CHAPTER
2. LITERATURE REVIEW
2.1. Introduction
Many articles and studies conducted on causes of delay in construction projects
have been reviewed either locally or internationally. To achieve this study few
articles published during the last 20 years were reviewed concerning delays and time
management used like.
The study Sugiharto Alwi and Keith Hampson (2006) showed that in Indonesia
(Bali) there is no agreement between the two groups of contractors (small and large
contractors). In their result, it stipulates that those contractors generally agree on the
importance ranking of the individual delay variables. Recently contractors tried to
overcome delay problems; the main reason is because the contractors have no ability
to identify the important causes of delay occurring during the construction process.
2.2. Fundamentals of construction contracts
In construction contract there are two (2) types of risk either contractual or
construction itself.
6
2.2.1. Contractual Risk
In case there is no damage for delay, “Contractor‟s sole remedy for delay, loss
of productivity, impact damages or other similar claims shall be an extension of time
in which to complete the work. In no event in which to complete be entitle to
additional compensation or damages for delay. The owner shall not be liable in
monetary damages for the cost of delays which arise from acts or omissions for which
the owner is responsible.
In case of Limited delay damages the contractor shall be entitled to an
increase in the General Conditions if the Contractor‟s General Condition has actually
been increased as a result of a delay to the critical path of the Project Schedule caused
by the improper acts or omissions of the Owner.
Finally in case of Delay Damages, “In the event that Contractor's performance is
delayed or hindered , through no fault of its own Contractor through no fault of its
own, Contractor shall be entitled an extension of time corresponding to the number of
days its performance was delayed, and shall be entitled to additional costs related to
such delay or hindrance."
2.2.2. Extension of time
According to Tony Farrow (2007) Extensions of time clauses in construction
contracts do not assist the parties because they are not prescriptive; they are drafted in
a general way and it is not industry practice to predetermine how delays should be
7
analyzed, either in terms of methodologies or in dealing with such factors as float and
concurrency.
Adding to that if the Contractor is delayed at any time in the commencement
or progress of the work by an act or neglect of the Owner or Architect, or of an
employee of either, or a separate contractor employed by the owner, or by changes
ordered in the work, or by labor disputes, fire, unusual delay in deliveries,
unavoidable causalities or other causes beyond the Contractor‟s control, or by delay
authorized by the Owner pending mediation and arbitration, or by other causes which
the Architect determines may justify delay, them the Contract Time shall be extended
by Change Order for such reasonable time as the Architect may determine.
2.3. Construction schedule delays
The task of investigating the events that led to project delay for the purpose of
determining the financial responsibilities of the contracting parties arising from the
delay is called “delay analysis” or DA.
2.3.1. Types of delays
Terry Williams (2001) revealed that there are three basic ways to group delays
which are excusable delay with compensation, excusable delay without compensation
and non-excusable delay. Therefore Trauner et al, 2009 has specified that delay might
be groups in four main groups which are critical or non-critical, excusable or non-
excusable, compensable or non-compensable, concurrent or non-concurrent delays
can be classified by their origin (Caused Delays or CD), compensability (Excusable
8
Delays / ED and Non-Excusable Delays / NED), and timing (Non-Concurrent Delays
/ NCD and Concurrent Delays / CD).
Project Delays'
Classification
(PDC)
Origin Compensability Timing
Third Non-excusable
Owner Contractor Excusable Non-concurrent Concurrent
Party (NED)
(OCD) (CCD) (TPCD) (ED) Non-compensable (NCD) (CD)
Compensable Non-compensable
(ECD) (ENCD)
Figure 2-1: Project Delays Classification
(Source: Trauner et al, 2009)
2.3.1.1. Excusable versus non-excusable delays
All delays are either considered as excusable or non-excusable. According to
Callahan et al. (1992) and Trauner et al. (2009), it depends on the clauses in the
contract. Excusable Delays are further subdivided into two categories. They are Non-
Compensable Delays and Compensable Delays.
An excusable delay is a delay that is due to an unforeseeable event beyond
the contractor‟s or the subcontractor‟s control for instance general labor strikes, fires,
9
floods, acts of god, owner-directed changes, errors and omissions in the plans and
specifications, differing site conditions or concealed conditions, unusually severe
weather, intervention by outside agencies, lack of action by government bodies
(building inspection). In addition to that, Levy (2006) adds two more excusable
delays to the above list as illness or death of one or more of the contractors,
transportation delays over which the contractor has no control. In another study,
Kelleher (2005) added two more conditions which are epidemics, quarantine
restrictions.
Non-excusable delays are events that are within the contractor‟s control or
that are foreseeable. Mubarak (2005) defines non-excusable delays as “delays that are
either caused by the contractor or not caused by the contractor but should have been
foreseen by the contractor”. Furthermore Trauner et al. (2009) point out some
examples which are late performance of sub-contractors, untimely performance by
suppliers, faulty workmanship by the contractor or sub-contractors, a project-specific
labor strike caused by either the contractor‟s unwillingness to meet with labor
representative or by unfair labor practices. Moreover Mubarak (2005) added some
more examples as Contractor cash-flow problems, accidents on the site caused by the
contractor‟s negligence or lack of preparations, late delivery of the contractor‟s
furnished materials and equipment.
