Process Control Lab
Process Control Lab
EXPERIMENT NO:-1
Experiment:
Apparatus used:
• Patch cords
Theory:
The basic of this experiment is to control the temperature of the process with the use of
heat exchanger. This process contains temperature process rig. The temperature rig has
two isolated water circuits. The primary circuit which is used normally as heat source
comprises:
• A heater
• A circular pump
• A servo valve for flow control
• A pulse flow meter
• A header tank
• A heat exchanger
The secondary circuit contains a heat exchanger and a cooler.
The primary circuit is self contained and has to be filled before the system is
used. The secondary circuit is normally supplied via flexible hoses, from the Basic
Control Rig which is set up to provide a controlled flow. An alternative arrangement is to
use a Temperature Auxiliary Control Pack 38-480 to provide a control flow from a mains
water tap. Alternatively if we have a 38-610 forced Air Cooling Unit, the water from the
Temperature Rig can be cooled and re-circulated.
Role of Thermistor:
2
There are five such devices included with the Temperature Process Rig.
They are positioned to measure the temperature at five points around the secondary
and primary flows.
• In the primary flow they are positioned before (T1) and after (T2) the heat
exchanger. This is obviously crucial in observing the cooling effect of the heat
transfer.
• In the secondary flow they are also positioned before (T3) and after (T4) the heat
exchanger. The fifth device is placed at the output (T5) of the radiator in order to
show the temperature of the flow before and after cooling has taken place.
Heat Exchanger:
A major element in the topic of process control is the heat exchanger. These devices
can be found in so many configurations that a person who has been simply introduced to
the science of heat exchangers can be quite perplexed in trying to determine which of the
almost limitless types available, many apparently satisfying the required heat transfer
duty, should be used. For example, designs which incorporate tubes are only a subset of
the many heat exchangers available. However, often the most critical step in the analysis
of a heat exchanger is the determination of the overall heat transfer coefficient, U. This,
in turn, involves the application of convection and (or) phase change correlation's to find
the surface coefficients, h and uses these with the areas, A1 and A2 and wall resistance R ,
w
in a number of ways through pumps and joints. This air can find itself trapped in
the upper part of the cooling radiator, where it will remain until bleeding can be
carried out.
• Bleeding involves the removal of air from a fluid system by whatever method.
The type of domestic system mentioned earlier is usually bled from a small 'tap'
on the offending radiator.
• Air is pushed out under the system pressure until water begins to be expelled. The
tap is closed and the radiator is free of air.
• The main reason for the cooler on the Temperature Process Rig (TPR) is to drop
the temperature of the heated return fluid (secondary flow).
• The overall effect of this process is to prevent the secondary flow circuit (water in
the tank of the BPR) from heating up too quickly.
• This is achieved using a cooler, which consists of a radiator and a fan unit,
commonly known as an Air blow Water Cooler. The radiator itself comprises an
aluminum structure of heat dissipating fins, whereby the fluid to be cooled passes
behind.
• In order to increase the cooling efficiency, a fan is attached to the rear of the
radiator to draw air through the radiator dissipating the heat from the fins.
• It must be noted that coolers of this type can only reduce the temperature to a
minimum degree equal to the ambient air temperature. However with respect to
the TPR due to the size of the cooler this would actually take a considerable
amount of time depending upon the temperature of the BPR fluid.
• It is therefore shown that the cooler is only intended to provide a degree of
cooling to the BPR (if connected).
• However in industrial applications, a cooler may be the primary source (only
source) for cooling a process, in which case its specification would be critical to
the dissipation required. Coolers of this type tend to be relatively large with
respect to their function.
• In this particular case the cooler is switched on to demonstrate its efficiency in
cooling the secondary flow before returning to the sump tank of the BPR.
In the overall controlling of the process, the roles of the controllers are very important.
The functions of the controllers and their role in the process are described briefly
described here.
