CPM Pert
CPM Pert
IT Project Management
Module II
Applications
© Wiley 2010
Project Life Cycle AIITL
© Wiley 2010
Network Planning Techniques AIITL
© Wiley 2010
Both PERT and CPM AIITL
© Wiley 2010
Network Diagrams AIITL
• Activity-on-Node (AON):
– Uses nodes to represent the activity
– Uses arrows to represent precedence relationships
Step 1-Define the Project: Cables By Us is bringing a new
product on line to be manufactured in their current facility in existing
AIITL
space. The owners have identified 11 activities and their
precedence relationships. Develop an AON for the project.
Immediate Duration
Activity Description
Predecessor (weeks)
A Develop product specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E&F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H&I 4
K Transition to manufacturing J 2
© Wiley 2010
Step 2- Diagram the Network for AIITL
Cables By Us
© Wiley 2010
Step 3 (a)- Add Deterministic Time AIITL
© Wiley 2010
Step 3 (a) (Con’t): Calculate the
AIITL
© Wiley 2010
ES, EF Network AIITL
© Wiley 2010
LS, LF Network AIITL
© Wiley 2010
Calculating Slack AIITL
© Wiley 2010
Estimated Path Durations throughAIITL
the Network
© Wiley 2010
Gantt Chart Showing Each Activity AIITL
© Wiley 2010
Adding LS and LF to Network AIITL
© Wiley 2010
Gantt Chart Showing the Latest Possible AIITL
© Wiley 2010
Estimating the Probability ofAIITL
Completion Dates
• Using probabilistic time estimates offers the advantage of predicting
the probability of project completion dates
• We have already calculated the expected time for each activity by
making three time estimates
• Now we need to calculate the variance for each activity
• The variance of the beta probability distribution is:
2
2 p o
σ
6
– where p=pessimistic activity time estimate
o=optimistic activity time estimate
Project Activity Variance AIITL
the Network
Path Activities on Path Variance
Number Path (weeks)
1 A,B,D,E,G,H,J, 4.82
k
2 A,B,D,E,G,I,J,K 4.96
3 A,C,F,G,H,J,K 2.24
4 A,C,F,G,I,J,K 2.38
Reducing Project Completion AIITL
Time
© Wiley 2010
Reducing Project Completion AIITL
Time – con’t
© Wiley 2010
Reducing the Time of a Project (crashing)
AIITL
© Wiley 2010
Crashed Network Diagram AIITL
The Critical Chain ApproachAIITL
• The Critical Chain Approach focuses on project due dates rather than on
individual activities and the following realities:
– Project time estimates are uncertain so we add safety time
– Multi-levels of organization may add additional time to be “safe”
– Individual activity buffers may be wasted on lower-priority activities
– A better approach is to place the project safety buffer at the end
© Wiley 2010
Project Management OM AIITL
© Wiley 2010
Highlights AIITL
© Wiley 2010
HAPPY LEARNING!!
38