Charnawati Khola Hydroelectric Project
Appearance
Charnawati Khola Hydroelectric Project | |
---|---|
Country | Nepal |
Location | Dolakha District |
Coordinates | 27°39′13″N 86°00′59″E / 27.6535°N 86.0164°E |
Purpose | Power |
Status | Operational |
Opening date | 24th Jestha ,2070 BS |
Owner(s) | Nepal Hydro Developer Limited |
Dam and spillways | |
Type of dam | Gravity |
Impounds | Mati River |
Commission date | 2070BS |
Type | Run-of-the-river |
Hydraulic head | 199 m (653 ft) (Gross) |
Turbines | 2 Pelton-type |
Installed capacity | 3.52 MW |
Charnawati Khola Hydroelectric Project is a run-of-the-river hydroelectric power station with an installed capacity of 3.52 MW. This power station is located in Dolakha District, Nepal. The flow is 2.19 m3/s and gross head is 199 m.[1] The annual generation of energy is 20.383 GWh.[2][3] The electricity is connected to Makaibari (Gaighat) substation of NEA via 11 km long 33kV transmission line.[4]
The plant is operated by Nepal Hydro Developer Limited, a public company developing various hydropower projects in Nepal.[5]
References
[edit]- ^ Ltd, Hydro Solutions Pvt. "Hydro Solutions Pvt. Ltd". Retrieved 2020-07-30.
- ^ "Charanawoti Hydroelectrical Project 3.52 MW". Retrieved 2020-07-30.
- ^ "Charnawati Khola Hydroelectric Project". Retrieved 2020-07-30.
- ^ Charnawati_press_May19_2013.pdf (PDF), archived from the original (PDF) on 2020-02-15, retrieved 2020-07-30
- ^ "Operating Projects :: Hydro (Above 1MW)".