Proportional Control:
In ON/OFF control, small deviations from the desired value cause just as much
movement of the correcting element as large deviations. However, it is frequently
convenient to arrange that the position of the correcting element is directly related to the
deviation. This is known as proportional control. The following diagram shows that,
5
within the proportional band, there is a unique correcting element position for every value
of the controlled condition. Suppose water passing through the secondary circuit of a heat
exchanger is being heated by the hot water primary circuit. If the temperature of the
secondary circuit is being controlled by regulating the primary flow circuit, via a
proportional controller, the primary circuit valve would be half open when the
temperature is correct and the flow of water through the secondary was normal. This is
point A on the following diagram.
Should the temperature rise or fall, then the primary valve will open or close, in an
attempt to restore the temperature to the desired value. If, however, the flow of water in
the secondary be suddenly increased, then the primary flow must also be increased to
maintain the temperature desired value. The primary valve will open but, as the
temperature begins to rise towards the desired value, the valve will gradually close.
PI Control of Temperature:
2. For negative deviation, integral action shifts the whole proportional band
above the desired value until the controller condition reaches it. This means that the
correcting element does not start to close until it is too late to prevent overshoot.
The following diagram shows the output from a controller set to PI following a sudden
deviation.
Practical Procedure:
7
• The water in the primary flow circuit should be about room temperature (20 -30.).
• The Process Interface (PI) and the Process Controller (PC) should be switched on
and then the patching diagram is completed.
• In this experiment the Process Controller is only being used as an interface to the
computer.
• The positions of all the thermistors (1 to 5) are located and their significance with
respect to the flow circuits is determined.
• Now observed the readings of T1 (TTT is set to position A).
• Now by clasping hand around T1 (gripping tightly) , both the TTT reading and the
chart recorder are recorded.
• Next it is switched to B and the temperature is observed which should be the same
as T1.
• Then switch to A-B. This will give the temperature difference between A and B
(T1 and T2).
Patching Diagram:
8
Observation table:
EXPERIMENT NO-2
9
2) To control pressure with or without air receiver when different valves (i.e.,
V1,V2,V3,V4,V5,V6) are opened or closed
Apparatus required:
Theory:
The unit is designed to operate with the 38-200 and 38-300 Process
Interface and Process Controller to configure open or closed loop control circuits. The
pneumatic instrumentation comprises an I/P Converter and Pneumatic Control Valve.
The I/P Converter accepts a 4-20 mA control signal from the 38-200 Interface and
converts this to a 3-15 psi pneumatic signal which operates the control valve.
The control valve comprises the diaphragm actuator which positions the
stem of a plug type valve. An indicator on the valve shows the actual position on the
valve.
A set of manual valves V1,V2 and V3 allow a rear mount air receiver to be
connected in series or in parallel with the process pipe to change the response of the
system (to vary the process lag). The air receiver incorporates a pressure relief valve.
Step changes may be applied to the process by bleeding air through an
additional diffuser by opening and closing the valve V4.
The Discovery software contains an integral Chart Recorder and configuration
program.
12
Patching diagram:
Procedure:
1. Connect the equipment as shown in the patching diagram with the air receiver in
series with the process pipe.
20mA loops to provide a record of the response. The set point of the system has
been set to 50%.
Observe the response of the system when valve V4 is open and close to give a
disturbance.
Isolate the air receiver from the process pipe by opening V2 and closing V1& V3.
Apply a disturbance to the new configuration and observe the change in response.
Observation table:
1) To control pressure with or without air receiver
2) To control pressure with or without air receiver when different valves (i.e.,
V1,V2,V3,V4,V5,V6) are opened or closed
EXPERIMENT NO-3
Name of experiment:
Objective:
To control the flow of liquid using PID control.
Apparatus required:
THEORY:
A small change in the control effort will after the position of the servo valve
only slightly, but this will affect flow rate quite considerably. It can be said that the
process plant has a very high gain; a small change in the input (control effort to servo
position) produces a large change in the output (flow rate).
