Formwork
Formwork
Presented
By
K.Lavanya
M.Tech
1
DEFINITION:
Its is an artificial support provided below and around
Steel
wood
SP-4. 2
Qualities of formwork:
It should be strong
It can be reusable
member.
3
Uses:
4
Major objectives considered in
formwork:
Quality
Safety
Economy
5
Quality:
Economy:
b) Concrete placement
8
TYPES OF FORMWORK:
Temporary Structure
9
Formwork detail for different
structural members
In concrete construction formwork is
commonly provided for the following
structural members.
o Wall
o Column
o Slabs & Beams
o Stairs
o Chimneys
o Water tanks
o Cooling Towers
10
Formwork for Wall
It consists of
• Timber sheeting
• Vertical posts
• Horizontal members
• Rackers
• Stakes
• Wedges
After completing
one side of
formwork
reinforcement is
provided at the
place then the
second side
formwork is
provided.
11
Wall forms:
Wall forms principally resist the lateral pressure
supported members.
Snap ties, flat ties, loop ties are single use ties usually
12
Wall forms:
13
Formwork for Column
It consists of
the following
Side & End
Planks
Yoke
Nut & Bolts
Two end & two
side planks are
joined by the
yokes and bolts.
14
Column
forms:
Column-forms materials tend to vary with the column
shape.
Wood or steel is often used with square or rectangular
column.
Round column forms more typically pre manufactured in a
17
Formwork for Slabs & beams:
It consists of
Sole plates
Wedges
Props
Head tree
Planks
Batten
Ledgers
Beam formwork
rests on head
tree
Slab form work
rests on battens
and joists
If prop height
are more than 8’
provide
horizontal
braces. 18
Lintel or Beam Formwork:
19
FORMWORK FOR SLAB:
20
FORMWORK FOR
STAIRS:
It consists of
Vertical &
inclined posts
Inclined
members
Wooden Planks
or sheeting
Stringer
Riser Planks
21
FORMWORK FOR STAIRS:
The sheathing or decking for deck slabs is
.
The cross- joists may be 5cm x 10cm size
23
FORMWORK FOR STAIRS:
24
FORMWORK FOR CHIMNEYS:
a) Jump form
b) Slip form
25
Jump Form:
In this type jacking bars are either cast
29
FORMWORK FOR CHIMNEYS:
30
Removal of formwork:
Time of formwork removal depends on the following factors
1. Type of Cement
31
Time of Removal of
formwork:
Sr OPC Rapid
. (Ordinary Hardeni
N
Structural Member
Portland
Cement)
ng
o
Cement
1 Beam sides, walls & 2-3 Days 2 Days
Columns
2 Slab (Vertical Supports remains 4 Days 3 Days
intact)
33
Cost of formwork
For normal works cost of formwork is about 30%-
factors
• Formwork Material cost
• Labor charges. 34
Advantages of steel form work:
It is non absorbent.
Easy to use.
35
LOADS ON FORMWORK:
Formwork is subjected to following loads:
a) Dead weight of concrete
b) Hydrostatic pressure of the concrete
c) Live load due to working laborers
d) Impact effect at the time of pouring
concrete into the formwork
e) Vibrations transmitted to formwork
during pouring concrete
36
FORMWORK DESIGN
Guiding points in the Design of formwork
For design purpose, temporary live load due to
q .(h/2) or 46 kg/ft
39
Contd...
40
Contd...
For horizontal pressure of concrete is given by:
For walls constructing R less than 2.1m/hr;
p =150+9000(R/T)
For walls constructing R varies from
2.1m/hr to 3m/hr;
p = 150+(43,400/T)+2800(R/T)
For columns 3m/hr;
p = 150+9000(R/T)
Where, R => rate of vertical placement,
T => time for placement.
41
DESIGN OF SLAB FORMWORK:
spacing)
Step 4: Determine stringer size and span (shore spacing)
42
43