Ch. 4-Project Implementation
Ch. 4-Project Implementation
Life of a Project
Chapter- 4
Project Implementation
1
Overview of Chapter - 4
2
Project Life
Project Life Cycle-Timeline
Cycle-Timeline
Phase 3
Phase 1 Phase 2
Time
3
1. Project Kick off/launching
4
1.Project
Kick-off/launching
Once the project proposal or
project contract is done, get
team together for the first
time—calls for a meeting in
order to formally Launch or
kick-off the project.
A kick-off meeting is a
meeting held at the beginning
of a project so that
stakeholders can meet each
other, review the objectives of
the project, and discuss future
plans.
Often used to get support for
a project and clarify roles and
responsibilities; and project
champion should speak first
and introduce the project 5
2. Direct and manage
project execution
6
Project Implementation
Project Implementation
Phase
Phase
Managing Work
Managing Work Schedule
Schedule
12
3. Planning- Activities need to
be Undertaken
13
3. Planning
3. Planning
What needs
What needs to
to be
be How it
How it is
is to
to be
be
accomplished?
accomplished? accomplished?
accomplished?
Steps
1. Refer project objectives – the
expected result.
2. Determine activities and approach to
be carried out to attain objectives. 14
3.1 Planning-
3.1 Planning- Work
Work to
to be
be
Accomplished
Accomplished
1. Developing the WBS
Identifying the level one major tasks.
Breaking the major tasks into level-two
tasks.
Breaking the major tasks into level-
three tasks.
16
3.2 Work
3.2 Work Breakdown
Breakdown Structure
Structure (WBS)
(WBS
18
3.5 Network
3.5 Network Diagram
Diagram
4. Interview Users 3
5. Study Existing System 3
6. Define User Requirements 4
7. Prepare System Analysis Report 5,6
20
8. Input & Output 7
9. Processing & Database 7
10. Evaluation 8,9
11. Prepare System Design Report 10
12. Software Development 11
13. Hardware Development 11
14. Network Development 11
15. Prepare System Development Report 12,13,14
16. Software Testing 15
17. Hardware Testing 15
18. Network Testing 15
19. Prepare Testing Report 16,17,18
20. Training 19
21. System Conversation 19
22. Prepare Implementation Report 20,21 21
3.6 Network
3.6 Network Plan
Plan Format
Format
Activity in
Activity in the
the Activity on
Activity on the
the
Box (AIB)
Box (AIB) Arrow (AOA)
Arrow (AOA)
22
4. Scheduling
23
4.1. Scheduling
4.1. Scheduling
24
4.2 Activity
4.2 Activity Duration
Duration Estimates
Estimates
2. Placing the Tasks in a Proper Sequence: The tasks are analyzed and placed in a sequence to
get the desired results.
3. Network Diagramming: A network diagram is drawn using the activity sequence data showing
the sequence of serial and parallel activities .
4. Time Estimating: This is the time required to carry out each activity, in three parts:
1. Optimistic timing: The shortest time to complete an activity
2. Most likely timing: The completion time having the highest probability
3. Pessimistic timing: The longest time to complete an activity
5. Critical Path Estimating: This determines the total time required to complete a project.
27
3. Network Diagramming
Example
Paint
Floors Move Back Furniture
1 5 2 1
KEY
The time for the work to be done plus any associated waiting time.
Þ Based on the quantity and quality of resources expected to be
used on the activity.
Þ Estimate should be aggressive yet realistic.
Solution:
Þ To determine the PERT estimate, we need the Optimistic Time, Pessimistic
Time, and Most Likely Time for the activity.
