Session 9 - Process Costing
Session 9 - Process Costing
Topic 9
PROCESS COSTING
xx xx
Process B Account
Transfer from Transfer to next
Process A process C
xx xx
Direct Material
xx
Direct labour
xx
Production
Overheads
• During February, the following costs were incurred in a process:
$
Materials 20,000
Labour 10,000
Overheads 8,000
• A normal loss of 10% was expected. The actual output was 900 kg.
• A normal loss of 10% was expected. The actual output was 2,700 kg.
Losses have a scrap value of $5 per unit.
Calculate the cost per kg and prepare a Process Account and a
Loss Account.
ABNORMAL LOSS QUESTION
• During May, the following costs were incurred in a process:
$
Materials (1,000 kg) 9,000
Labour 18,000
Overheads 13,500
• A normal loss of 10% was expected. The actual output was 850 kg.
Losses are sold as scrap for $9 per kg
• A normal loss of 10% was expected. The actual output was 1,840 kg.
Losses are sold as scrap for $9 per kg.
Units $ Units $
Materials 3000 15000 Scrap: normal 600
($5*3000) loss 2400
(4*600)
Labour 2400 Process 2 2300 2300
(10*2300) 0
Overhead 9000 Abnormal loss 100
(2400*375%) (10*100) 1000
= 26400-2400
3000-600
=$10 per unit
Process 2 account
Units $ Units $
Process 1 2300 23000 Scrap: normal loss 430 2580
Materials 2000 16000 ($6*430)
Labour 1680 Finished Goods 4000 48000
Overhead 8340 ($12*4000)
(1680*469.4%)
4300 49020
Abnormal gain 130 1560
($12*130)
Units $ Units $
Process 1 100 1000 Scrap 100 400
Profit and 600
loss
100 1000 100 1000
Unit $ Unit $
Normal loss 600 2400 Abnormal 130 780
(Process1) gain(Process2)
(130*$6)
Working 2
Determining the output and loss:
Input (2300+2000) 4300 units
Less: normal loss (10%) 430 units
Expected output 3870 units
Actual output 4000 units
Abnormal gain 130 units
WORK IN PROGRESS
• At the end of a process there may be some units that have been started
but not completed. These are known as closing work-in-progress. They
are still there at the start of the next period, waiting to be finished. They
are therefore opening work-in-progress of the next period.
EQUIVALENT UNITS OF
PRODUCTION
• Equivalent units are notional whole units which represent incomplete
work, and which are used to apportion costs between work in process and
completed output.
• For costing purposes we assume the work done on 100 units that are only
half finished is equivalent to 50 fully finished units. Therefore, 100 units
each 50% finished is regarded as 50 equivalent complete units.
• Direct materials. These are added in full at the start of processing, and so
any closing WIP will have 100% of their direct material content.
• Direct labour and production overhead. These are usually assumed to be
incurred at an even rate through the production process, so that when we
refer to a unit that is 50% complete, we mean that it is half complete for
labour and overhead, although it might be 100% complete for materials.
EXAMPLE :PROCESS ACCOUNT
Process Account
Units $ Units $
Materials 1,000 6,200 Finished goods 800 ?
Labour overhead 2,850 Closing WIP 200 ?
1,000 9,050 1,000 9,050
Let us also assume that the closing WIP is 100% complete for materials and 25%
complete for labour and overhead.
STEP 1 (CALCULATE EQUIVALENT UNITS)
STATEMENT OF EVALUATION
Materials Labour and overhead
Cost per Cost per
Item Equivalent equivalent Equivalen equivalent Total
units unit Cost t units unit Cost Cost
$ $ $ $ $
Finished 800 6.20 4,960 800 3.3529 2,682 7,642
output
Closing 200 6.20 1,240 50 3.3529 168 1,408
WIP
1,000 1,000 850 2,850 9,050
PROCESS ACCOUNT (WORK IN PROGRESS, OR
WORK IN PROCESS ACCOUNT)
Process Account
Units $ Units $
Materials 1,000 6,200 Finished goods 800 7,642
Labour overhead 2,850 Closing WIP 200 1,408
1,000 9,050 1,000 9,050
EXAMPLE
• The total production cost for January 2019 was $40000.
8000 units had been completed and 4000 units were 50%
complete.
118000
TANK YOU TANK YOU TANK YOU