Chapter 7 - Formulating Network Problems

Uploaded by

zqweo23
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 55

Chapter 7

Formulating and Solving Network Flow


Problems
Prof. Hai Yang
Department of Civil and Environmental Engineering
HKUST

1
Outline

• Introduction to Network Flow Models

• Shortest Path Problem


– LP Formulation
– Dijkstra’s Algorithm
– Directed Arcs Example

• Maximum Flow Problem


– LP Formulation
– Maximum Flow Algorithm

• Minimum Spanning Tree Problem


– Minimum Spanning Tree Algorithm

• Summary

2
Network Flow Models

• A lot of real-life problems can be solved using network flow models.


– Minimum cost flow problem
– Shortest path problem The most fundamental
– Maximum flow problem
– Minimum spanning tree problem

c: arc cost
u: arc capacity –3
9 6
3 2
2
c12, u12 3
7 10
3 8 -1
+1 4
1
100,10
2
50,3
4 –7 1 5
8 5
6 7
7
+10 4
5 3 5 4
5

3
Minimum Cost Flow Problem

• The most fundamental model of all network flow problems


• 𝑥𝑖𝑗 = amount of flow from node i to node j
• 𝑢𝑖𝑗 (𝑙𝑖𝑗 ) = upper (lower) capacity of arc (i,j)
• 𝑐𝑖𝑗 = unit flow cost from node i to node j
• 𝑓𝑖 = net flow at node i
𝑓𝑖 > 0 for supply nodes (sources)
𝑓𝑖 = 0 for intermediate (transhipment) nodes
𝑓𝑖 < 0 for demand nodes (sinks)

What is the least costly shipment


arrangement through the network to
satisfy the demands at sinks from
available suppliers at sources ?

4
Minimum Cost Flow Problem:
LP Formulation

• The LP formulation in terms of the amount of flow from node i to


node j, 𝑥𝑖𝑗 , can be written as:

Minimize 𝑍 = σ𝑖 σ𝑗 𝑐𝑖𝑗 𝑥𝑖𝑗


Subject to: σ𝑗 𝑥𝑖𝑗 − σ𝑘 𝑥𝑘𝑖 = 𝑓𝑖 for all nodes i
(Outflow – Inflow = Net Flow)
𝑥𝑖𝑗 ≤ 𝑢𝑖𝑗 for all i and j
(Arc capacities not exceeded)
𝑥𝑖𝑗 ≥ 𝑙𝑖𝑗 for all i and j
(Meet the lower bound, if any, of each arc)
𝑥𝑖𝑗 ≥ 0 for all i and j

5
Minimum Cost Flow Problem:
LP Formulation Example
Min 𝑍 = 3𝑥12 + 4𝑥13 + 1𝑥14 + 5𝑥23 + 6𝑥25 + 1𝑥34 + 2𝑥35 + 2𝑥46 + 4𝑥56

subject to (Outflow – Inflow = Net Flow)

𝑥12 + 𝑥13 + 𝑥14 = 100 (Node 1 - Supply)


𝑥23 + 𝑥25 − 𝑥12 = 200 (Node 2 - Supply)
𝑥34 + 𝑥35 − 𝑥13 − 𝑥23 = 0 (Node 3 - Intermediate)
𝑥46 − 𝑥14 − 𝑥34 = −100 (Node 4 - Demand)
𝑥56 − 𝑥25 − 𝑥35 = −80 (Node 5 - Demand) Lower &
upper bound
−𝑥46 − 𝑥56 = −120 (Node 6 - Demand)

6
Minimum Cost Flow Problem
LP Formulation Example

Min 𝑍 = 3𝑥12 + 4𝑥13 + 1𝑥14 + 5𝑥23 + 6𝑥25 + 1𝑥34 + 2𝑥35 + 2𝑥46 + 4𝑥56

Subject to (Arc capacities)


50 ≤ 𝑥14 ≤ 80 (Arc 14)
70 ≤ 𝑥34 ≤ 120 (Arc 34)
100 ≤ 𝑥56 ≤ 120 (Arc 56)
𝑥𝑖𝑗 ≥ 0 for all arcs (i,j)

7
Minimum Cost Flow Problem:
Application Examples

• Distribution of a product from manufacturing plants to


warehouses or from warehouses to retailers.