If the deviation between measured value and set point is changing rapidly this
will produce a large and so that care must be taken when selecting parameters values the
expression below is that made previously for PID control law.
Uc =Up + Ur + Ud
=k [e+ (1/Tr) + ∫edt +Td (de/dt)]
The greater PB is (so that smaller the system gains k), the smaller the overall
control effort will be for a measured deviation. This allows for a greater range of
derivative configuration to the control before it produces the oscillation.
In the practical, the PID values have been set such that the least performance is
achieved out of the system. We can observe changes, nothing the system response on the
chart recorder.
In the second part of the practical we can investigate the effect of the deviation
action on the overall system. We will be able to change Td from 0 to 5 seconds, in 1 sec
division.
Although this sounds very small, it will be enough of a variation to observe all
consequences derivation action in the control effort, both good and bad. We will be able
to switch derivative action ‘ON’ & ‘OFF’ as we did integral action earlier.
By providing the same deviation (changing the set point) in the most
convenient way of design this I to PI and PID algorithm, we will be able to observe the
difference between them.
There will be control bars on screen to change the set point, Tr and Td. We will
not apply Td>5 sec. As these will already be instability at this level, although there is of a
control bar on screen for PB gain, we are still able to change it using the manual keys on
the front of 38-300.
16
Patching diagram:
Procedure:
i. Complete the patching diagram.
ii. Ensure the control action set to reserve and then at the input filter FLT.1 is set
to 1 second.
iii. Fully open MV3.When initializations is complete switch ON the pump and
switch the controller to automatic mode. Thus the practical begins in PI mode,
with optimum values set for PI. The derivative action is logged with the
onscreen button. When the derivative component time is variable with the
control bars.
iv. Derivative action improves the response of controller to a rapidly changing
error and provides a breaking effect. When the measured variable approaches
the set point.
17
v. Integrating the overall performance of the system with respect to set point
changes, remembering that the system has been configured for optimum
performance. Note for this part of the experiment only the set point will be
changed.
vi. Once we have a feel for how the system performs, experiment with the full
range of Td and observe the response of the system to set point changes. We
will find that it is very easy to produce instability in the system, both in a
steady state situation & also when attempting to reach the set point.
Observation table:
Flow PB
Serial Control valve Tr(Tc)
Set point Meter range (% Td(sec)
No opening (%) (sec)
(%) )
1. 50 49.8 to 50.6 11 101 13 5
2. 60 59.4 to 60.5 24 123 19 4
3. 68 66.7 to 68.7 38 153 22 5
4. 75 73.8 to 74.9 49 192 20 7
18
Experiment No.-4
Experiment name:
Objectives:
Our aim is to control the water level in different tanks under various conditions and set
point.
Apparatus used:
The Coupled Tanks Unit consists of 4 tanks placed on a rig. Fifth reservoir tank is
placed at the bottom. In the reservoir two submersible pumps are placed, which pump the water
on command to the tanks. The water flows freely to the bottom tanks through the configurable
orifice. The way the water flows through the setup can be configured in many ways with manual
valves labeled (MV1, MV2, MV3, MV4 ). Configuration with valves allows for dynamics coupling
introduction and disturbances generation giving vast possibilities of control. Apart from the
mechanical parts the coupled tank system is equipped with power supply unit and power
amplifier (PSUPA) and the universal control interface (UCI). The UCI serves as an interface
between the PC and the PSUPA. Further more it can be used as a controller. The PSUPA unit
amplifier the water pressure-level signals and passes them an analog signal to the UCI and PC.
The pumps control signal can be sent from the PC through the UCI and PSUPA or from the UCI
to the PSUP
19
PID CONTROLLER:
A PID Controller consists of three blocks—proportional, integral and derivative.
Each of PID controller blocks (P, I and D) plays an important rule. A PID controller calculates an
error value as the difference between a measured process variable and desired set point. The
equation governing the PID controller is as follows-
The proportional block is mostly responsible for speed of the system reaction. However
for oscillatory plants it might increase the oscillations if the value of P is set to be too large.
