Job Scheduling1
Job Scheduling1
DEADLINES
The problem is stated as below.
• There are n jobs to be processed on a machine.
• Each job i has a deadline di≥ 0 and profit pi≥0 .
• Pi is earned iff the job is completed by its deadline.
• The job is completed if it is processed on a machine
for unit time.
• Only one machine is available for processing jobs.
• Only one job is processed at a time on the machine.
1
JOB SEQUENCING WITH
DEADLINES (Contd..)
• A feasible solution is a subset of jobs J such that
each job is completed by its deadline.
• An optimal solution is a feasible solution with
maximum profit value.
Example : Let n = 4, (p1,p2,p3,p4) = (100,10,15,27),
(d1,d2,d3,d4) = (2,1,2,1)
2
JOB SEQUENCING WITH
DEADLINES (Contd..)
Sr.No. Feasible Processing Profit value
Solution Sequence
(i) (1,2) (2,1) 110
(ii) (1,3) (1,3) or (3,1) 115
(iii) (1,4) (4,1) 127 is the optimal one
(iv) (2,3) (2,3) 25
(v) (3,4) (4,3) 42
(vi) (1) (1) 100
(vii) (2) (2) 10
(viii) (3) (3) 15
(ix) (4) (4) 27
3
Algorithm: GreedyJob (d, J, n)
• { // Jobs are arranged in decreasing order of profits.
• // J is a set of jobs that can be completed
• // by their deadlines.
• J = {empty set};
• // Initialize J as an empty set
• for i = 1 to n do
• { if (all jobs in J U {i} can be completed by their
deadlines)
• then J = J + {i}; // Add job i to the set J } }
4
Q.
Profit
Job Deadline (di) (Pi)
J1 1 100
J2 2 10
J3 2 15
J4 2 27
Sort by Profit (Decreasing): The jobs are rearranged based on
profit in descending order.
Deadline Profit
Job (di) (Pi)
J1 1 100
J4 2 27
J3 2 15
J2 2 10 5
•Select Maximum Deadline: The maximum deadline among all jobs is identified as 2.
•This indicates the total number of slots available for scheduling.
•Greedy Selection:
•Job J1: Deadline is 1, which fits within the available slots. It's selected and contributes a profit
of 100.
•Job J4: Deadline is 2, which also fits within the available slots. It's selected and adds a profit of
27.
•Job J3: Deadline is 2, but the slot for deadline 2 is already occupied by J4. Therefore, J3 is
skipped.
•Job J2: Deadline is 2, but the slot for deadline 2 is already occupied by J4. Therefore, J2 is
skipped
10
GREEDY ALGORITHM TO
OBTAIN AN OPTIMAL SOLUTION
• Consider the jobs in the non increasing
order of profits subject to the constraint that
the resulting job sequence J is a feasible
solution.
• In the example considered before, the non-
increasing profit vector is
(100 27 15 10) (2 1 2 1)
p1 p4 p3 p2 d1 d4 d3 d2
11
GREEDY ALGORITHM TO OBTAIN AN
OPTIMAL SOLUTION (Contd..)
J = { 1} is a feasible one
J = { 1, 4} is a feasible one with processing
sequence
( 4,1)
J = { 1, 3, 4} is not feasible
J = { 1, 2, 4} is not feasible
J = { 1, 4} is optimal
12
GREEDY ALGORITHM TO OBTAIN AN
OPTIMAL SOLUTION (Contd..)
13
GREEDY ALGORITHM TO OBTAIN AN
OPTIMAL SOLUTION (Contd..)
Proof:
• By definition of the feasible solution if the
jobs in J can be processed in the order
without violating any deadline then J is a
feasible solution.
• So, we have only to prove that if J is a
feasible one, then represents a possible
order in which the jobs may be processed.
14
GREEDY ALGORITHM TO OBTAIN AN
OPTIMAL SOLUTION (Contd..)