• The flow of components and sub-assemblies through various


machining stations in a production line.

• Routing of automobiles through an urban street network.

• Sub-problem (All-or-Nothing) assignment in road traffic


assignment problem.

• Design of an offshore natural gas pipeline network connecting


well heads in the Gulf of Mexico to an inshore delivery point
with the minimum cost of constructing the pipeline.

• Determination of the maximum monthly capacity of a coal


slurry pipeline network joining coal mines and power plants.
8
Formulating and Solving Network
Flow Problems

Shortest Path Problems

9
Shortest Path Problem

• The simplest of all network flow problems.

• Goal: To find the shortest (least costly) path from a specific


origin node to a destination node.

• The shortest path problem can be formulated as a minimum


cost flow problem with one unit of supply at the origin node
and one unit of demand at the destination node.

9 6 2
3 2
7 10
3 8 -1 f1 = +1, f8 = –1, and
+1 4
1 5 fi = 0 for all other nodes
8 5
6 7
4
7 All arc capacities uij = 1
3 5 4
5
10
Shortest Path Problem Example:
LP Formulation

Both directions
Min 𝑍 = 3𝑥12 + 3𝑥21 + 4𝑥13 + 4𝑥31 + 5𝑥23 + 5𝑥32 + ⋯ + 5𝑥78 + 5𝑥87

Subject to (Outflow – Inflow = Net Flow)


𝑥12 + 𝑥13 − 𝑥21 − 𝑥31 = 1 (Node 1 - Supply)
𝑥21 + 𝑥23 + 𝑥24 + 𝑥26 − 𝑥12 − 𝑥32 − 𝑥42 − 𝑥62 = 0 (Node 2 - Intermediate)
𝑥31 + 𝑥32 + 𝑥34 + 𝑥35 − 𝑥13 − 𝑥23 − 𝑥43 − 𝑥53 = 0 (Node 3 - Intermediate)

𝑥84 + 𝑥86 + 𝑥87 − 𝑥48 − 𝑥68 − 𝑥78 = −1 (Node 8 - Demand)

𝑥𝑖𝑗 ≥ 0 for all i and j 9 6 2


3 2
7 10
3 8 -1
+1 4
1 5
8 5
6 7
7
4
3 5 4
5 11
Shortest Path Problem Example:
LP Formulation

Objective Value = 13
0 6
𝑥𝑖𝑗 0
1 2
1 0
1 8 -1
+1 4
1 0
0 0
0 0
7
0
3 5 0 9 6
0 2
3 2
7 10
3 8 -1
+1 4
1 5
8 5
6 7
7
𝑐𝑖𝑗 4
3 5 4
5

12
Shortest Path Problem Special Restricted Case
Case 1: Unavailable Arcs

• Finding the shortest path which does not go through


some arcs, e.g. arc (4,8)
→ Solution 1: Assign a high cost or length to those unavailable
arcs (e.g. arc (4,8))
→ Solution 2: Assign the capacity of those arcs to 0 and impose
capacity constraints
9 6 2
3 2
7 10
100 8 -1
+1 4
1 5
8 5
6 7
7
4
3 5 4
5
13
Shortest Path Problem Special Restricted Case
Case 2: Unavailable Nodes

• Finding the shortest path which does not go through some


nodes, e.g. Node 6

→ Solution 1: Assign a high cost or length to the arcs incident


to the unavailable nodes (Node 6)

→ Solution 2: Assign the capacity of the arcs incident to those


nodes to 0 and impose capacity constraints.