The integral part is very important and assures zero error value in the steady state,
which means that the output will be exactly what we want it to be. Nevertheless the integral
action of the controller causes the system to response slower to the desired value changes and for
system were very fast reaction is very important it has to be omitted .Certain nonlinearities will
also cause problem for the integration action.
The Derivative part has been introduced to make the response faster. However, it
is very sensitive to noise and may cause the system to react very nervously. Thus, very often it is
omitted in the controller design. Derivative part output filtering may reduce the nervous reaction
but also slows the response of the controller down and sometimes undermines the sense of using
the Derivative part at all proper filtering can help to reduce the high frequency noise without
degrading the control system performance in the lower frequency band.
20
Procedure:
2. Make sure that the PC connects to UCI. Proper connection manage should appear in the
‘Connection Console’ window on LCD.
3. Select the UCI control mode from the working mode selection menu.
4. From the list of possible control schemes select the water level control in tank1/tank 3.
5. In the middle of control panel the plots of the measurements and control signal are
presented.
6. On the right, the displays are presented with the numerical representation of the
measurement.
7. On the left, a panel is placed for control parameters setting and variation.
9. While the experiment is running the controller parameters and the set point value can be
change.
10. If we are sure the configuration is correct we may start the control algorithms, by
pressing the ‘starts simulation’ button.
11. Observe the water level being controlled by the simple PI controller. We may change the
set point character using the provided interface. The controller parameter can also be
varied.
Observation Table:
21
For Tank 1-
Set point P I D
EXPERIMENT NO:5
To study pH control
Apparatus used:
• patch cord
• pH probe
The constituent components of the 38-716 are similar to those which can be
found in many industrial situations. The rig is specifically designed to withstand attack
from strong acid and alkaline fluids.
The effluent holding tank, reagent holding tank. Reaction vessel, treated
fluid tank, circulating pumps, variable area flow meters, manual flow control valves,
22
solenoid valves, motorized servo control valve and appropriate pipe work and fittings are
mounted on a support frame which is designed to stand on a firm level bench top.
Fig.1: a pH rig
The effluent to be treated is stored in the effluent tank and fed, via a filter, to a
constant speed high pressure circulating pump. The pump automatically switches off if
back-pressure becomes too great, i.e., at approximately zero flow. The switch-off point is
adjustable on the pump.
1) Control valve:
23
The control valve, in the reagent feed circuit, has been developed to
provide a small scale demonstration of an infinitely variable control valve. The
needle-type valve is driven by a dc electric motor is provided by the 38-200.
2) pH probe:
The current output from the 38-471 may be calibrated using the ‘zero’ and ‘span’
controls on its front panel. A small screwdriver may be used for this purpose. A set of
capsules to make up buffer solutions is also supplied for the purpose of calibration.
pH processes:
The parts of the process interface(PI) that have not yet been discussed are
the On-Off Control features, including 0-5 V Schmitt trigger with variable hysteresis
loop (providing variable threshold voltages) and logic inputs to the switched ac and
24V dc outputs. These are located next to the power unit-circuit breaker arrangement.
The On-Off Control found on the Process Interface can be used to control a
process without using the 38-300 Process Controller. The later assignments explore
the use of on-Off Control using the microphones controlled 38-300.
Patching diagram:
24
The DDM is not a highly accurate measurement device, but the purpose here is
to illustrate the process of calibration and to provide sufficient accuracy to the
practical that follow.
PC:
The 25-way D type connector is connected from the PC serial port to the left
hand connector on the 38-300 Process Controller rear panel.
The Connection switch (38-300 rear panel ) is ensured that it is set ON. And
the Termination switch (38-300 rear panel) is set to ON.
It is ensured that the treated fluid tank is emptied into a vessel of adequate
capacity at the conclusion of each experiment and is emptied at the start of an
experiment.