0% found this document useful (0 votes)
254 views30 pages

Project Management: A Short Introduction and History

This document provides an introduction to project management. It defines key project management terms like critical path, slack time, crashing, dependencies and gives a brief history of how project management has developed over time. Project management emerged as a formal discipline in 1917 and the two main techniques, PERT and CPM, were introduced in the late 1950s to help the US military and industry better manage complex projects.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
254 views30 pages

Project Management: A Short Introduction and History

This document provides an introduction to project management. It defines key project management terms like critical path, slack time, crashing, dependencies and gives a brief history of how project management has developed over time. Project management emerged as a formal discipline in 1917 and the two main techniques, PERT and CPM, were introduced in the late 1950s to help the US military and industry better manage complex projects.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 30

URBS 609 PERT, Unit 1

Project Management
A Short Introduction and History

About This Training Module


by Microsoft Corporation. It has been packaged with PowerPoint Viewer, a standalone Microsoft product that allows a user to view this module without use of PowerPoint.

This training module was crafted using PowerPoint

Left mouse-click or enter to go to next slide Right mouse-click or backspace to go to previous slide ESC to exit this module
This Unit of Instruction was crafted by Robert Hugg For Minnesota State University, Mankato Urban and Regional Studies Institute - 2004

Urban and Regional Studies Institute

Training Module Preview


This module will provide:
A basic history of Project Management Introduction to key terms Introduction to key concepts Introduction to traditional methodologies Introduction to logical task sequence

This module is constructed as the first


block in a building block approach
Urban and Regional Studies Institute 3

What Is Project Management?


Management of resources & constraints to meet
a goal in as efficient a manner as possible
Resources: Time, money, people, equipment Constraints: preceding task completion Science: based on statistical means & norms Art: based on intuition into human behavior Both: balancing the known and unknown to achieve a more predictable result

A science or an art? Both

Urban and Regional Studies Institute

The Unbroken Thread of Time


Project Management (PM) is not new
Used in some form for centuries Pyramids, sphinx, coliseum intricate plans Active management of resources to meet a goal Value: listing and tracking complex tasks Value: Provides a focus for project communication

Based on a quest for efficiency


Arranging tasks and resources for most efficient and productive result
Urban and Regional Studies Institute

A Philosophy, not a Technique


PM is a management philosophy
Often mistaken as a technique
Efficient management yields effective results

Many techniques, many tools, one goal


Urban and Regional Studies Institute

PM contains many techniques flexible Adaptable techniques that are industry specific Techniques work in some industries and not others PM techniques evolve within the philosophy

Project Management Definitions


There are several key PM terms
Critical Path: The longest time path through the task network. The series of tasks (or even a single task) that dictates the calculated finish date of the project (That is, when the last task in the critical path is completed, the project is completed) The "longest" path (in terms of time) to the completion of a project. If shortened, it would shorten the time it takes to complete the project. Activities off the critical path would not affect completion time even if they were done more quickly.
Slack Time: The amount of time a task can be delayed before the project finish date is delayed. Total slack can be positive or negative. If total slack is a positive it indicates the amount of time that the task can be delayed without delaying the project finish date. If negative, it indicates the amount of time that must be saved so that the project finish date is not delayed. Total Slack = Latest Start Earliest Start. By default and by definition, a task with 0 slack is considered a critical task. If a critical task is delayed, the project finish date is also delayed. (Also known as float time )

Urban and Regional Studies Institute

Project Management Definitions


More key PM terms:
Crashing: Shifting resources to reduce slack time so the critical path is as short as possible. Always raises project costs and is typically disruptive a project should be crashed with caution. Dummy activity: An imaginary activity with no duration, used to show either an indirect relationship between 2 tasks or to clarify the identities of the tasks . In CPM, each activity must be uniquely defined by its beginning and ending point. When two activities begin and end at the same time, a dummy activity (an activity which begins and ends at the same time) is inserted into the model to distinguish the two activities.

Urban and Regional Studies Institute

Project Management Definitions


Even more key PM terms:
Gantt Chart: A bar chart. While visually appealing on a task/duration basis, it is limited because it does not show task or resource relationships well. Strength: easy to maintain and read. Network Diagram: A wire diagram, Also known as a PERT network diagram. A diagram that shows tasks and their relationships. Limited because it shows only task relationships. Strength: easy to read task relationships.
Urban and Regional Studies Institute 9

Project Management Definitions


Yet more key PM terms:
types of dependencies:

Dependencies: Links between project tasks. There are 3


Causal, where 1 task must be completed before another can begin (have to bake bread before you can make a sandwich) critical path schedules are based only on causal dependencies Resource, where a task is limited by availability of resources (more bread can be baked by 2 bakers, but only 1 is available) Discretionary, optional task sequence preferences that, though not required, may reflect organizational preferences

