Turbine Erection
Turbine Erection
Turbine Erection
HP Turbine
IP Turbine
26 May 2012
PMI Revision 00
Brg
26 May 2012
Salient Features Of Turbine Erection The fore most activity before taking up the work is the safe working conditions. Thus we should first assemble temporary railing and covers before the start of the job Remove construction material & sweep the foundation well. A proper foundation is of utmost importance for proper operation of the machine. A hammer test is to be carried to detect any flaw / void in the concrete layer. An ultrasonic testing of the TG deck should also be carried out if possible. No looseness below the base plates is acceptable
26 May 2012 PMI Revision 00 4
26 May 2012
PMI Revision 00
26 May 2012
PMI Revision 00
26 May 2012
PMI Revision 00
26 May 2012
PMI Revision 00
BASE PLATES & BEARING PEDESTALS : LAYING The base plates are designed to transfer uniformly all forces & vibrations caused by the operation of the machine.The pedestal are aligned as the deflection curve of the rotor. The base plates are leveled with help leveling screws provided below the base plate
26 May 2012
PMI Revision 00
10
26 May 2012
PMI Revision 00
11
26 May 2012
PMI Revision 00
12
26 May 2012
PMI Revision 00
13
26 May 2012
PMI Revision 00
14
26 May 2012
PMI Revision 00
15
26 May 2012
PMI Revision 00
16
26 May 2012
PMI Revision 00
17
26 May 2012
PMI Revision 00
18
26 May 2012
PMI Revision 00
19
26 May 2012
PMI Revision 00
20
26 May 2012
PMI Revision 00
21
26 May 2012
PMI Revision 00
22
26 May 2012
PMI Revision 00
23
26 May 2012
PMI Revision 00
24
26 May 2012
PMI Revision 00
25
26 May 2012
PMI Revision 00
26
26 May 2012
PMI Revision 00
28
26 May 2012
PMI Revision 00
29
26 May 2012
PMI Revision 00
30
26 May 2012
PMI Revision 00
31
26 May 2012
PMI Revision 00
32
26 May 2012
PMI Revision 00
33
26 May 2012
PMI Revision 00
34
26 May 2012
PMI Revision 00
35
26 May 2012
PMI Revision 00
36
26 May 2012
PMI Revision 00
37
26 May 2012
PMI Revision 00
38
26 May 2012
PMI Revision 00
39
26 May 2012
PMI Revision 00
40
26 May 2012
PMI Revision 00
41
26 May 2012
PMI Revision 00
42
BEARING PEDESTALS The Function of the Bearing Pedestal Is To: -Support the Rotors -Connect HP & IP to Form One Unit -Support HP & IP Turbine Sections -Center the Turbine Sections THRUST BEARING takes care of the uncompensated residual thrust FRONT BEARING PEDESTAL houses the main oil pump for lube oil & control oil. The over speed trip device is also installed in this pedestal AXIAL MOVEMENT : those pedestals which are not fixed point are designed to take care of thermal expansion. The movement is based in the length of the turbine section and the casing temperatures Setting of spacer bolt clearance Checking of radial & axial clearance on the right & left hand sides
26 May 2012
PMI Revision 00
43
The Erection any equipment is a complete & systematic process which is well conceived before start of the job. It involves detailed planning about the content and the scope of work that needs to done. The complete technical specification of the equipment, its Layout, the foundations, and the Terminal points have to be defined before the start of the work. It is well said, that a work well planned is half done. Thus while award of the work the complete technical specifications are frozen in detail during pre award discussions with the Engineering and the Contract services.
26 May 2012
PMI Revision 00
44
-The complete erection of a TG is a long drawn process requiring more that 30 months of work. -Thus the sequence of supplies and their dates of dispatches are decided before hand. -Similarly the dates of readiness of the Foundations is also decided before hand. -The Terminal points are also decided before the Final award of the contract i.e. NTPC scope(Customer Scope) which generally are free construction power supply, water supply, Civil foundations, EOT Crane (optional) with operators, Compressed air, Area lighting, accommodation land, storage area, DM water etc. -The rest of the work is in the scope of the equipment supplier. - This includes Supply, Storage, Erection, Testing & Commissioning and Trial operation of the equipment.
