Network Analysis OR MBA PPT 2
Network Analysis OR MBA PPT 2
Module 4
network
A network is a graphical plan consisting of a certain configuration of arrows and nodes for showing the logical sequence of various activities to be performed to achieve project objectives
event
Events in the network represents the project milestones such as Start or completion of an activity or activities and occur at a particular instant of time at which some specific part of the project has been or is to be achieved Events are commonly represented by circles (nodes) in the network diagram
activity
Activities in the network diagram represent project operations or tasks to be conducted Note: except dummy activity each activity consumes time and resources and incur cost An arrow is used to represent the direction of the activity activities are identified by the numbers of their starting event and ending event
i
Starting event
Activity
j
Completion event Activity
Activity
node
node
Classification of activity
Predecessor activity-an activity which must be completed before one or more other activities start is known as predecessor activity Successor activity-an activity which started immediately after one or more of other activities are completed is known as successor activity Dummy activity-an activity which does not consume either an resources and/or time is known as dummy activity
Rules contd.
All activities emerging from event should not be preceded by any other activities Event carrying the highest number denotes the completion of the project A network should have only one initial event and only one terminal event The general rule for numbering is that the head event should always be numbered larger than that at its tail .i.e. i<j
Rules contd.
An event number should not be repeated or duplicated Two activities should be identified by the same completion event An event can not occur until all the incoming activities into it have been completed An activity can not start unless all the preceding activities on which it depends have been completed Dummy activity also should follow all the rules
G
H I
D
E,F,G H
Soln.
3 B 1 A 2 D 5 C 4 F G
E
6 H 7 I 8
ACTIVITY
DURATION(DAYS) 2 7 8 3 6 10 4 6 2 5
1-2 1-3 1-4 2-5 3-5 3-6 3-7 4-6 5-7 6-8
7-8
Soln.
E=2 L=11
E=13 L=14
From the network, Critical path is 1 3 6 8 And duration of critical path is 7+10+5=22 days
2 1 8
E=8 4 L=11
2 7
E=7 L=7
E=0 L=0
E=15 L=16
7 10
E=22 L=22
5 6
E=17 L=17
Activity 1-2 2-3 2-4 3-6 3-5 4-6 5-7 6-7 7-8
to 4 5 4 15 10 8 4 1 6
tm 6 7 8 20 18 9 8 2 7
tp 8 15 12 25 26 16 12 3 8
Soln.
8
1
E=0 L=0
E=14 L=14
18 20 6
E=32 L=32
5 8 2
E=34 L=38
2
E=6 L=6
7
E=40 L=40
8
E=47 L=47
8
4
E=14 L=28
10
From the network, Critical path is 1 2 3 5 7
Soln. contd.
te = to+ tm+ tp 6 to= optimistic time te= most likely time tp= pessimistic time
2
Probability that the project will be Completed in x days P(DX)= P Z GT-AT Where, Z = value under normal curve = standard deviation GT = Given Time AT = Actual Time