15
GREEDY ALGORITHM TO OBTAIN AN
OPTIMAL SOLUTION (Contd..)
in i1,i2,…,ik]
1 = (r1,r2,… ra rb … rk )
i1=r1, i2=r2,…ia-1= ra-1, ia rb but ia = rb
17
GREEDY ALGORITHM TO OBTAIN AN
OPTIMAL SOLUTION (Contd..)
19
GREEDY ALGORITHM TO OBTAIN AN
OPTIMAL SOLUTION (Contd..)
• Theorem2:The Greedy method obtains an optimal
solution to the job sequencing problem.
• Proof: Let(pi, di) 1in define any instance of the
job sequencing problem.
• Let I be the set of jobs selected by the greedy
method.
• Let J be the set of jobs in an optimal solution.
• Let us assume I≠J .
20
GREEDY ALGORITHM TO OBTAIN AN
OPTIMAL SOLUTION (Contd..)
26
GREEDY ALGORITHM FOR JOB
SEQUENSING WITH DEADLINE
Procedure greedy job (D, J, n) J may be represented by
// J is the set of n jobs to be completed// one dimensional array J (1: K)
// by their deadlines // The deadlines are
J {1} D (J(1)) D(J(2)) .. D(J(K))
for I 2 to n do To test if JU {i} is feasible,
If all jobs in JU{i} can be completed we insert i into J and verify
by their deadlines D(J®) r 1 r k+1
then J JU{I}
end if
repeat
end greedy-job
27
GREEDY ALGORITHM FOR
SEQUENCING UNIT TIME JOBS
Procedure JS(D,J,n,k)
// D(i) 1, 1 i n are the deadlines //
// the jobs are ordered such that //
// p1 p2 ……. pn //
// in the optimal solution ,D(J(i) D(J(i+1)) //
// 1 i k //
integer D(o:n), J(o:n), i, k, n, r
D(0) J(0) 0
// J(0) is a fictious job with D(0) = 0 //
K1; J(1) 1 // job one is inserted into J //
for i 2 to do // consider jobs in non increasing order of pi //28
GREEDY ALGORITHM FOR
SEQUENCING UNIT TIME JOBS (Contd..)
// find the position of i and check feasibility of insertion //
r k // r and k are indices for existing job in J //
// find r such that i can be inserted after r //
while D(J(r)) > D(i) and D(i) ≠ r do
// job r can be processed after i and //
// deadline of job r is not exactly r //
r r-1 // consider whether job r-1 can be processed after i //
repeat
29
GREEDY ALGORITHM FOR
SEQUENCING UNIT TIME JOBS (Contd..)
31
COMPLEXITY ANALYSIS
OF JS ALGORITHM
• Let n be the number of jobs and s be the number of
jobs included in the solution.
• The loop between lines 4-15 (the for-loop) is
iterated (n-1)times.
• Each iteration takes O(k) where k is the number of
existing jobs.
The time needed by the algorithm is 0(sn) s n so
the worst case time is 0(n2).
If di = n - i+1 1 i n, JS takes θ(n2) time
D and J need θ(s) amount of space.
32
A FASTER
IMPLEMENTATION OF JS
• The time of JS can be reduced from 0(n 2) to
0(n) by using SET UNION and FIND
algorithms and using a better method to
determine the feasibility of a partial
solution.
• If J is a feasible subset of jobs, we can
determine the processing time for each of
the jobs using the following rule.
33
A FASTER IMPLEMENTATION OF
JS (Contd..)
• If job I has not been assigned a processing time,
then assign it to slot [ -1, ] where is the
largest integer r such that 1 r di and the slot [
-1, ] is free.
• This rule delays the processing of jobs i as much
as possible, without need to move the existing jobs
in order to accommodate the new job.
• If there is no , the new job is not included.
34
A FASTER IMPLEMENTATION OF
JS (Contd..)
EXAMPLE: let n = 5, (p1,--------p5) = (20,15,10,5,1) and (d1,--d5) =
(2,2,1,3,3). Using the above rule
J assigned slot jobs being considered action or
Ø none 1 assigned to [1, 2]
{1} [ 1,2] 2 [0,1]
{1,2} [0,1],[1,2] 3 cannot fit reject as
[0,1] is not free
{1,2} [0,1],[1,2] 4 assign to [2,3]
{1,2,4} [0,1],[1,2],[2,3] 5 reject
35
A FASTER IMPLEMENTATION OF
JS (Contd..)
