Lecture 7 - Project Crashing
Lecture 7 - Project Crashing
Project Crashing
Course Outline
Course Component Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7
Wk Begin 27-Jan 03-Feb 10-Feb 17-Feb 24-Feb 03-Mar 10-Mar
Online
Feb Bank
Lecture 1 No Lecture 1 PM Roles & Assessment 1 Managing & No Lecture 1
Holiday PERT
Mon 17.00 - 18.00 Project Scope 25% Budgeting
Lecture 2 Course
Project Project No Lecture 2 Goldratt &
Tues 17.00-18.00 Overview & Planning Scheduling
Selection Crashing Levelling
Introduction
Network PERT/CPM
Video Tutorials Introduction Project Project
Diagrams & Activity
Released to MS Project Selection Crashing
CPM Sequencing
Class Update
• This weeks Reading
– Chapter 6 Project Management in Practice
– “Planning For Crises in Project Management”
Physical resources
– Materials, machine, chemicals, services, etc
Human resources
– People, labour, competencies
– Consumed resources imply that specific quantities are allocated and used during
the project such as materials or energy.
– Non-consumed resources imply that resource which are no longer required or
currently not required will be available for other projects, such as skilled workers,
machines and specialist competencies.
• In either case PMs need to optimise the use of resources, which means
management of limitations and trade offs (time, cost, performance etc).
Crashing
• We evaluated project duration CPM. We will
extend this to consider use of limited
resources.
– Crashing the project is to expedite by leveraging
extra resources.
– Crashing requires available resources (beyond the
standard) and therefore additional cost.
Crashing Objective
• The objective of crashing is to reduce the critical path
duration whilst minimising the impact on project costs.
Activity Predecessor Normal Duration Crash Duration Normal Crash Cost Cost per Day
s (Days) (Days) Cost
a - 6 5 60 90 30/d
b - 7 4 50 150 33/d
c a 6 4* 100 160 60*
d a 7 7 30 30 NA
e b 5 4 70 85 15/d
f c 9 7 40 120 40/d
g d,e 7 4 50 230 60/d
Example Network
Critical Path = 21 days
Activity Predecessor Normal Duration Crash Duration Normal Crash Cost Cost per Day
s (Days) (Days) Cost
a - 6 5 60 90 30/d
b - 7 4 50 150 33/d
c a 6 4* 100 160 60*
d a 7 7 30 30 NA
e b 5 4 70 85 15/d
f c 9 7 40 120 40/d
g d,e 7 4 50 230 60/d
Note. When we crash activity “a” by 1 day it cannot be crashed any further as
it has reached its crashing contraint. We have reduced the critical path to 20
days. The cost of the project has increased to $430.
Check the other paths
Activity a is crashed from
Critical Path = 20 days
6 days to 5
Critical Path = 21 days
5 days
a, d, g Path = 20 days
a, d, g Path = 19 days
b, e, g Path = 19 days
Activity Predecessor Normal Duration Crash Duration Normal Crash Cost Cost per Day
s (Days) (Days) Cost
a - 6 5 60 90 30/d
b - 7 4 50 150 33/d
c a 6 4* 100 160 60*
d a 7 7 30 30 NA
e b 5 4 70 85 15/d
f c 9 7 40 120 40/d
g d,e 7 4 50 230 60/d
Check the other paths
Activity c is crashed from
a, c, f Path = 19 days
6 days to 4
4 days Critical Path = 21 days
b, e, g Path = 19 days
Activity Predecessor Normal Duration Crash Duration Normal Crash Cost Cost per Day
s (Days) (Days) Cost
a - 6 5 60 90 30/d
b - 7 4 50 150 33/d
c a 6 4* 100 160 NA
d a 7 7 30 30 NA
e b 5 4 70 85 15/d
f c 9 7 40 120 40/d
g d,e 7 4 50 230 60/d
Check the other paths
Activity a is crashed from 6 days
a, c, f Path = 19 days
to 5 days and f is crashed from 9
to 8 days Critical Path = 21 days
8 days
5 days
Critical
a, d, gPath
Path==20
19days
days
b, e, g Path = 19 days
b, e, g Path = 19 days
a 6 5
b 7 4
c 6 4*
d 7 7 f=7
c=4
e 5 4 a, c, f Path = 16
19 days
c is fully f is fully
f 9 7 crashed at 4 crashed at 7
g 7 4 days days
a is fully
crashed at 5
days5 days
d is not
crashable at 7
g=4
days g is fully
b=4 crashed at 4
e=4 days
a, d, g Path = 16
19 days
b,b,e,e,g gPath
Path= =1219 days
16days
b, e, g Path = 16 days