Obviously, the distinction between these two is significant in that it
determines which party is liable for the delay. It dictates whether or not a contractor
10
would be entitled to a time extension and possibly if the contractor would be entitled
to compensation for that time extension.
DELAY
CATEGORIES
NON
EXCUSABLE EXCUSABLE
BEYOND CONTRACTOR
CONTROL WITHIN CONTRACTOR CONTROL
OWNER CHALLENGES CONTRACTOR SLOW
UNFORCESEEABLE PROGRESS
SUB CONTRACTOR
WEATHER SLOW
DIFFERING SITE PROGRESS
CONDITIONS BROKEN EQUIPMENT
STRIKES NO TIME EXTENSION / LD RELIEF
COMPENSABLE NON COMPENSABLE
POSSIBLY $ FOR DELAY NO $ FOR DELAY BEYOND
WITHIN OWNER CONTROL OWNER CONTROL
OWNER CHANGES UNFORCESEEABLE
DIFFERING SITE CONDITIONS WEATHER
STRIKES
Figure 2-2: Delay Categories
(Source: Trauner et al, 2009)
11
2.3.1.2. Critical versus Non-critical delays
Several studies classify delays only into three groups as Excusable and Non-
excusable, Compensable and Non-compensable and Concurrent and Non-concurrent.
Therefore certain authors (Trauner et al., 2009; Callahan et al., 1992) added one more
category which is critical and Non-critical delays.
According to them, delays that affect the project completion, or in some cases
a milestone date, are considered as critical delays, and delays that do not affect the
project completion, or a milestone date, are noncritical delays.
Trauner et al. (2009) also notified that the issue of critical delays emerges
from the Critical Path Method (CPM) scheduling. The determining which activities
truly control the project completion date depends on the following criteria which are
the project itself, the contractor‟s plan and schedule (particularly the critical path), the
requirement of the contract for sequence and phasing, the physical constraint of the
project.
2.3.1.3. Compensable versus Non-compensable Delays
According to Callahan (1992), an excusable delay can be classified either
“excusable compensable” or “excusable non-compensable”. Some studies notified
that excusable non-compensable delays are normally beyond the control of either
owner or contractor such as unusual weather conditions, natural disasters, wars,
national crises, floods, fires or labor strikes. There is a general lack of understanding
concerning the Non-Compensable Delay for weather. It should be noted that a Non-
12
Compensable Delay is for unusually severe weather. That is weather which is not
anticipated at that time of year in that part of the country.
On one hand "Non-compensable delays" are excusable delays which are
actual delays to the project schedule but are within the parties' contemplation and not
the fault of either the contractor or the owner. These include delays caused by unusual
weather, other acts of God, and even some forms of labor disputes. Essentially, these
types are beyond the control of the parties and, therefore, will neither be compensated
nor penalized to any particular party to the construction project. Although the
contractor is not entitled to extra compensation for non-compensable delays, in most
instances it is entitled to an extension of contract time.
"Compensable delays," on the other hand, are excusable delays to the
construction schedule which are allegedly within the control of the parties and are
caused by the fault of one party or the other or even a combination of forces. In these
instances, the parties to the contract undoubtedly have incurred cost impacts to their
extended performance due to an extended period of time that the project covers.
2.3.1.4. Concurrent delays
According to Callahan et al. (1992) too concurrent delay is “more than one
delay contributed to the project delay, not that the delays necessarily occurred at the
same time”. Mubarak (2005) states that a concurrent delay includes a combination of
two or more independent causes of delay occurring within the same time frame. For
Levy (2006), it is known as overlapping delays.
13
Furthermore Mark Boe, P.E. stated in the Capital Project Management, Inc
that concurrent delay occurs when a contractor and an owner have both caused
independent critical path delays — delays that affect the completion date of a project
— during the same approximate time period. Consequently, barring a contract
provision to the contrary, neither can recover damages without a clear allocation of
each party‟s delay and expense.
Concurrent delay refers to the complex situation where more than one event
occurs at the same time, but where not all of those events enable the contractor to
claim an extension of time or to claim loss and expense.
2.3.2. Causes of delay
The result of the study of Alwi and Keith Hampson (2003) concerning the
main causes of delay in Indonesia is poor design, user changes, weather, site
conditions, late deliveries, economic conditions and increases in quantity. In addition
to that, Hampson et al. (2001) stated that destructive conflict resolution leads to
additional costs and delays to a project.
Also Chan and Kumaraswamy (1997) found that the five principal and
common factors of delays to be poor risk management and supervision, unforeseen
site conditions, slow decision making involving all project teams, client-initiated
variations, and necessary variations of works.
