locking devices shall be used at all threaded connections of the hanger assembly (double nuts). 13.3.7. Where atmospheric corrosion is a concern hanger rods shall be protected against external corrosion. T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 15 of 20 G E N - 0 0 4 - R 1
pppppppyu 13.4. SPRING SUPPORTS 13.4.1. Spring supports immediately downstream of rotating equipment shall be limited to 10-15% load variation. 13.4.2. Supports shall be designed such a way that they cannot be disengaged by movements of the supported Pipe. 13.4.3. All springs shall be in compression, so that failure will not result in the complete release of load. 13.4.4. Springs shall be factory set to the calculated cold settings by means of travel stops. Upper stops for load preset and lower stops for hydro-test shall be provided. These stops shall be banded or locked in place so they cannot be easily dislodged during erection or hydro-test. The travel stops shall be painted red and shall have a bright colour tag indicating "Remove after Hydro-test." 13.4.5. Each spring hanger assembly must be capable of sustaining the hydro test load. 13.4.6. Where atmospheric corrosion is a concern spring supports shall be protected against external corrosion. 13.5. RING GIRDERS 13.5.1. Above ground fully restrained piping shall be supported on ring girders, or 180-degree saddles with top strap, designed to prevent lateral buckling of the pipeline. 13.5.2. Suitable electrical insulation strips shall be provided between the pipe and the support if required to prevent dissipation of cathodic protection current. 13.5.3. The pipe surface covered by the ring girder or saddle and top strap shall be coated with approved epoxy coating to prevent corrosion of the pipe. Coating is not required if a fiberglass insulating spacer is epoxy bonded to the pipe after abrasive blasting the pipe surface. 13.6. LOW FRICTION SUPPORTS 13.6.1. If Teflon sheets or similar low friction materials are used to reduce the design loads on piping and/or the supporting structure, provision shall be made to allow angular adjustment of the bearing surface during installation, so that an even distribution of the load can be assured. 13.6.2. Low friction supports shall be designed such that sand or other debris cannot accumulate on sliding surfaces (by making the top surface larger than the bottom surface). 13.7. DUMMY SUPPORTS T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 16 of 20 G E N - 0 0 4 - R 1
pppppppyu 13.7.1. The dummy supports shall not create excessive stresses at the attachment welds to the run pipe. This can be accomplished by minimizing the length of the supports and/or increasing the size of the supports. 13.7.2. A 6 mm deep hole shall be drilled for all dummy supports. The weep hole shall be located near the base plate for all vertical dummy supports, and near the run pipe at 6 o'clock position for all horizontal dummy supports.
14. ANCHORS AND GUIDES 14.1. END ANCHORS The Design Agency shall ensure that above-ground restrained and buried pipelines terminating at the plant facilities be provided with end anchors. 14.2. INTERMEDIATE ANCHORS, GUIDES, AND LINE STOPS 14.2.1. The free movement of unrestrained piping, both in axial and lateral directions, shall be controlled and limited by properly located guides and anchoring points to within acceptable bounds. 14.2.2. Intermediate anchors or axial line stops shall be provided for above-ground unrestrained piping between and/or at the centre of expansion loops or offsets. The design load for such intermediate anchors shall include the effect of friction forces. 14.2.3. Axial line stops and guides shall be provided for above ground unrestrained lines subject to slug forces in services listed below. Slug forces shall be estimated based on the worst case assumed velocity and average density of the liquid/vapor slug expected to occur. 14.2.4. The supporting structures shall be designed to withstand slug forces acting at changes in direction. However the pipe guides and stops shall yield prior to the pipe. The following are examples of services with potential slug flow; however this doesn't remove responsibility of the Deign Consultant to identify others. Two-phase flow lines Liquid intermittent lines, such those used to control liquid level in the drums Pressurized drain lines Relief and blow-down lines Flare lines High-pressure gas lines 14.3. DAMPENING ANCHORS Suitable dampening anchors shall be provided to hold down the piping and mitigate vibration as required at control valve stations, (surge) relief valves, and where flow surges can occur. T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 17 of 20 G E N - 0 0 4 - R 1
pppppppyu
