CLAIMS - EOT - Lecture 5&6
CLAIMS - EOT - Lecture 5&6
&
EOT CLAIMS
LECTURE 5
E.MOHAMED HUSSIEN
Senior Project Controls Engineer
1
Concurrent delays/concurrency
Fragnet
Disruption
3
Who owns the float? It is a question
that you probably will not find a
definite answer for
4
• CONTRACTOR
• OWNER/CLIENT
• PROJECT
5
• The ‘contractor owns the float’
argument
6
Some industry insiders insist that
if the contract does not specify who
owns the float
it belongs to the contractor
because the contractor should have the right
to control its work
7
• The ‘client owns the float’ argument
8
The ‘project owns the float’
argument/joint ownership of float
9
END OF PART 1
10
LECTURE 6
WHO OWNS THE FLOAT
PART 2
11
Regardless of who owns the float, the
first question to ask is: what
are the implications of such ownership
12
Any delay or disruption
of that activity by the owner could
entitle the contractor to
compensation
for any additional costs of
delaying
performance of that event even
though
it does not delay completion of the
project 13
If the owner owns the float, it can
require that the contractor
perform additional work
that is not on a critical path
without extending the original
contract's deadline and without
paying additional compensation to
the contractor
14
As with many construction
issues, the ownership of the
float is a matter which can be
clearly settled by a specific
contract provision
15
How to mention the float in the
contract
16
CONCLUSION
17