50 6
2 50
3 7 50 c26=50
3 8 -1
+1 1 5
4 c46=50
8 c86=50
7 5
6
7
4
3 5 4 Undirected arcs
5 14
Shortest Path Problem Special Restricted Case
Case 3: Compulsory Arcs

• Finding the shortest path which does go through an arc, e.g. arc
(4,7) or (7,4)
→ Does Not Work: Assign a zero cost to the compulsory arc (e.g. arc
(4,7))

9 6
2 2
3 10
7 3 8 -1
+1 4
1 5
8 5
6 0
7
4
3 5 4
5 Cost of 1-2-4-7-8 = 15
Cost of 1-2-4-8 = 13 (Optimal)

15
Shortest Path Problem Special Restricted Case
Case 3: Compulsory Arcs (Cont.)
• Finding the shortest path which does go through an arc, e.g. arc (4,7)
→ Solution:
(1) Find the shortest path between nodes 1-4 and 7-8: Cost = 22
(2) Find the shortest path between nodes 1-7 and 4-8: Cost = 23
(3) Take the smaller one, i.e. 1-2-4-7-8

9 6
2 2
3 10
7
3 8 -1
+1 4
1 5
8 5
6 7
7
4
3 5 4
5 16
Shortest Path Problem: Dijkstra’s Algorithm

• This algorithm finds the shortest path from source nodes to all other
nodes in the network.

• It is implemented by labeling nodes in the network.

• Label for node j is written as


𝑑 𝑗 , 𝑖 = [𝑑 𝑖 + 𝑐 𝑖𝑗 , 𝑖]

where i is the node immediately preceding j on the shortest path and d(j)
indicates the length of the current shortest path from s to j.

17
Labels

2
(3) (2)

(7) Total Node


1 4 5 Node (j) impedance to preceding j
(4) node (j)
(4)
3 1 0 -
2 3 1
3 4 1
2 4 5 2
5 12 4
1 4 5

18
Shortest Path Problem: Dijkstra’s Algorithm

• Step 1: Label node s with the permanent label [0,–]. Label every
node i connected to node s with a temporary label [c(s,i),s]. Assign
the label [∞, –] to all other nodes.

• Step 2: Select the node with the smallest temporary label, say node
i, and make it permanent.

• Step 3: For all node j connected to i by arcs that do not have


permanent labels, compare the current temporary distance label d(j)
with d(i)+c(i,j). If d(i)+c(i,j) < d(j), give a temporary label to node j
with [d(i)+c(i,j),i].

• Step 4: If all nodes have permanent labels, STOP. Otherwise, Go to


Step 2.

19
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City

• Consider a city with the following road network.

• Each node represents a road junction. Each road section has a different
length, as shown in the network diagram.

• Goal: To find the shortest path from node s to every other node.

6
A
3
C
4 2
s 1 E

3 2
B D
3
20
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City
• Step 1: Label node s with the permanent label [0,–]. Label every node i
connected to node s with a temporary label [c(s,i),s]. Assign the label
[∞, –] to all other nodes.

Initialization 6 [6,s]
[4,s]
A
3
C
4 2
[0,–]* s 1 E [∞, –]
3 2
B D
Permanent label with * 3
[3,s] [∞, –]

Preceding node is Node s


21
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City

• Step 2: Select the node with the smallest temporary label, say node i,
and make it permanent.

Iteration 1 6 [4,s] [6,s]


A
3
C
4 2
[0,–]* s 1 E [∞, –]
3 2
B D
3
[3,s]* [∞, –]
The smallest
temporary label
Permanent label with *
22
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City
• Step 3: For all node j connected to i by arcs that do not have permanent
labels, compare the current temporary distance label d(j) with d(i)+c(i,j).
If d(i)+c(i,j)<d(j), give a temporary label to node j with [d(i)+c(i,j),i].
• Step 4: If not all nodes have permanent labels, Go to Step 2.

6 [4,s] [6,s]
3
Iteration 1 A C
4 2
[0,–]* s 1 E [∞, –]
3 2
B D
3 The node connected
[3,s]* [6, B] to Node B and with
temporary label
3+3=6 23
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City
• Step 2: Select the node with the smallest temporary label, say node i,
and make it permanent.

