Sow Asphalt Frontcac-052416
Sow Asphalt Frontcac-052416
Sow Asphalt Frontcac-052416
The project is described as the repair and resurfaces the asphalt located at the Chancery
Front CAC driveway at the US Embassy Kuala Lumpur.
The Contractor is required to furnish all materials, labor, transportation, tools and
equipment and perform all work within in a fixed-price contract.
The entire Front CAC Parking asphalt is damaged with potholes. The soil is settling
around with cracks.
The work consists of milling, sweeping and overlaying the entire Front CAC driveway and
parking area with a 1 ½ inch compacted lift of asphalt.
Major Milling work shall be done with a self-propelled grinding machine capable of
removing 7ft of the asphalt in a single pass at a depth ranging from 1 to 2 inch. Minor
milling at the end of the lot or may be done with a smaller machine capable of removing
up to a 30 inch width. Unless otherwise noted, all milling shall do to an average depth of
1 ½ inches. All milling must be removed immediately from the pavement and must not
allow remaining in the lot more than a day. Care must be taken to avoid damaging the
existing concrete cover on the underground tanks adjoining storm sewer inlets. As such,
some chipping by use of a jackhammer maybe required.
1. Fixed-Price Proposal. The Contractor shall provide one fixed-priced Proposal for the
complete Project that includes every aspect of the Work.
2. Specifications. The Work shall be governed by the US Embassy Kuala Lumpur.
International Codes, which includes the National Fire Prevention Association (NFPA),
International Building Code, International Mechanical Code, International Plumbing
Code, and National Electric Code (NEC), also are applicable. Should there be a
discrepancy between the US Embassy Specifications and the applicable Building Code,
the more stringent of the two shall govern.
The Contractor is responsible for compliance with all Building Codes; Work not in
compliance with the Codes shall be deemed to be unacceptable.
3. Execution. The Work shall be executed in a diligent and workmanlike manner in
accordance with the negotiated fixed-price, this Scope of Work, the Project Schedule,
International Building Codes, and the laws of the City of Antananarivo where applicable.
4. Work Hours. Unless otherwise agreed with COR or the Facility Manager/COR , the Work
shall be executed during normal Embassy work hours. Night, weekend or holiday work
shall not be permitted except as arranged in advance with Facilities Management and
COR. Embassy holiday schedule is available from Facilities Management or COR. If any
aspect of this work is deemed by the Facility Manager to be interruptive of normal
embassy operations, the contractor shall be required to perform that portion of the
work at night, on Saturdays and Sundays. A provision for this should be included in the
response to the request for quotation. Working at night, on Saturdays and Sundays will
not be considered a change order or a change in field conditions, but rather a standard
provision of the contract.
5. Safety. The Contractor shall be responsible for conducting the work in a manner that
ensures the safety of the employees and visitors to the Embassy, as well as the
Contractor’s employees. All contractor personnel shall wear hard hats, safety glasses,
ear-plugs, gloves, close-toes shoes and any other Personal Protection Equipment
deemed necessary by the Facility Manager/ COR.
6. Workforce. The contractor shall provide all supervision, skilled and unskilled labor
needed to perform the work. The contractor shall prepare list of all the names of
personnel working for the contractor and any subcontractors, with national ID numbers
and submit the list to the Facility Manager/COR for vetting of employees by the RSO at
least 14 days prior to commencement of work.
7. Equipment. The contractor shall also provide the Facility Manager /COR with a list of all
equipment, listing the manufacturer, model, serial number of all equipment to be used
on this project at least seven (7) days prior to the commencement of any work. Any
vehicles utilized by the contractor are also considered equipment. The contractor must
provide make, year, model number and license plate number. All vehicles will be
inspected prior to entering and prior to leaving the premises. The contractor must
notify the Facility Manager in writing at least 24 hours in advance of the pending
removal of any contractor owned equipment.
9. Modification to Contract. The Contractor shall not incur any costs beyond those
described in this SOW unless directed otherwise in writing by the Contracting Officer.
Any work performed by the Contractor beyond this SOW without written direction from
the Contracting Officer will be at the Contractor’s own risk and at no cost to the
Embassy.
10. Stop Work. At any time during the Project, the Contracting Officer reserves the right to
Stop Work for protection of employees or visitors, security, or any other reason at
his/her discretion.
