Chapter 3 Ipm
Chapter 3 Ipm
Chapter 3
Project Time Management
Content
s
1. Time Management
1. Importance of Project Schedules
2. Schedules and Activities
3.Sequencing and
Scheduling Activity
3.2. Project Network Diagrams
2
Importance of Project Schedules
Often cite delivering projects on time as one of their
biggest challenges.
3
Project Time Management Processes
Activity definition: Identifying the specific activities that the
project team members and stakeholders must perform to
produce the project deliverables.
Activity sequencing: Identifying and documenting the
relationships between project activities.
Activity resource estimating: Estimating how many resources
a project team should use to perform project activities.
Activity duration estimating: Estimating the number of work
periods that are needed to complete individual activities.
Schedule development: Analyzing activity sequences, activity
resource estimates, and activity duration estimates to create the
project schedule.
Schedule control: Controlling and managing changes to the
project schedule.
4
Activity Definition
An activity or task is an element of work normally found on
the WBS that has an expected duration, a cost, and resource
requirements.
Project schedules grow out of the basic documents that
initiate a project.
The project charter includes start and end dates and
budget information.
The scope statement and WBS help define what will
be done.
Activity definition involves developing a more detailed WBS
and supporting explanations to understand all the work to be
done, so you can develop realistic cost and duration
estimates.
5
Activity Lists and Attributes
An activity list is a tabulation of activities to be included on a
project schedule. The list should include:
6
Activity Sequencing
Involves reviewing activities and determining
dependencies.
7
Conti….
Three Types of Dependencies
10
Arrow Diagramming Method (ADM)
Also called activity-on-arrow (AOA) network diagram.
12
Activity Resource Estimating
Before estimating activity durations, you must have a
good idea of the quantity and type of resources that will
be assigned to each activity.
Consider important issues in estimating resources:
How difficult will it be to complete specific
activities on this project?
What is the organization’s history in doing similar
activities?
Are the required resources available?
13
Activity Duration Estimating
Duration includes the actual amount of time worked on
an activity plus the elapsed time.
14
Schedule Development
Uses results of the other time management processes
to determine the start and end dates of the project.
Ultimate goal is to create a realistic project schedule
that provides a basis for monitoring project progress
for the time dimension of the project.
Important tools and techniques include Gantt charts,
critical path analysis, critical chain scheduling, and
PERT(Program Evaluation And Review Technique)
analysis.
15
Gantt Charts
Gantt charts provide a standard format for displaying
project schedule information by listing project activities
and their corresponding start and finish dates in a
calendar format.
17
Calculating the Critical Path
Develop a good network diagram.
Add the duration estimates for all activities on each
path through the network diagram.
The longest path is the critical path.
If one or more of the activities on the critical path takes
longer than planned, the whole project schedule will
slip unless the project manager takes corrective action.
18
Con…
19
Buffers and Critical Chain
A buffer is additional time to complete a task.
20
Schedule Control
Perform reality checks on schedules.
Allow for contingencies.
Don’t plan for everyone to work at 100 percent capacity all the
time.
Hold progress meetings with stakeholders and be clear and
honest in communicating schedule issues.
Goals are to know the status of the schedule, influence factors
that cause schedule changes, determine that the schedule has
changed, and manage changes when they occur.
21
Cont…
Tools and techniques include:
Progress reports.
22
Reality Checks on Scheduling
Review the draft schedule or estimated completion date
in the project charter.
Prepare a more detailed schedule with the project team.
Make sure the schedule is realistic and followed.
Alert top management well in advance if there are
schedule problems.
23
Using Software to Assist in Time
Management
Software for facilitating communication helps people
exchange schedule-related information.
24
Chapter Summary
Project time management is often cited as the main
source of conflict on projects, and most IT projects
exceed time estimates.
Main processes include:
Activity definition
Activity sequencing
Activity resource estimating
Activity duration estimating
Schedule development
Schedule control
25
26