Trabajo Calculo de Hidrologia
Trabajo Calculo de Hidrologia
Trabajo Calculo de Hidrologia
90.00
80.00
CURVA HIPSOMETRICA Y FRECUENCIA DE ALTITU
0.00 2.00 4.00 6.00 8.00 10.00
100.00
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0 1000 2000 3000 40
K=0.28
K=
517.12/√6078.
52
2 RECTANGULO EQUIVALENTE
DATOS
K= 1.86 L=
A (KM2)= 6078.52 I=
0 26.155 0.000000
733.72 26.155 28.052933
456.83 26.155 17.466365
545.82 26.155 20.868794
511.52 26.155 19.557374
421.04 26.155 16.097976
618.89 26.155 23.662541
811.76 26.155 31.036702
740.18 26.155 28.299923
650.69 26.155 24.878377
480.58 26.155 18.374419
78.73 26.155 3.010150
28.76 26.155 1.099605
sumatoria 6078.52 232.40515890897
2 DENSIDAD DE DRENAJE
DATOS
LONGITUD DE TODOS LOS CAUCES DE AGUA KM (L)= 3945.33
AREA TOTAL DE CUENCA KM2 (A)= 6078.52
(Dd)=(3945.33/
6078.52) Dd= 0.649
B
A D 2
P=(60𝑥709.7+65𝑥965.8+75𝑥1
2
SUMATORIA AREA
TOTAL 3104.2
P=
% TOTAL QUE QUEDA
SOBRE LA ALTITUD
% TOTAL
(5)=(((2))/ (6)=(((4))/
6078.52)100 6078.52)100
0.00 100.00
12.07 87.93
7.52 80.41
8.98 71.43
8.42 63.02
6.93 56.09
10.18 45.91
13.35 32.56
12.18 20.38
10.70 9.67
7.91 1.77
1.30 0.47
0.47 0.00
DATOS
PERIMETRO DE CUENCA KM 517.12
A (KM2)= 6078.52
1.86
232.405 KM
26.155 KM
km/km2
P= (65+75)/2 P= 70 MM
metodo de thinssen=
P= 67.21 MM
P=(60𝑥709.7+65𝑥965.8+75𝑥1169.6+60𝑥259.1)/(709.7+965.8+1169.6+259.1)
metodo de Isoyetas=
metodo de isoyetas=
65
60
75
66.98 MM