Milestone: A significant task which represents a key accomplishment within the project. Typically requires special attention and control.
Urban and Regional Studies Institute 10

Project Management Definitions


Yet more key PM terms:
WBS: a work breakdown structure (WBS) is a detailed, hierarchical (from general to specific) tree structure of deliverables and tasks that need to be performed to complete a project. The purpose of a WBS is to identify the actual tasks to be done in a project. WBS serves as the basis for much of project planning. Work breakdown structure is, perhaps, the most common project management tool, it was created by the US military in the 1960s as an extension to PERT.
Urban and Regional Studies Institute 11

Project Management Definitions


Yet more key PM terms:
Duration: The time it takes for an activity to be completed, given the planned amount of material, labor and equipment. Effort: The amount (not duration) of work required to complete a task. Duration may decrease by adding resources but the effort required will remain the same. Scope: A specific definition of what the project does and does not entail. Critical to managing expectations of customers and workers alike.
Urban and Regional Studies Institute 12

Project Management Definitions


Final key PM terms:
Constraints: Restrictions set on the start or finish date of a task. You can specify that a task must start on or finish no later than a particular date. Constraints can be flexible (not tied to a specific date) or inflexible (tied to a specific date)

Flexible constraints such as As Soon As Possible (ASAP) and As Late As Possible

There are many more PM Terms, but these are the


basics it is important to know these concepts

(ALAP) do not have specific dates associated with them. Setting these constraints allows you to start tasks as early as possible or as late as possible with the task ending before the project finish, given other constraints and task dependencies in the schedule. Inflexible constraints such as Must Start On (MSO) and Must Finish On (MFO) require an associated date, which controls the start or finish date of the task. These constraints are useful when you need to make your schedule take into account external factors, such as the availability of equipment or resources, deadlines, contract milestones, and start and finish dates.

Urban and Regional Studies Institute

13

Project Management Assumptions


PM makes several key assumptions
All tasks have distinct begin and end points All estimates can be mathematically derived Tasks must be able to be arranged in a defined sequence that produces a pre-defined result Resources may be shifted to meet need Cost and time share a direct relationship (Cost of each activity is evenly spread over time) Time, of itself, has no value

These assumptions make PM controversial


Urban and Regional Studies Institute

14

THE PM Concept Assumption


A Critical Path Exists
The Key Concept used by CPM/PERT is that a small set
of activities, which make up the longest path through the activity network control the entire project. If these "critical" activities could be identified and assigned to responsible persons, management resources could be optimally used by concentrating on the few activities which determine the fate of the entire project. By contrast, non-critical activities can be re-planned, rescheduled and resources for them can be reallocated flexibly, without affecting the whole project. (Wiest, 1974)
Urban and Regional Studies Institute

15

The Emergence of Standardized PM


Organized as a formal Discipline in 1917
Henry Gantt introduced standardized PM tools Gantt Chart visual tracking of tasks and resources Depiction of relationships between tasks Depiction of constraints between tasks First Widespread acceptance of a single technique Created out of need and frustration as industrialization became ever more complex

Little change to PM for another 40 years


Urban and Regional Studies Institute

16

The Birth of PM as We Know It


Two main (complementary) techniques within PM
PERT (Program Evaluation and Review Technique) introduced by US military in 1958

US Navy needed tools to control costs and schedules for Polaris


Submarine construction

CPM (Critical Path Method) introduced by US industry in 1958 (DuPont Corporation and Remington-Rand)

Industry needed to control costs and schedules in manufacturing Considers only completion of a preceding required task

Common weakness to both: ignores most dependencies

Both rely on a logical sequence of tasks


Urban and Regional Studies Institute

Organized visually (Charts), tabular or simple lists

17

An Example of a Logical Sequence


Making a simple list of tasks

Planting trees with

flowers and edging around them tasks required to complete this project:
1. 2. 3. 4. 5. 6. 7. 8. Mark utilities Dig Holes Buy trees Buy flowers Plant trees Plant flowers Buy edging Install edging

This list does not reflect


time or money This list does not reflect task relationships This list is a simple sequence of logical events This list does not provide an easy project snapshot Hard to see conflicts

Urban and Regional Studies Institute

18

An Example of a Logical Sequence Visual - Using a PERT Chart (Network Diagram)


Planting trees with flowers and edging around them Visual task relationships are clear good snapshot

7
Buy Edging

3
Buy Trees

1
Start Mark Utilities

2
Dig Holes

5
Plant Trees

6
Plant Flowers

8
Install Edging Finish

4
Buy Flowers

Created using RF Flow or Visio

Urban and Regional Studies Institute

19

An Example of a Logical Sequence Tabular including time and cost data


Task Name Normal Time (Days) Crashed Time (Days) Normal Cost ($) Crashed Cost ($)

