SAP PM - 2
SAP PM - 2
For Batch #3
March 3 , 2024
Topics covered
SAP PM KDS and Master Data
Maintenance Task Lists, Maintenance plan & Catalogue, Code groups and
Codes)
Master Data
Master data is the foundation of any SAP system.
Master data is typically updated infrequently, but it is critical to ensure that it is accurate and up-to-
date.
Some examples of PM master data include:
• Functional Location
• Equipment
• Work Center
• Measure Point / Counter
• Task List
• Maintenance Plan etc.
Cont.
SAP PM Organizational structure
SAP PM Technical structure
Cont.
Cont.
Work center
Usually represent one persons or a department responsible
so
• Costing data
• Create IR01
• Change IR02
• Display IR03
Object Type describes the type of technical object and used for grouping of
categorization based on similar type/ usage, e.g. DG, Turbine, Generator, Squirrel
Object type is assigned to Technical objects and can be used for technical objects
objects of a company
Coding template:- used to control which characters may be used when a label is
assigned together and how these characters are grouped together or split
Hierarchy level:- used to define which level ends at which characters and how many
• Create ILo1
• Change IL02
• DisplayIL03
• It usually represent a single object such as pumps, motors, for which maintenance
management
Machine
Fleet object
• Create IE01
• Change IE02
• Display IE03
• Structure IH03/IH04
)
Bill of material (BOM
2. Equipment BOM
• Create IB01
• Change IB02
• Display IB03
• Create IB11
• Change IB12
Measuring point and counters
• For Example coolant temperature in nuclear power station after the coolant has left
the pressure vessel and the number of revolution at rotor shaft of wind turbine
For example the characteristic ratio can have the characteristic unit percent and
the characteristic temperature can have the characteristic unit degree Celsius
or degree faharanite
Measuring document
Create:-IK11
Change:-IK12
Display:-IK13
Display all measuring documents:-Ik17
Maintenance task list
equipment
Reference object
Task list
interval
Cont..
Maintenance plane type
Single cycle plans
• Single cycle plans used to manage the maintenance of machines and operational
systems which are always inspected or maintained in the same way at fixed
interval
Completion requirement:- If you set this indicator, the system only generates the next Call
object once the preceding call object has been confirmed.
If incase you're planning to release the second schedule, the completion requirement check box is
in marked stage, the interface will not allow you to release the schedule due to the incompletion
of first schedule.
Start of cycle :- start date for calculating planned and call dates
Cycle modification factor :-Maintenance cycles can be lengthened or shortened using a
modification factor.
A modification factor greater than one lengthens the cycle, a modification less than one shortens
it.
Cycle modification factor
Scheduling period
Multiple counter plane
preventive maintenance
Define once, and then used in linking task list and maintenance plans
• The call horizon is used to define when the maintenance object (maintenance
order) is generated compared to the planned date
• Call horizon is specified as percentage of cycle
• If the total maintenance cycle is 250 day ,we define call horizon 0%,80% and
100% the system creates the maintenance order after following number of days
• 0%- immediately call the maintenance order
• 80%- call after 200 days (80% of 250 day)
• 100%- the call is made when the planned date has been reached
cont.
Shift factor
• The shift factor is the percentage of shift that a plan can move if not completed on
time.
• For example, if a maintenance plan is due Sept. 1, but the work is not confirmed
until Sept. 5, the shift factor will determine the next plan due date.
• A100% shift on a monthly plan will move the due date to the exact day in the next
month that the work was confirmed in September (in this case, Oct. 5).
• A 0% shift will not allow the plan to move the due date. The order was completed
Sept. 5, but the due date is on the first of every month, therefore, the next due
date will be Oct. 1.
cont.
Tolerances for late & early completion
If the completion is made no more than 3 days before the planned date ,the
system does not consider this deviation when calculating the next planed date.
cont.
Catalogs(QS41)
content
plant
describe objects
explanatory text
Cont..
Codes :- description of damage ,an activity, cause of damage, object part and
task and so on
for example damage to vehicle ,pumps and motors or mechanical damage and
electrical damage
Classification systems has the task of describing objects using characteristics ,and
grouping similar objects in a classes to classify them and make them easier to find
When we mange many objects we must be able to group these objects according to
features
CL01
CL02
CL03
CT04
Thank you