15. NON-PRESSURED WELDED ATTACHMENTS 15.1. During the design stage the following requirements shall be adhered to: 15.1.1. Welded attachment to the piping systems shall be minimized. Design should avoid the use of bimetallic welds. 15.1.2. The pipe shall not be used to support other pipes and structures without an appropriate analysis. 15.1.3. All structural attachments, which transfer loads to the pipe through welds, shall be welded to full encirclement sleeves or saddle pads if the piping is designed to operate at a hoop stress in excess of 50% of the allowable stress. The corners of the pad shall be rounded corners. ASME B31.4 paragraph 419.1(d) and ASME B31.8 paragraph 834.5(b), if applicable, shall not be waived. 15.1.4. On the construction drawings, all welds to the pipe shall be shown as continuous with smooth finish. 15.2. Wear Pads and Saddles 15.2.1. Piping in hazardous services where condensation can form on the pipe, or operating within 30 m of the sea shall have wear pads or corrosion bars welded to the pipe at each support. 15.2.2. Excluded from this requirement are low pressure systems with hoop stress at design pressure below 18% of Specified Minimum Yield Strength (SMYS) of the pipe. 15.2.3. Wear pads shall be fully welded to avoid ingress of moisture. 15.2.4. Saddle-type supports: Saddle-type supports with pads shall be provided for piping 30-inch NPS and larger. In case saddle pipe support cannot be installed, the line shall be analyzed for localized stresses.
16. INSTRUMENT PIPING Instrument piping within the scope of the Code shall meet all the applicable requirements of the Code.
T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 18 of 20 G E N - 0 0 4 - R 1
pppppppyu 17. PLANT UTILITY PIPING SYSTEM 17.1. This section of the standard defines additional limitations on piping used for connecting a supply of steam, water, air, nitrogen or other inert gas to process equipment in hazardous services except as stated below. It also includes connections for the purpose of purging or cleaning when the process equipment is not in operation. 17.2. This section does not apply to purge connections to open furnaces or fire boxes. It also does not cover connections to process equipment where the process flow and utility flow remain physically separated such as in cooling water or instrument air.
17.3. The design of utility Stations located in various locations within one plant area shall be uniform and shall be such that the risk of accidental connection to the wrong utility is eliminated. 17.4. The connectors and colour coding for utility piping shall be specification EECS-20-102-015. 17.5. Hose connections, where applicable, shall be positioned at elevation not higher than 1200 mm above finished plant grade or above platform of multilevel equipment but not lower than 600 mm. They shall be pointing 45 degrees downward. The piping shall be securely bolted to a supporting structure and have adequate access. Utility connections shall be installed with minimum 140 mm clearance between each other. 17.6. Each utility take-off connection shall be located at the top of the horizontal main header or auxiliary header. Root valves shall be provided for each utility take-off connection from a main header or auxiliary header which can not be taken out of service without shutting down a complete processing unit or operating facility. 17.7. Instrument air take-off connections to the plant utility station shall always be provided with root valves. 17.8. Each utility line shall be provided with an isolation valve just upstream of the specified hose connector at the termination. Ball or globe valves shall be used for air, water, and nitrogen services; globe or angle valves shall be used for steam service. Each line shall have a service name plate in Hindi and English indicating the service. The utility pipe and the ends of hoses provided with the station shall be color coded. 17.9. The steam line shall have steam trap and shall be insulated for personnel protection except for utility steam take-off lines. Utility steam take-off lines shall be insulated but shall not be provided with steam traps. Utility steam stations located above the utility steam header shall be self-draining towards the utility steam header. Utility steam lines to utility stations below the utility steam header shall be allowed to gather steam condensate, which is removed before applying the utility steam. 17.10. Water supply systems which deliver drinking water shall not be connected to process equipment as utility water source, except via a break tank designed to prevent backflow. T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 19 of 20 G E N - 0 0 4 - R 1
pppppppyu 17.11. Firewater systems shall not be connected to process equipment.