The smallest Permanent label with *


temporary label

6 [4,s]* [6,s]
Iteration 2 3
A C
4 2
[0,–]* s 1 E [∞, –]
3 2
B D
3
[3,s]* [6, B]
24
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City
• Step 3: For all node j connected to i by arcs that do not have permanent
labels, compare the current temporary distance label d(j) with d(i)+c(i,j).
If d(i)+c(i,j)<d(j), give a temporary label to node j with [d(i)+c(i,j),i].
• Step 4: Go to Step 2.
4+3=7>6
Keep the old label

Iteration 2
6 [4,s]* [6,s]
A
3
C
4 2
[0,–]* s 1 E [∞, –]
3 2
B D
3
[3,s]* [5, A] [6, B]
4+1=5<6 25
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City

• Step 2: Select the node with the smallest temporary label, say node i,
and make it permanent.

6 [4,s]* [6,s]
Iteration 3
A
3
C
4 2
[0,–]* s 1 E [∞, –]
3 2
B D
3 Permanent label with *
[3,s]* [5, A]*

The smallest
temporary label
26
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City

• Step 3: For all node j connected to i by arcs that do not have permanent
labels, compare the current temporary distance label d(j) with d(i)+c(i,j).
If d(i)+c(i,j)<d(j), give a temporary label to node j with [d(i)+c(i,j),i].
• Step 4: Go to Step 2.

6 [4,s]* [6,s]
Iteration 3 3
A C
4 2
[0,–]* s 1 E [7, D]
3 2
B D 5+2=7
3
[3,s]* [5, A]*
27
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City

• Step 2: Select the node with the smallest temporary label, say node i,
and make it permanent.

The smallest
temporary label

6 [4,s]* [6,s]*
Iteration 4 3
A C
4 2
[0,–]* s 1 E [7, D]
3 2
B D
3
[3,s]* [5, A]*
28
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City
• Step 3: For all node j connected to i by arcs that do not have permanent
labels, compare the current temporary distance label d(j) with d(i)+c(i,j).
If d(i)+c(i,j)<d(j), give a temporary label to node j with [d(i)+c(i,j),i].
• Step 4: Go to Step 2.

6 [4,s]* [6,s]*
Iteration 4 A
3
C
4 2
[0,–]* s 1 E [7, D]
3 2
B D 6+2=8>7
3 Keep old label
[3,s]* [5, A]*
29
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City
• Step 2: Select the node with the smallest temporary label, say node i,
and make it permanent.
• Step 3: Check the label for all node j connected to i by arcs that do
not have permanent labels.
• Step 4: If all nodes have permanent labels, STOP. Otherwise, Go to
Step 2.

6 [4,s]* [6,s]*
Iteration 5 A
3
C
4 2
[0,–]* s 1 E [7, D]*
3 2
B D
3
[3,s]* [5, A]* 30
Shortest Path Problem – Dijkstra’s Algorithm
Example 1: Travelling in a City

• Optimal Solution:

6 [4,s]* [6,s]*
A
3
C
4 2
[0,–]* s 1 E [7, D]*
3 2
B D
3
[3,s]* [5,A]*
Skim tree for node s

31
Iteration s → A B C D E Table format
4 3 6 ∞ ∞
Initial
s s s - -

4 3 6 6 ∞
1 B
s s s B -

4 3 6 5 ∞
2 A
s s s A -

4 3 6 5 7 Distance label
3 D
s s s A D

4 3 6 5 7
4 C
s s s A D Predecessor (preceding
node) label
4 3 6 5 7
5 E
s s s A D

6
The node made permanent Red text cell s : label being checked
in current iteration 3
Yellow cell s : permanent label
Each iteration has two steps:
• Make the node with the smallest temporary label permanent
• Update temporary labels of nodes connected to the (new) permanent node 32
Shortest Path Problem – Dijkstra’s Algorithm
Example 2: Travelling in a City with One-Way Roads
• Consider a city with the following road network.
• Each node represents a road junction. Each road section has a
different length, as shown in the network diagram.
• Goal: To find the shortest path from node s to every other node.