In the study of Murali Sambasivan and Yau Wen Soon (2006) the most
important causes were contractor‟s improper, planning, contractor‟s poor site
14
management, inadequate contractor experience, inadequate client‟s finance and
payments for completed work, problem with subcontractors, shortage in material,
labor supply, equipment availability and failure, lack of communication between
parties and mistakes during the construction stage.
According to Sugiharto Alwi and Keith Hampson the delay factors were
divided into six (6) major groups which are People, Professional Management,
Design and Documentation, Materials, Execution and External. Their research
stipulates that the main causes of delay are poor design, user changes, weather, site
conditions, late deliveries, economic conditions and increases in quality.
Kaming et al. (2006) studied influencing factors on 31 high-rise projects in
Indonesia and found out that cost overruns occur more frequently and are more severe
problem than time overruns. They stated the majors factors influencing cost overrun
are material cost increase due to inflation, inaccurate material estimation and degree
of complexity.
Al-Barak discussed the main causes of failure in Construction industry in
Saudi Arabia by surveying 68 contractors and about 34 different causes of failure.
The study concluded that lack of experience, poor estimation practices, bad decisions
in regulating company‟s policy, and national slump in the economy are the severe
factors.
15
Figure 2-3: Factors of delays in construction project
(Source: Assaf et al, 2006)
- 16 -
2.3.3. Effects of delays in construction
Gene Wortham has presented in his study that construction delays has for
effects acceleration, schedule change or inefficiency, delayed project completion,
missed intermediate completion dates, liquidated damages, frustrations of the parties
(claims) and last but not the least increased costs of the projects.
In the research about the problems of projects and effects of delays in the
construction industry of Pakistan, 2011, it stipules that mostly delay problems are
cause of dispute, negotiation, lawsuit, total desertion, litigation and abandonment.
The parties included in contract through claims agree on the additional capital and
extra time linked with construction delay. The general consequences are the loss of
wealth, time and capacity. For owner, delay means the loss of income and
unavailability of facilities. For contractor, delay means the loss of money for extra
spending on equipment and materials and hiring the labor and loss of time.
Delays on a project will have different contractual consequences depending on the
cause of the delay. First when impacts on the completion date is caused by the
contractor, the contractor will be liable to pay Liquidated and Ascertained Damages
(LAD's) to the client. Second if the impacts the completion date is not caused by
either party, the contractor may be entitled to an extension of time. And third when
the delay is caused by the client, the contractor may be able to claim an extension of
time and loss and expense.
- 17 -
2.4. Methods of Delay Analysis
To identify delays and to measure the effects on a construction projects, it is
primordial to use the appropriated methods. In delays construction, bar charts and
Critical Path Method are the basic tools to identifying them. To make sure that the
agreed construction duration is done on time, a planned schedule should be given by
the contractor. With that they will maintain and upload any changes on the project
(unexpected conditions). A basic premise of schedule delay analysis is that delay is
measured from the project‟s completion rather than from any interim activity date
(Bramble and Callahan 2002). When a schedule delays occurs, the as-planned and as-
built schedules are the basic data source for delay analysis (Bubshait and
Cunningham, 1998).The main idea is that the as-planned versus as-built method
compares two schedules, which is why it is also called “the total time method or net
impact method”. The hypothesis is that the contractor is not responsible of the delay
and the owner causes all delays.
In the theory of Nguyen (2007), the method displays the net impact of all claimed
delays on project‟s finish date. There are three kinds of activity in as-built schedules
which are the delayed activity, actual duration activity and actual time-shortened
activity.
- 18 -
*As-planned by Contractor
*As-built by owner
Figure 2-4: As-planned and As-built schedule
(Source: Delay Analysis Method Using Delay Section)
2.5. Planning sequences in construction industry
According to C. Hendrickson (1998), construction planning is a fundamental
and challenging activity in the management and execution of construction projects. It
involves the choice of technology, the definition of work tasks, the estimation of the
required resources and durations for individual tasks, and the identification of any
- 19 -
interactions among the different work tasks. A good construction plan is the basis for
developing the budget and the schedule for work.
2.6. Methods of minimizing construction delays
Based on several studies of project success factors and rectification of delays in
construction project, several recommendations were given to all parties. First owners
should pay progress payment to the contractor on time, minimize change orders
during construction to avoid delays, avoid delay in reviewing and approving of design
documents than they anticipated, and check for resources and capabilities, before
awarding the contract to the lowest bidder (Assaf. and Al-Hejji, 2006).
Secondly these are the recommendations from Majid, 2006: frequent progress
meeting, use up-to-date technology utilization, use proper and modern construction
equipment, use appropriate construction methods, effective strategic planning, roper
material procurement, accurate initial cost estimates, clear information and
communication channels, frequent coordination between the parties involved, proper
emphasis on past experience and proper project planning and scheduling.
- 20 -