• As there are only n jobs and each job takes one unit of time,
it is necessary to consider the time slots [i-1,i] 1 i b
where b = min {n, max {di}}
• The time slots are partitioned into b sets .
• i represents the time slot [i-1,i]
[0 1]is slot 1
[1 2] is slot 2
• For any slot i, ni represents the largest integers such that ni
i and slot ni is free.
If [1,2] is free
n2=2 otherwise
n2=1 if [0 1] is free 36
A FASTER IMPLEMENTATION OF
JS (Contd..)
• To avoid end condition, we introduce a fictious
slot [-1, 0] which is always free.
• Two slots are in the same set iff ni= nj
• If i and j i < j are in the same set, then i, i+1, i+2,
…i are in the same set.
• Each set k of slots has a value f(k) ,f(k)=ni, for all
slots i in set k. (f(k) is the root of the tree
containing the set of slots k)
• Each set will be represented as a tree.
37
A FASTER IMPLEMENTATION OF
JS (Contd..)
• Initially all slots are free and f(i) = i 1 i b.
• P(i) represents as a negative number the
number of nodes in the tree represented by the
set with slot I.
• P(i) = -1 0 i b initially.
• If a job with deadline d is to be scheduled, we
find the root of the tree containing the slot min
{n, d}.
38
A FASTER IMPLEMENTATION OF
JS (Contd..)
EXAMPLE: For the problem n =5 (p1…p5) = (20,15,10,5,1),
(d1------d5) = (2,2,1,3,3) the trees defined by the P(i)’s are
J 1 2 3 4 5 Job considered
-1 -1 -1 -1 -1 -1 1,d1 = 2 [1,2] is free
φ P(0) P(1) P(2) P(3) P(4) P(5)
1 0 1 P(1) F(1)=0 2, d1 = 2
-2 F(1) = 1 [0,1] free
P(0) P(2) {1,2} -3 P(1)2 F[1] = 0 reject
0 0
39
A FASTER IMPLEMENTATION OF
JS (Contd..)
The algorithm for fast job scheduling (FJS) is as follows
Procedure FJS (D,n,b,j,k)
// Find an optimal solution J = J(1),…,J(k) 1 k n //
// It is assumed that p1 p2 …..pn and b = min{n, max(d(i)) //
Integer b, D(n) ,J(n),F(O: b), P(O: b)
for i0 to b. Do // initialize trees //
F(i) i; P(i)-1
repeat
K 0 // Initialize J //
40
A FASTER IMPLEMENTATION OF
JS (Contd..)
For i 1 to n do // use greedy rules //
j FIND (min (n, D(i)) // F(j) is the nearest free
slot if F(j) ≠ 0 //
if F(j) ≠ 0 then k k+1 ; J(k)i
All slots are not occupied
//select job i //
L Find (F(j)-1); call union (L, j)
F(j)F(L) // j may be new root //
endif
repeat
end FJS
41
A FASTER IMPLEMENTATION OF
JS (Contd..)
It is F(j) –1 because you need to union J with I which
is F(j) -1.
F(i) is a value for a set of slots with l which is F(j)-1
F(k) = ni for all slots in the set k.
ni is that largest integer such that
ni i and slot ni is free
F(1)=1 [0 1]
F(2)=2 [1 2]
P(i)= is the number of nodes in the tree respectively the
set with slot . 42
A FASTER IMPLEMENTATION OF
JS (Contd..)
Complexity of algorithm FJS
As there are n unions and 2n finds, in the for loop the
computing time is
0(n (2n , n))
(m, n) m n is related to Ackermal function
(m,n)= min {z 1/A(3, 4[m/n]) > logn2}
For all practiced purposes, we may
assume log n < A(3,4) and hence
(m,n) 3 m n
The computing time of FJS is O(n)
Additional 2n words of space for F and P are required.
43