A 15
C
100 20 55
10
30 60
s B D

33
Shortest Path Problem – Dijkstra’s Algorithm
Example 2: Travelling in a City with One-Way Roads

• Step 1: Label node s with the permanent label [0,–]. Label every
node i connected to node s with a temporary label [c(s,i),s]. Assign
the label [∞, –] to all other nodes.

[100, s]
Initialization
A 15 [∞, -]
C
100 20 55
10
30 60
[0, -]* s B D [∞, -]
[30, s]

34
Shortest Path Problem – Dijkstra’s Algorithm
Example 2: Travelling in a City with One-Way Roads
• Step 2: Select the node with the smallest temporary label, say node i,
and make it permanent.
• Step 3: For all node j connected to i by arcs that do not have
permanent labels, compare the current temporary distance label d(j)
with d(i)+c(i,j). If d(i)+c(i,j)<d(j), give a temporary label to node j with
[d(i)+c(i,j),i].
• Step 4: Go to Step 2. Cannot go to Node A
[100, s] from Node B

Iteration 1 A 15 [40, B]
C
100 20 55
10
30 60
[0, -]* s B D [90, B]
[30, s]* 35
Shortest Path Problem – Dijkstra’s Algorithm
Example 2: Travelling in a City with One-Way Roads
• Step 2: Select the node with the smallest temporary label, say node i,
and make it permanent.
• Step 3: For all node j connected to i by arcs that do not have permanent
labels, compare the current temporary distance label d(j) with d(i)+c(i,j).
If d(i)+c(i,j)<d(j), give a temporary label to node j with [d(i)+c(i,j),i].
• Step 4: Go to Step 2.
40 + 15 = 55 < 100

Iteration 2
[100, s] [55, C]
A 15
C [40, B]*
100 20 55
10
30 60
s B D
[0, -]* [30, s]* [90, B]
36
Shortest Path Problem – Dijkstra’s Algorithm
Example 2: Travelling in a City with One-Way Roads
• Step 2: Select the node with the smallest temporary label, say node i,
and make it permanent.
• Step 3: For all node j connected to i by arcs that do not have permanent
labels, compare the current temporary distance label d(j) with d(i)+c(i,j).
If d(i)+c(i,j)<d(j), give a temporary label to node j with [d(i)+c(i,j),i].
• Step 4: Go to Step 2. Node B is the only node connected from
Node A, but it already has a permanent
[55, C]* label → No change needed

A 15 [40, B] *
Iteration 3 C
100 20 55
10
30 60
[0, -]* s B D [90, B]
[30, s]* 37
Shortest Path Problem – Dijkstra’s Algorithm
Example 2: Travelling in a City with One-Way Roads
• Step 2: Select the node with the smallest temporary label, say node i,
and make it permanent.
• Step 3: For all node j connected to i by arcs that do not have permanent
labels, compare the current temporary distance label d(j) with d(i)+c(i,j).
If d(i)+c(i,j)<d(j), give a temporary label to node j with [d(i)+c(i,j),i].
• Step 4: If all nodes have permanent labels, STOP.
Only one temporary label left,
[55, C]* which is changed to permanent.

A 15 [40, B] *
Iteration 4 C
100 20 55
10
30 60
[0, -]* s B D [90, B]*
[30, s]* 38
Shortest Path Problem – Dijkstra’s Algorithm
Example 2: Travelling in a City with One-Way Roads
• What is the shortest path from Node s to Node A?
– Node A → Node C → Node B → Node s
– Shortest path: s-B-C-A, Distance 55.