26 May 2012 PMI Revision 00 45
Pert Networks The contractor is required to submit a PERT network indication the major mile stone dates The three types viz. L1, L2 & L3 networks are submitted by the contractor which is reviewed & finalized after incorporating the comments of the owner. L3 is the complete detailed network which is normally used at site for each commitment Similarly the supplies are also decided as per the milestone dates and any slippage from the committed date is subject to LD to be levied by the owner. This is levied @ 1/2 % per weeks delay subject a maximum ceiling of 5 % 26 May 2012 PMI Revision 00 46
The fronts are handed over to the contractor after due checking of the soundness & dimensional check of the elevation & pocket, insert sizes and their location after a joint protocol It is essential to provide weather proof TG hall along with crane girder which includes side wall cladding, railway siding, approach ladders / staircase, adjoining floors etc
26 May 2012
PMI Revision 00
47
CONSTRUCTION OF TG DECK The TG deck is supported on steel / RCC columns. A vibration isolation system is provided on the column to isolate the deck vibrations from the columns After the layout of steel inserts on the form work/ shuttering, the TG deck is constructed by a process of non stop casting in order to provide monolithic structure. The cement setting is delayed by adding certain additives to the concrete mixture. The curing is carried out for a period of 28 days after which it is released for erection of the equipments
26 May 2012 PMI Revision 00 48
26 May 2012
PMI Revision 00
49
26 May 2012
PMI Revision 00
50
26 May 2012
PMI Revision 00
51
26 May 2012
PMI Revision 00
52
26 May 2012
PMI Revision 00
53
26 May 2012
PMI Revision 00
54
26 May 2012
PMI Revision 00
55
26 May 2012
PMI Revision 00
56
26 May 2012
PMI Revision 00
57
26 May 2012
PMI Revision 00
58
26 May 2012
PMI Revision 00
59
26 May 2012
PMI Revision 00
60
26 May 2012
PMI Revision 00
61
26 May 2012
PMI Revision 00
62
26 May 2012
PMI Revision 00
63
26 May 2012
PMI Revision 00
64
26 May 2012
PMI Revision 00
65
26 May 2012
PMI Revision 00
66
26 May 2012
PMI Revision 00
67
26 May 2012
PMI Revision 00
68
26 May 2012
PMI Revision 00
69
26 May 2012
PMI Revision 00
70
26 May 2012
PMI Revision 00
71
26 May 2012
PMI Revision 00
72
26 May 2012
PMI Revision 00
73
26 May 2012
PMI Revision 00
74
26 May 2012
PMI Revision 00
75
26 May 2012
PMI Revision 00
76
26 May 2012
PMI Revision 00
77
26 May 2012
PMI Revision 00
78
26 May 2012
PMI Revision 00
79
26 May 2012
PMI Revision 00
80
26 May 2012
PMI Revision 00
81
26 May 2012
PMI Revision 00
82
26 May 2012
PMI Revision 00
83
26 May 2012
PMI Revision 00
84
26 May 2012
PMI Revision 00
85
26 May 2012
PMI Revision 00
86
26 May 2012
PMI Revision 00
87
26 May 2012
PMI Revision 00
88
26 May 2012
PMI Revision 00
89
26 May 2012
PMI Revision 00
90
26 May 2012
PMI Revision 00
91
26 May 2012
PMI Revision 00
92
26 May 2012
PMI Revision 00
93
26 May 2012
PMI Revision 00
94
26 May 2012
PMI Revision 00
95
26 May 2012
PMI Revision 00
96
26 May 2012
PMI Revision 00
97
26 May 2012
PMI Revision 00
98
26 May 2012
PMI Revision 00
99
26 May 2012
PMI Revision 00
100
26 May 2012
PMI Revision 00
101
26 May 2012
PMI Revision 00
102
26 May 2012
PMI Revision 00
103
26 May 2012
PMI Revision 00
104
26 May 2012
PMI Revision 00
105
26 May 2012
PMI Revision 00
106
26 May 2012
PMI Revision 00
107
26 May 2012
PMI Revision 00
108
26 May 2012
PMI Revision 00
109
26 May 2012
PMI Revision 00
110
26 May 2012
PMI Revision 00
111
26 May 2012
PMI Revision 00
112
26 May 2012
PMI Revision 00
113
26 May 2012
PMI Revision 00
114
26 May 2012
PMI Revision 00
115
26 May 2012
PMI Revision 00
116
26 May 2012
PMI Revision 00
117
26 May 2012
PMI Revision 00
118
26 May 2012
PMI Revision 00
119
26 May 2012
PMI Revision 00
120
26 May 2012
PMI Revision 00
121
26 May 2012
PMI Revision 00
122
26 May 2012
PMI Revision 00
123
26 May 2012
PMI Revision 00
124
26 May 2012
PMI Revision 00
125
26 May 2012
PMI Revision 00
126
26 May 2012
PMI Revision 00
127
26 May 2012
PMI Revision 00
128
26 May 2012
PMI Revision 00
129
26 May 2012
PMI Revision 00
130
THANK YOU
26 May 2012
PMI Revision 00
131