Operations: Field GG Spud Date 28/01/2016 Well GG 2/2 - Vertical P.B 2355 Perforation Intervals 1805.5-1812.5 M

This document provides the game plan for well HH 83/5X, including operations, safety considerations, required materials, boats, rig issues, and mud plan. Key points are: 1) Current operations include keeping the hole filled, drifting tubulars while running in hole, and perforating at 1805.5-1812.5m. 2) Forecast operations include running in hole with a cleaning assembly, circulating until clean, and running in hole with a scraping assembly. 3) Safety permits must be signed by the company man. Required materials include a scraper and drill pipe. 4) The rig has issues with some engine generators and air conditioning that need addressing. Mud parameters

Uploaded by

Mohamed Hamdy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
125 views3 pages

Operations: Field GG Spud Date 28/01/2016 Well GG 2/2 - Vertical P.B 2355 Perforation Intervals 1805.5-1812.5 M

This document provides the game plan for well HH 83/5X, including operations, safety considerations, required materials, boats, rig issues, and mud plan. Key points are: 1) Current operations include keeping the hole filled, drifting tubulars while running in hole, and perforating at 1805.5-1812.5m. 2) Forecast operations include running in hole with a cleaning assembly, circulating until clean, and running in hole with a scraping assembly. 3) Safety permits must be signed by the company man. Required materials include a scraper and drill pipe. 4) The rig has issues with some engine generators and air conditioning that need addressing. Mud parameters

Uploaded by

Mohamed Hamdy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

GAME PLAN #1_ HH 83/5X_NAO_GPC

Field
Well
P.B

GG
GG 2/2
Vertical
2355

Spud Date

28/01/2016

Perforation
intervals

1805.5-1812.5
m

Operations
Current:
** Keep hole fill every time
** Drift all tubular while RIH
** PB 1931mt TD
1. HPJSM, flow check well static , POOH with milling assy. BHA #3
Forecast:
2. RIH with BHA #4; 8-1/2 open jet TCI bit (equipped with float valve) cleaning assy
to 1931 mt, POOH & R/B with same
o Keep hole fill
o Check proper installation for a float valve (drillers responsibilities)
3. RIH with BHA #5; 9-5/8 scrapper assy. To 1931 mt, circ. Till shaker clean, POOH
& R/B with same
Safety:
All work permits should be signed by a company man
Barge:
- Water maker quality is low
- Boat MD 11 (D/P, tubing)
- Boat misr gulf 15 (spooler machine, ESP, slick line unit & tools..Deisel 40,000
litre)
Material required:
- 9-5/8 scrapper, 1500 mt inspected 5 D/P
- High pressure hose from rig floor to platform

Safety always is safety first


Company Man
Mahmoud Abdelrazik

GAME PLAN #1_ HH 83/5X_NAO_GPC

Field
Well

NAO
Spud Date
20/04/2016
HH 83/5X Exploratory - Deviated Max I 28.07 @
614 m
2116.94 m
Last csg shoe 13-3/8 @ 710 m

TD

Operation: Cont. drlg 12-1/4 hole to 840 m to 950 or top of Belyim(wash & ream
twice once every stand , sweep hole with 10 bbl lo-vis followed 20 hi-vis) , POOH wiper
trip to csg shoe , Cont. drlg to 1250 m (TD)
** keep monitoring shaker screens cleaned , mud pits , mud parameters , overboard
ditch cleaned all time
After tomorrow >> Fill up tools , cold cutter (on location; please check) ,
MLH engineer ?? no answer
Plan for mud: dont add EMEC TEX , add
before kareem fm with 50 mt
Treatment only
If losses appeared please call me

Boats: Masr gulf: WA gharib >>


remaining csg and hlb floating eq. ,
food container
Capitano gee: 60 jt csg , IPJ 9-5/8 csg
handling equipment , BHI back up tools
Md 11 >> rig >> LCM non
conventional >> getty
Md 8 >> ad 6
Problems: no problems

Rig issues:
-

Two engine out of hours , 4th engine generator not in location


Air conditioning very bad , open internet full access
SWACO sup to check shaker conditions
Plan for hlb cmt replacement with slb one

GAME PLAN #1_ HH 83/5X_NAO_GPC

Safety first is safety always