[55, C]*
1 A 15 [40, B] *
C
100 20 55
10
30 60
1 s B D [90, B]*
[0, -]* [30, s]*

39
Shortest Path Problem – Dijkstra’s Algorithm
Example 2: Travelling in a City with One-Way Roads
• What is the shortest path from Node s to Node A?
Min 𝑍 = 100𝑥𝑠𝐴 + 30𝑥𝑠𝐵 + 20𝑥𝐴𝐵 + 10𝑥𝐵𝐶 + 60𝑥𝐵𝐷 + 15𝑥𝐶𝐴 + 55𝑥𝐶𝐷

s.t. (Outflow – Inflow = Net Flow)

𝑥𝑠𝐴 + 𝑥𝑠𝐵 = 1 (Node s - Supply)


𝑥𝐴𝐵 − 𝑥𝑠𝐴 − 𝑥𝐶𝐴 = −1 (Node A - Demand)
𝑥𝐵𝐶 + 𝑥𝐵𝐷 − 𝑥𝑠𝐵 − 𝑥𝐴𝐵 = 0 (Node B - Intermediate)
𝑥𝐶𝐴 + 𝑥𝐶𝐷 − 𝑥𝐵𝐶 = 0 (Node C - Intermediate)
−𝑥𝐵𝐷 − 𝑥𝐶𝐷 = 0 (Node D - Intermediate)
𝑥𝑖𝑗 ≥ 0 for all i and j 1 A 15
C
100 20 55
10
30 60
1 s B D

40
Shortest Path Problem – Dijkstra’s Algorithm
Example 2: Travelling in a City with One-Way Roads

• What is the shortest path from Node s to Node A?


𝑥𝐬𝐀 𝑥𝒔𝑩 𝑥𝑨𝑩 𝑥𝑩𝑪 𝑥𝑩𝑫 𝑥𝑪𝑨 𝑥𝑪𝑫
Min Z = 100 30 20 10 60 15 55
Node s 1 1 =1
Node A -1 1 -1 = -1
Node B -1 -1 1 1 =0
Node C -1 1 1 =0
Node D -1 -1 =0

1 A 15
C
Each column has one “1” and one “-1” 55
100 20
10
Optimal: z = 55, xsB = 1, xBC = 1, xCA = 1 30 60
1 s B D
41
Shortest Path Problem – Dijkstra’s Algorithm
Summary

• The shortest path problem have many real life applications.

• There are many different kinds of shortest path problems:


undirected graph, directed graph, with/without negative
edge/curve weight, with/without negative cycle, k-shortest
path, etc.

42
Formulating and Solving Network Flow
Problems

Maximal Flow Problem

43
Maximal Flow Problem

• The maximal flow problem is concerned with determining the


maximal volume of flow from one node (called the source) to another
node (called the sink).

• In the maximal flow problem, each link has a maximum flow capacity
which limits the flow through the arc.
1 12 3
16 20
• There is no cost associated with the flow.
s 10 4 9 7 t
• For any directed graph D = (V, A)
13 14 4
– Source (node): vs 2 4
– Sink (node): vt V: Set of vertices (nodes)
– Intermediate points (nodes): vi A: Set of arcs
– Link capacity: u(vi, vj)  0 (or uij) for each link (vi, vj)A

• Network D = (V, A, U)

44
Maximal Flow Problem

• Flow: a function f = {f(vi, vj)} (or link flow fij)

• Feasible flow: a flow f that satisfies:


– Capacity limitation:
for  link (vi, vj)A, 0  fij  uij
– Flow conservation:

q i=s

 fij −  f ji =  0 i  s, t
( vi ,v j )A ( v j ,vi )A −q i = t

where q is the volume of the feasible flow
• A feasible flow always exists, e.g., q = 0