Mark Utilities
Dig Holes Buy Trees Buy Flowers Plant Trees Plant Flowers Buy Edging Install Edging TOTALS

3
2 .5 .5 2 1 .5 1

3
1 .5 .5 1 .5 .5 .5

0
100 50 50 100 50 25 25

0
200 50 50 200 100 25 50

10

400

675

NOTE: Shaded areas are concurrent tasks that are completed along the timeline- they contribute to overall cost but not overall duration Urban and Regional Studies Institute 20

PERT and CPM The Basics


PERT
Weighs and estimates task and project timing based on probabilistic norms and averages Optimistic, expected, pessimistic input estimates Derives probable completion dates based on a
formula (does not consider constraints)

The derived dates are estimates (educated guess) The analysis yields a best-case date, worst-case
date, and due (derived expected) date
Urban and Regional Studies Institute

(Optimistic x1 + expected x4 + pessimistic x1) / 6

21

PERT and CPM The Basics


PERT (continued) Manipulating these estimates provides:
Likely (estimated) completion dates Probability of meeting estimated dates Best case date Expected (due) date Worst case date

ALL PERT dates are estimates (ALWAYS) Preferred choice in Social & Behavioral Sciences
Urban and Regional Studies Institute 22

PERT and CPM The Basics


CPM
Unlike PERT, analyzes only the longest likely chain of activities The earliest time a project can be completed
when using the longest possible task durations

Deterministic, not probabilistic Events will be determined by preceding events, not


probability

Derives a normal completion time


Urban and Regional Studies Institute 23

PERT and CPM The Basics


CPM (Continued) CPM assumes projects may be crashed
Completing a task or project in a shorter amount of time by using extra resources May be crashed for time but does not directly consider any impact other than cost/time

Preferred choice in industry and construction

Impact on shared resources (with other projects) Impact on other projects (resources, timing) Impact on quality or reliability

tasks and outcomes are more finite and tangible


Urban and Regional Studies Institute

24

PERT and CPM The Basics


PERT and CPM can be used Together
Provides benefits of each Time estimates a range (PERT) Time estimates likely (CPM) Cost estimates (CPM) Time and cost if crashed (CPM) Probability of completion on time (PERT) Used together: valuable management tools PERT and CPM have remained unchanged since 1958

Urban and Regional Studies Institute

25

PERT and CPM The Basics


Valuable planning tools but:
Only consider logical (causal) dependencies Completion of a preceding required task Does not consider resource or discretionary dependencies Availability of a worker, money, or machines Task sequence that best fits the bigger picture

Relies on clearly defined tasks and goals Provides estimates, not guarantees
Urban and Regional Studies Institute 26

PM Today Necessary?
Frustration with cost & schedule overruns Frustration with reliability of production estimates Management challenges exist today:
Only 44% of projects are completed on time On average, projects are 189% over-budget 70% of completed projects do not perform as expected 30% of projects are canceled before completion On average, projects are 222% longer than expected

PM has been shown to improve this performance


Urban and Regional Studies Institute

These statistics were compiled by an independent monitoring group, The Standish Group, and represent the US national average for 1998

27

PM Overview
Valuable tools for planning and tracking
A good way to explore what if before a project ever begins How much it could cost - money What it could entail tasks How long it could take - time Probabilities of success - risks How much resource needed people & equipment

A good way to get and stay organized Provides estimates, not guarantees
Urban and Regional Studies Institute

28

Resources Used in This Unit


Dr. Anthony Filipovitch Goldratt, Eli, Dr., The Goal: A Render, Barry and Stair Jr., Ralph
Process of Ongoing Improvement, Great Barrington: New River Press, 1996 MS Project, by Microsoft Corporation PM Body of Knowledge (PMBOK), Philadelphia: PMI, 2000 Project Management Institute (PMI) Resource Center
Project Management Institute Website

M. - Quantitative Analysis for Management, Massachusetts: Allyn & Bacon Inc., 1982 US National Performance Survey, The Standish Group, 1998 Verma, Vijay K., Managing the Project Team: The Human Aspects of Project Management, Philadelphia: PMI, 1997 Wiest, Jerome D., and Levy, Ferdinand K., A Management Guide to PERT/CPM, New Delhi: Prentice-Hall of India Private Limited, 1974

Urban and Regional Studies Institute

29

You have completed


URBS 609 PERT Unit 1 Please proceed to URBS 609 PERT Unit 2
This Unit of Instruction was crafted by Robert Hugg For Minnesota State University, Mankato Urban and Regional Studies Institute - 2004

Urban and Regional Studies Institute

30

You might also like