Chapter 5
Chapter 5
Investment Criteria
and
Cash flow projection
• The key steps involved in
determining whether a project is
worthwhile or not are
• Estimate the cost and benefits of the
project
• assess the riskiness of the project
• Calculate the cost of capital
• Compute the criterion of merit and
judge whether the project is good or bad
Methods of Financial Evaluation
Year 1 2 3 4
Cash 1500 3000 2000 2500
flow
NPV = 1053.00
• Decision: Accept the project since NPV
>0
Cont….
• Advantages of NPV
Considers time value of money
Gives a decision criteria
Recognizes uncertainty of cash flow by
discounting
Uses all project cash flows
• Disadvantages of NPV
Gives absolute values which cannot be used
to compare project of different sizes
There is difficulty in selecting the discount
rate to use
It does not show the exact profitability of the
project
Cont…..
• Where; R = IRR
• It should be noted that IRR is computed using
a trial and error method.
• However, financial calculators are
programmed to compute IRR
Cont….
38.19 0
IRR 15 (18 15) 16.08%
38.19 ( 68.23
• Disadvantages of IRR
Some project have multiple IRRs if their NPV profile
crosses the x-axis more than once (project cash flow signs
change several time)
Assumes re-investment of cash flows occurs at project’s
IRR which could be exorbitantly high
Doesn’t provide a decision criteria
Not conclusive for mutually exclusive projects
Cont…..
Year 1 2 3 4
Cash 300 400 700 900
Flow
• If the required rate of return is 9% and the
project initial cost is 1500 Br, calculate the PI
of the project and advice if the project is
acceptable
Solution
Year Cash PVIF PV
Flow (9%)
1 300 0.9174 275.52
2 400 0.8417 336.68
3 700 0.7722 540.54
4 900 0.7084 637.46
Total PV = 1790
PVofC .F 1790
PI 1.193
int ial cos t 1500
• Decision: The project is acceptable since PI >
0
Cont….
• Advantages of PI
Recognized time value of money
Compares projects of different sizes
Gives a decision criteria
• Disadvantages of PI
Does not indicate the risk
Cont….
d) Discounted payback period
• This is the number of year taken to recover the
original (initial) investment from annual cash
flows.
• The lower the payback period the better the
project is
• Illustration:
• Assume a company wants to invest in two
mutually exclusive projects of 1000 Br each
generating the following cash flows.
• If the required rate of return is 10%. Which of the
projects should the company invest in?
Cont….
Year 1 2 3 4 5 6
Year 1 2 3
Net 20,00 10,00 30,00
Profit 0 0 0
Cont….
• Advantages of ARR
Easy to compute and use
Computed from readily available accounting information
Cont….
• Disadvantages of ARR
Ignores time value of money
Ignores uncertainty of cash flows and
there is no consideration of risk in
calculation
Uses accounting profits rather than cash
flows
Doesn’t give a decision criteria
Not consistent with investor’s wealth
maximization
PROJECT
CASH FLOWS
Project cash flows
• The estimated of cash flows are a key element in
investment evaluation.
• So far we assumed that cash flows were given
because we wanted to focus our discussion on
investment criteria.
• Estimating cash flows-the investment outlays and
the cash inflows after the project is commissioned-is
the most important, but also the most difficult step
in capital budgeting.
• Forecast error can be quite large, particularly in
gigantic, complex project. For example, when
several oil majors decided to construct the
Cont….
• It is estimated as follows:
• Cash flow to all investor =PBIT(1-Tax rate)
+ Depreciation & non cash
charges
- Capital Expenditure
- Change in working capital
• The cash flow of a project from the point of view of
equity shareholders is the cash flow available to
equity shareholders after paying taxes, meeting
investment needs, and fulfilling debt-related
commitments.
• It is estimated as follows:
Cont….
• Illustration 1.
• ABC enterprises is considering a capital project about
which the following information is available:
The investment outlay on the project will be 100
million Birr. This consists of 80 million on plant and
machinery and 20 million on net working capital. The
entire outlay will be incurred at the beginning of the
project.
The project will be financed with 45 million of equity
capital, 5 million of preference capital, and
Cont…..
• Required:
given the above
detail, prepare
the project
cash flows
Solution
Years 0 1 2 3 4 5
1. FA (80.00) - - - - -
2. NWC (20.00) - - - - -
3. Revenues 120 120 120 120 120
4. Cost (other than depr. & 80 80 80 80 80
int)
• Project cash flow (in millions20of Birr0
5. Deprec. 15 11.25 8.44 6.33
6. PBT 20 25 28.75 31.56 33.67
7. Tax (30%) 6 7.5 8.63 9.47 10.10
8. PAT 14 17.5 20.12 22.09 23.57
9. Net salvage value of FA - - - - 30
10. Recovery of NWC - - - - 20
11. Initial outlay (100.00
)
12. Operating Cash 34 32.5 31.37 30.53 29.90
inflow(8+5)
Illustration 2
•Required: based on
the above
information
prepare the cash
flow for the project
Cash flow for the K-cin project
Year 0 1 2 3 4 5
1. Capital Requirement (100) - - - - -
2. Level of WC (ending) (20) 30 40 30 20 0
3. Revenues 100 150 200 150 100
4. RMC 30 45 60 45 30
5. Labour cost 20 30 40 30 20
6. Oper. & Maint. cost 5 5 5 5 5
7. Loss of Contribution 15 15 15 15 15
8. Depreciation 25 18.8 14.1 10.5 7.9
9. Bad debt loss - - - - 5
10. PBT 5 36.2 65.9 44.5 17.1
11. Tax 2 14.5 26.4 17.8 6.8
12. PAT 3 21.7 39.5 26.7 10.3
Cont….
Year 0 1 2 3 4 5
12. Profit after tax (BBF) - 3 21. 39. 26. 10.3
7 5 7
13. Net salvage value of - - - - 20
capital Requirement
14. Recovery of WC - - - - 20
15. Initial Inv ‘t (100 - - - - -
)
16. Operating Cash inflow - 2 57. 53. 37. 23.2
(12+8+9) 8 9 6 2
17. Increase in WC 20 1 10 (10 (10 -
0 ) )
18.
TheTerminal
loss ofcash in flow
contribution (120
(item 7) 1 47.opportunity
is an 63. 47. 63.2
(14+15 - 16+17 ) 8 9 6 2
cost.
OH expenses allocated to the project have been
ignored as they do not represent incremental OH
expense for the firm as a whole.
Cont…