45
Maximal Flow Problem: LP Formulation

Maximal Flow
max q
f
Flow
s.t. Conservation
q i=s

 fij −  f ji =  0 i  s, t
( vi ,v j )A ( v j ,vi )A −q i=t

0  fij  uij ,  ( vi , v j )  A

Capacity
Limitation

46
Maximal Flow Problem: LP Formulation: Example

• To determine the maximal flow in the network

12
16 1 3 20
s 10 4 9 7 t
13 4
2 4
14

Capacity

47
Maximal Flow Problem: LP Formulation

1 12 3
16 20
+𝑞 −𝑞
s 10 4 9 7 t
Max 𝑞
13 4
s.t. (Flow conservation) 2 4
14
𝑓𝑠1 + 𝑓𝑠2 = 𝑞 (Node s - Source)
𝑓12 + 𝑓13 − 𝑓𝑠1 − 𝑓21 = 0 (Node 1 - Intermediate)
𝑓21 + 𝑓24 − 𝑓𝑠2 − 𝑓12 − 𝑓32 = 0 (Node 2 - Intermediate)
𝑓32 + 𝑓3𝑡 − 𝑓13 − 𝑓43 = 0 (Node 3 - Intermediate)
𝑓43 + 𝑓4𝑡 − 𝑓24 = 0 (Node 4 - Intermediate)
−𝑓3𝑡 − 𝑓4𝑡 = −𝑞 (Node t – Sink/Destination)

(Link capacity constraints)


0 ≤ 𝑓𝑠1 ≤ 16 0 ≤ 𝑓𝑠2 ≤ 13 0 ≤ 𝑓12 ≤ 10 0 ≤ 𝑓13 ≤ 12
0 ≤ 𝑓21 ≤ 4 0 ≤ 𝑓24 ≤ 14 0 ≤ 𝑓32 ≤ 9 0 ≤ 𝑓3𝑡 ≤ 20
0 ≤ 𝑓43 ≤ 7 0 ≤ 𝑓4𝑡 ≤ 4
48
Maximal Flow Problem: Multiple Sources Network

• What if we have several sources and several destinations? We


want to maximize the total flow from all sources to all
destinations.
– Create a super-source and a super-sink.

49
Maximal Flow Problem:
Application Example

• Petroleum products in a pipeline network

• Cars in a road network

• Messages in a telecommunication network

• Capacity of a water distribution network

• Internet bandwidth

• Electrical power in the electricity supply network

• Sewer in the sewerage system

50
Formulating and Solving Network Flow
Problems

Minimum Spanning Tree Problem

51
Minimum Spanning Tree Problem
(undirected graph)

• For a network, a tree is a cycle-free (no cycle) connected network


consisting of a subset of nodes, and a spanning tree is a tree that
links all the nodes of the network.

2 4 2

1 3 5 1 3
Network Tree

2 4 2 4 2 4

1 3 5 1 3 5 1 3 5

Spanning Tree 52
Minimum Spanning Tree Problem
(undirected graph)

• Goal: To identify a spanning tree of


minimum cost or length.

• Any node should be reachable from any


other node in the network, but there
should be no redundant connections.

• Minimum spanning tree problem can be


formulated and solved as LP, but it is not
practical because numerous constraints
must be added to exclude all cycles,
resulting in a huge LP for even small
networks.

53
Minimum Spanning Tree Problem: Applications

• Constructing highways or railroads spanning several cities.


• Connecting a number of computer sites by high-speed lines, at the
least possible monthly leasing cost.
• Determining the minimum pipeline
network connecting offshore natural
gas wellheads with an inshore
delivery point.

Hub-and-Spoke

54
Summary

• Network Flow Models


– Minimum cost flow problem – most fundamental network flow model
– For each arc: Amount of flow, upper and lower bounds, and unit flow cost
– For each node: Net flow = +ve (sources), 0 (intermediate nodes), -ve (sinks)

• Shortest Path Problem


– Shortest path from an origin node to a destination node. One unit of demand.
– Besides solving as LP, Dijkstra’s Algorithm can be used.

• Maximal Flow Problem


– Find the maximal volume of flow from the source to the sink.
– Besides solving as LP, Maximal Flow Algorithm can be used.

• Minimum Spanning Tree Problem


– Link all the nodes in a network with no cycles at the minimum cost or length.
– Not practical to be formulated and solved as LP.

55