18. UTILITY-PROCESS CONNECTIONS Requirements of this section are specific to the Utility-Process Connections, in addition to the requirements of this standard. 18.1. Temporary Utility-Process connections with components listed in the direction of the utility flow shall be as follows:
18.1.1. The utility side shall have a block (root) valve, pressure gauge, check valve and a drain valve to depressurize the hose or the break-away spool. The process side shall also have a check valve; block valve, and pressure gauge near the hose connection. 18.2. No permanent connections other than air or steam shall be made to process equipment operating above 100C nor shall water or steam be permanently connected to equipment that operate below 0C. 18.3. Permanent connections without a break tank shall not be made except when the required service is continuous or frequent (at least twice per week) or needed for emergencies. Permanent connections without a break tank shall consist of the following (in the direction of the utility flow): 18.4. The utility flow shall have instrumentation for automatic shut-off on low flow or low pressure (in addition to a check valve) in all cases where redundant protection against back flow is required. 18.4.1. The utility side shall have a pressure gauge, block valve, bleed valve and spectacle blind or quick change blind (normally open). 18.4.2. The process side shall have a check valve, bleed valve or drain, block valve and pressure gauge. 18.4.3. The block valves of the connection shall be within sight of each other and shall be as close as practical to the process equipment. The pressure gauges and the position of the blind shall be clearly visible from a single point. 18.5. Air connections to asphalt or hot oil piping through which air is supplied to blow the product to tankage, shall be provided with a water knock-out (KO) drum with drainage facilities. The line downstream of the KO drum shall not contain low points and shall have an additional drain valve immediately upstream of the process connection. 18.6. When air is injected as a reaction agent, such as in Merox and air sweetening units, the control shall be such that the hydrocarbon/air mixtures will not enter the flammable range unless required by the process. Instrumentation shall be provided to shut off the air flow if the process flow fails. In addition, a restriction orifice shall be provided. T h e
d r a w i n g ,
d e s i g n
a n d
d e t a i l s
g i v e n
o n
t h i s
f o r m a t
a r e
t h e
p r o p e r t y
o f
E S S A R
E N G I N E E R I N G
C E N T R E .
T h e y
a r e
m e r e l y
l o a n e d
o n
t h e
b o r r o w e r ' s
e x p r e s s
a g r e e m e n t
t h a t
t h e y
w i l l
n o t
b e
r e p r o d u c e d ,
c o p i e d ,
e x h i b i t e d
o r
u s e d ,
e x c e p t
i n
t h e
l i m i t e d
w a y
p e r m i t t e d
b y
a
w r i t t e n
c o n s e n t
g i v e n
b y
t h e
l e n d e r
t o
t h e
b o r r o w e r
f o r
t h e
i n t e n d e d
u s e .
DOCUMENT NO REV PIPING DESIGN PHILOSOPHY EECS-20-102-002-03 03
ESSAR ENGI NEERI NG CENTRE , MUMBAI Page 20 of 20 G E N - 0 0 4 - R 1
pppppppyu 18.7. The rating of all Components of a permanent connection shall be suitable for the more severe of pressure/temperature of the process or the utility service. 18.8. For temporary connections the pressure/temperature rating of the process side shall extend to the hose or break-away spool. 18.9. If the process fluid requires internal lining or material other than used in the utility system, the lining or the material shall extend from and include the check valve on the process side. Valves with bodies of gray cast iron, ductile iron, or low melting point alloys (such as brass or bronze) shall not be used in a permanent connection including the utility side. Valve bodies and trim in a permanent connection shall be suitable for both the process and the utility fluid with regard to corrosion and pressure rating.
19. CHEMICAL CLEANING LINE IDENTIFICATION 19.1. Lines that require chemical cleaning during construction shall be identified and marked up on the appropriate P&ID's and Line Index Tables. The systems to be cleaned shall have high and low point vents and drains installed.
20. TESTING AND INSPECTION 20.1. The design of the piping systems shall facilitate effective pressures testing. 20.2. Test procedures that may require special attention may be prepared during the design stage.