Jump to content

Grants:IEG/Lua libs for behavior-driven development/Timeline

From Meta, a Wikimedia project coordination wiki

Timeline for Lua libs for behavior-driven development

[edit]
Timeline Date
Baseline for the community portal is up and running 1. June 2016
Week 26; done initial setup, working on page indicators 3. jul 2016
Week 27; changed to strategy patterns, working on final report 10. jul 2016
Week 28; done class final report, documentation 17. jul 2016
Week 29; nothing to report 24. jul 2016
Week 30; working on extract status and invoke subpage, started on a common monitor user 31. jul 2016
Week 31; working on logging, tracking categories, and a lot of refactoring 7. aug 2016
Week 32; done console interaction, started on expectations 14. aug 2016
Week 33; working on expectations, doc on notifications 21. aug 2016
Week 34; working on expectations, start working on renders 28. aug 2016
Week 35; done renders for result, started on frame, started on extractors 4. sept 2016
Week 36; done extractors, started on README (sdd) 11. sept 2016
Week 37; done missing tests, done introduction to basic idea 18. sept 2016
Week 38; notes and a few tests on an alternate coverage model 25. sept 2016
Week 39; nothing to report 2. oct 2016
Week 40; nothing to report 9. oct 2016
Week 41; nothing to report 16. oct 2016
Week 42; nothing to report 23. oct 2016
Week 43; nothing to report 30. oct 2016
Week 44; remove use of extension data, refactor 6. nov 2016
Week 45; i18n, indications of bug in pageprops 13. nov 2016
Week 46; nothing to report 20. nov 2016
Week 47; design, icons, refactor indicators 27. nov 2016
Week 48; refactor, PSR-logging, logging, tracking categories, bug in pageprops 4. dec 2016


Monthly updates

[edit]

Please prepare a brief project update each month, in a format of your choice, to share progress and learnings with the community along the way. Submit the link below as you complete each update.

June

[edit]

A basic portal is up and running on Help:Spec.

This is before project start, aka month 0, but after a question from FDC on how to do community outreach. The portal is pretty sketchy so far.

July

[edit]

Set up the test environment, and figuring out the overall organization. Testing some alternate solutions.

Methods for identifying the correct page for test module, and invoke the method to get the test report. Most of this code is pretty general, and it is possible to repurpose the code for other frameworks. That is it is agnostic to spec-style testing, it only assumes tap-formatted reports.

Some basic documentation.

August

[edit]

Buttons for the test panel works, and calls the correct exported method. Reports will then be collected from the Scribunto debug facility. The reports are assumed to be TAP13, with additional data as comments.

Work is ongoing on the expectations, that is the expect and subject library functions. Rewrote several times, in the end it is somewhat similar to the proof of concept.

Started on reporting and realization of the reports, it seems like compact and full text report should be sufficient, and probably a vivid html report.

September

[edit]

Low activity, mostly documentation and notes on alternate solutions.

Awaiting reply on midpoint report.

October

[edit]

Is your final report due but you need more time?



Extension request

[edit]

New end date

[edit]

15. December 2016 (The new end date is not clear at all at this point.)

Rationale

[edit]

Have not been able to work on this project lately.

Extension request

[edit]

Noting that a more recent and complete extension request was posted on 3 January 2019 at Grants talk:IEG/Lua libs for behavior-driven development#Extension request, new completion date. Program officer reply and approval was also posted there on 4 January 2019.

Approved new end date

[edit]

30 June 2019

New final report due date is 30 July 2019. -- JTud (WMF), Grants Administrator (talk) 23:06, 4 January 2019 (UTC)