Lecture 9 - Resourcing & Goldratts Critical Chain
Lecture 9 - Resourcing & Goldratts Critical Chain
Resource Allocation
Chapter 6
Course Outline
Course Component Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7
Wk Begin 27-Jan 03-Feb 10-Feb 17-Feb 24-Feb 03-Mar 10-Mar
Online
Feb Bank
Lecture 1 No Lecture 1 PM Roles & Assessment 1 Managing & No Lecture 1
Holiday PERT
Mon 17.00 - 18.00 Project Scope 25% Budgeting
Lecture 2 Course
Project Project No Lecture 2 Goldratt &
Tues 17.00-18.00 Overview & Planning Scheduling
Selection Crashing Levelling
Introduction
Network PERT/CPM
Video Tutorials Introduction Project Project
Diagrams & Activity
Released to MS Project Selection Crashing
CPM Sequencing
Class Update
• This weeks Tutorial on PERT & Levelling is now uploaded to
Brightspace
• Required Reading
–Chapter 6 Project Management in Practice
–Overview-of-Critical-Chain
• Then the employee is assigned other tasks until he or she reaches 100 percent
booked. This would then mean that the employees cannot take on any additional
work.
• With resource loading, a project manager can predict an employee's hours for the
year and see how tasks can be assigned. This also allows the project manager to
decide whether or not additional employees or contractors are needed to
complete the scheduled projects.
• Consider the AOA network diagram shown. Critical Path 1,2 & 4
• Task 2 & 3 are sharing the same resource A
Managing the Critical Chain
ID Task Task Name Duration 09 Mar '15 16 Mar '15 23 Mar '15 30 Mar '15 06 Apr '15
Mode M T WT F S S M TW T F S S M TW T F S S M TW T F S S M T W
1 Task 1 Start 0 days 12/03
2 Task 2 7 days A
3 Task 3 5 days A
4 Task 4 6 days B
5 Task 5 10 days C
• Gannt Chart demonstrates both task 2 & 3 starting at the same time
competing for resource A
Resource Levelling
• For project managers, a key mission is to ensure that all
project team members are assigned the right tasks – and the
right amount of work – given their availability. That means if
someone is only available 8 hours a day, then the project
schedule should only reflect (at most) 8 hours of work on that
person each day.
• Good project managers know a resource can’t squeeze triple
the work into a given day just because that is what we see on
the screen, so it’s the project schedule that needs to adjust. It
needs to be “resource levelled.”
Managing the Critical Chain
ID Resource Name Work Details 09 Mar '15 16 Mar '15 23 Mar '15 30 Mar '15
M T W T F S S M T W T F S S M T W T F S S M T W
Unassigned 0 hrs Work
Task 1 Start 0 hrs Work
1 A 96 hrs Work 16h 16h 16h 16h 16h 8h 8h
Task 2 56 hrs Work 8h 8h 8h 8h 8h 8h 8h
Task 3 40 hrs Work 8h 8h 8h 8h 8h
2 B 48 hrs Work 8h 8h 8h 8h 8h 8h
Task 4 48 hrs Work 8h 8h 8h 8h 8h 8h
3 C 80 hrs Work 8h 8h 8h 8h 8h 8h 8h 8h
Task 5 80 hrs Work 8h 8h 8h 8h 8h 8h 8h 8h
180%
160%
140%
120%
100%
80%
60%
40%
20%
A
Overallocated: Allocated:
ID Task Task Name Duration 09 Mar '15 16 Mar '15 23 Mar '15 30 Mar '15 06 Apr '15
Mode MTWT F S S MTWT F S S MTWT F S S MTWT F S SMTWT F S
1 Task 1 Start 0 days 12/03
2 Task 2 7 days A
3 Task 3 5 days A
4 Task 4 6 days B
5 Task 5 10 days C
• Managing the resource A conflict has now extended project timeline and changed the critical path to
1,2,34
Figure 6-24 Sample Network
Diagram
09 Mar '15 16 Mar '15 23 Mar '15 30 Mar '15 06 Apr '15
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
100%
80%
60%
40%
20%
Peak Units: 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
C
Overallocated: Allocated:
Resource Leveling with Microsoft Project