11. Submittals. The contractor is responsible to submit the following documents for COR
Review and approval. The Facility Manager/COR review, however, does not relieve of
the contractor’s responsibility for the engineering work as to provide a complete
working system:
a. Installer Qualifications:
All work under this Scope of work shall be performed by Construction Contractor
having experiences on asphalt works. The Contractor shall have the following
qualifications:
1. Qualifications for installation firm and installation supervisor
2. A list of the relevant projects. Do not list projects that proposed staff was not
involved, even if your firm was.
3. Qualifications/Experience of the firm
4. References
b. Materials
The Contractor shall provide product data and material safety data sheet for each
type of manufactured material with the design mixtures for the cationic emulsion,
binder course and hot mix asphalt as per ASTM standards.
12. Housekeeping. The contractor is responsible to clean up daily after working. All
cleanups should be done and completed before 4:30 PM daily.
3.0 SCOPE OF WORK:
“Front CAC PARKING AND DRIVEWAY ASPHALT REPAIR”: the contractor shall be furnishing,
handling, placing, and compacting all paved surfaces as set forth in this specification.
1. General Requirements
a. Within 5 days of Notice to Proceed/ PO issued, the contractor shall provide to the
COR a project schedule showing start to completion including significant milestones.
b. Within 10 days of Notice to Proceed/ PO issued, the Contractor shall provide to the
COR details of the proposed installation utilizing written description or sketches or
both.
e. When pursuing the work, the contractor is to take extra care as not to damage the
existing structure. The cost of any contractor damage to the structure will be
calculated by the Facility Manager and deducted from the payment of the final
invoice.
f. The Contractor shall provide protection such as taping, covers, plastic sheathing,
drop cloths and any other protective materials as needed so as to protect all areas
that are not to be coated prior to surface preparation.
g. The Contractor shall properly dispose of all soiled rags and protect unused product
from freezing.
2. Asphalt work
The asphalt work will concern the entire Front CAC and Driveway Asphalt Parking area where
many areas are damaged with potholes and the soil is settling around with cracks.
2.1. Preparation
a. The Contractor shall assess all points that are affected and mark out all areas.
b. The Contractor will remove all affected areas asphalt by milling at the base course
surface for at least 1 ½ inch – 2 inch and all edges shall be thoroughly broomed and
coated with an asphalt tack coat.
c. The Contractor shall ensure that the surface to be paved is cleaned with compressed
air and any dusts shall not be present for the adhesion of primer and tack coat.
2.2. Asphalt
All asphalt materials shall be preliminary approved by the COR before any application.
The Contractor shall submit in advance all aggregates and asphalt analysis as per ASTM
or AASHTO standards for testing. The test designations listed below are those that are
currently specified for use at least in this Project.
iii) The asphalt paver shall lay the material to the required thickness and level.
iv) The mix shall be compacted as soon as possible after spreading the material.
Tandem rollers shall follow the laying operation to carry out breakdown rolling up to
temperature of 110- 120° C. Pneumatic tired rollers and tandem rollers shall follow the
breakdown rolling and sufficient passes shall be made to achieve the required
compaction.
Rolling shall start from the sides and proceed toward the center. Each trip of the roller
shall overlap the pervious trip by at least 30 cm. Roller wheel shall be kept moistened.
The roller shall be capable of reversing without backlash and shall be free from worn
parts.
Heavy rollers shall be used to complete all rolling including elimination of waves caused
by the lighter rollers. Full compaction shall be obtained before the asphalt temperature
reaches 100° C. Compaction shall be in accordance with specification of relevant
standard.
v) The construction joints shall be prepared by cutting the layer vertically down by
means of asphalt saw cutting machine or with jack hammer. The joint shall be cleaned
well by compressed air and tack coat material shall be applied on the vertical and
horizontal surface for better bonding. Extremely good care shall be taken when asphalt
is laid at construction joints.
vi) The areas inaccessible for heavy rollers shall be compacted with plate compactors or
hand tampers. After reaching the base course top level, suitable fill material (dune
sand) shall be dumped to the top level of base course on the sides of road shoulders. It
shall be leveled, shaped (1:6 ratios) and compacted to 90% maximum dry density.
a. Tack coat
Provide emulsified asphalt conforming to ASTM D 2397 and AASHTO M-208 - Standard
Specification for Cationic Emulsified Asphalt.
Dilute the emulsified asphalt with equal parts of water. The base asphalt used to manufacture
the emulsion shall show a negative spot when tested in accordance with AASHTO T 102.
i) The material shall be applied at the rate of 0.3 to 0.6 lit/ sq.m at the temperature not
exceeding 54 °C above the binder and at where there is a joint with existing asphalt surface.
ii) The surface shall be cured for the period as per manufacturer’s recommendations until a
tacky surface is visible.
b. Surface course
Surface Course Bituminous Concrete design mixtures shall respond to all ASTM and
AASHTO standard specifications for Hot Mix Asphalt stipulated above. The Contractor shall
submit, with the design mixtures, the sufficient passes to reach the optimum compaction of the
asphalt.
i) The hot asphalt mix shall be spread over the cured surface of tack coat by automatic asphalt
paver to the required profile and thickness.
ii) The mix shall be compacted as soon as possible after spreading the material. Tandem roller
shall follow the laying operation to carry out breakdown rolling up to a temperature of 110-
120° C.
Self-propelled rollers and Tandem rollers shall follow the breakdown rolling and sufficient
passes shall be made to achieve the required compaction.
Rolling shall start from the sides and proceed toward the center. Each trip of the roller shall
overlap the previous trip by at least 30 cm.
Roller wheels shall be kept moistened. The roller shall be capable of reversing without backlash
and shall be free from worn parts. Heavy tandem roller shall be used to complete all rolling
including elimination of waves caused by the lighter rollers. Full compaction shall be obtained
before the asphalt temperature reaches 80° C. Compaction shall be in accordance with
specification of relevant standard.
Along curbing, structures, and all places not accessible to the roller, the mixture shall be
thoroughly compacted by tampers. Such tampers shall not weigh less than twenty-five (25)
pounds and shall have a tamping face of not more than fifty (50) square inches.
iii) No vehicular traffic loads shall be permitted on the newly paved area until adequate stability
has been attained and the material has cooled sufficiently to prevent distortion or loss of fines.
A minimum period of 12 hours shall be considered after the completion of the rolling.
3. Closeout
1. At completion of work, the Contractor shall clean any impacted areas to a condition
equal to original condition.
2. All shipping materials and construction debris are to be disposed of in a legal manner
outside of the Compound.
2. Point of Contact. The COR shall be the main point of contact for this Project. The
Contractor shall report to the COR on (a) status of the Project, (b) changes in Schedule,
(c) accidents and safety issues, (d) disruptions to utility services; and all other important
information pertaining to the Project
4. Management Personnel. The Contractor shall staff the site, full-time, with a competent
senior manager who shall perform project management. Remote project management
is not an option. This individual shall keep a detailed written history of the project and
shall update the Government weekly.
5. Site Security. The Contractor is responsible for on-site security as necessary to ensure
no unauthorized access to their work sites. The Contractor is 100% responsible for
securing their working materials and equipment. Any damage to facilities or
infrastructure, which happens due to a lack of security, will be the responsibility of the
Contractor to correct.
7. Health and Safety. The Contractor shall be solely responsible for risk assessments,
managing health, and safety issues associated with this project. Based on hazard
assessments, Contractor shall provide or afford each affected employee personal
protective equipment (PPE) that will protect the employee from hazards. At a minimum
PPE shall consist of eye protection, hard hats, closed toe shoes and respiratory
protection with filters. If the workers arrive on-site with sandals or athletic shoes, the
Contractor is expected to provide rubber boots to them or send them home. All
construction workers and management personnel must wear hard hats at all times on
the construction sites. Other PPE such as gloves, dust masks, air respirators and boots
are also recommended. These items must be provided at the Contractor’s expense.
Workers may use discretion if they feel unsafe in using the equipment in a hostile
environment. Any worker at an elevated location above 4 meters, with the exception of
a portable ladder, must be provided and utilize a safety harness.
The contractor must document in the bid for work how the hazard controls will be
implemented and maintained during the project. The Contractor shall prepare and
implement an Activity Hazard Analysis (AHA) prior to the start of work. The Contactor
must have a competent person on-site for inspection of equipment, training workers in
the safe use of equipment and the recognition of hazards related to their use,
supervision, and identifying and correcting unsafe work practices for high hazard work.
END OF SOW