Þ The question says it is most likely that the task can be completed in 20 days,
hence: Most Likely Time = 20 days
Þ It further says that in the worst case it may take 30 days, hence: Pessimistic
Time = 30 days
Þ It also says that if all conditions are favorable, it will take 15 days to complete
the task. Hence: Optimistic Time = 15 days
Now,
Þ PERT Estimate = [Optimistic Time + 4 X (Most Likely Time) + Pessimistic Time]
/6
Þ = [15 + 4X20 + 30] / 6 = [15 + 80 + 30] / 6 = 125 / 6 = 20.83 days
KEY Duration
Activity Description
estimate
Activity
number
Person responsible 34
Latest Start
Latest Start (LS)
(LS) and
and Latest
Latest Finish
Finish (( LF)
LF)
37
Schedule for
Schedule for Developing
Developing Questionnaire
Questionnair
for Market
for Market Survey
Survey -- Total
Total Slack
Slack Value
Value
Earliest Latest
Sl. Activity Respons Duration Total
No ible Estimate Slack
Start Finish Start Finis
h
40
5. Financial
Management
41
5.1 Determining Actual Cost
Once the project starts, it’s necessary to keep track of
actual cost and committed cost so that they can be
compared to the CBC.
5.1.1 Actual Cost
To keep track of actual cost on a project, it’s necessary to set up
a system to collect, on a regular and timely basis, data on funds
actually expended.
5.1.2. Committed
Cost
In many projects, large dollar amounts are expended for
materials or services (subcontractors, consultants) that are used
over a period of time longer than one cost reporting period.
These committed costs need to be treated in a special way so
that the system periodically assigns a portion of their total cost
to actual cost.
Committed costs are also known as commitments or encumbered
costs.
Costs are committed when an item is ordered even though actual
42
5.1 Determining Actual Cost
43
5.1. Determining Actual Cost
5.1.3. Comparing Actual Cost to Budgeted
Cost
Example.Actual
Example. ActualCost
Costby
byPeriod
Periodfor
forthe
thePackaging
PackagingMachine
MachineProject
Project
Week Total
expended
1 2 3 4 5 6 7 8
Design 2 5 9 5 1 22
Build 2 8 10 14 12 46
Install & 0
Test
Total 2 5 9 7 9 10 14 12 68
CAC 2 7 16 23 32 42 56 68 68
45
5.2. Determining the Value of
Work Performed
Consider a project that involves painting ten similar rooms over
ten days (one room per day) for a total budgeted cost of $2,000.
The budget is $200 per room.
At of the end of day 5, you determine that $1,000 has actually
been spent, but what if only three rooms have been painted?
Earned value, the value of the work actually performed, is a key
parameter that must be determined throughout the project.
Determining the earned value involves collecting data on the
percent complete for each work package and then converting
this percentage to a dollar amount by multiplying the TBC of the
work package by the percent complete.
It’s important that the person estimating the percent complete
not only assess how much work has been performed but also
consider what work remains to be done.
For example, in the project involving painting ten rooms for
$2,000, if three rooms were completed, it’s safe to say that 30
percent of the work has been performed. Therefore, the earned
value is:
0.30 x $2,000= $600 46
5.2. Determining the Value of
Work Performed
5.2.1 Cumulative Percent Complete by Period for the Packaging
Machine Project
Week
1 2 3 4 5 6 7 8
Build 0 0 0 5 15 25 40 50
Install & 0 0 0 0 0 0 0 0
Test
Week
TBC 1 2 3 4 5 6 7 8
Design 24 2.4 6 19.2 21.6 24 24 24 24
Build 60 3 9 15 24 30
Install & Test 16
CEV 100 2.4 6 19.2 24.6 33 39 48 54
48
5.3. Cost Performance
The following fourAnalysis
cost-related measures are
used
to analyze project cost performance:
1. TBC ( total budgeted cost)
2. CBC (cumulative budgeted cost)
3. CAC ( cumulative actual cost)
4. CEV ( cumulative earned value)
Implication:
Actual cost is exceeding the budgeted cost.
Value of work performed is not keeping up with
actual cost.
50
5.3 Cost Performance
Analysis
5.3.1 Cost Performance Index
51
5.3. Cost Performance
Analysis
5.3.1 Cost Performance
Index
CPI as of week 8 in our example:
CPI = $54,000 / $68,000
= 0.79
This ratio indicates that with every
$1.00 expended, only $0.79 earned
value is received.
When CPI goes below 1.0 or gradually
gets smaller, corrective actions should
be taken.
Trend in CPI should be watched 52
5.3. Cost Performance
Analysis
5.3.2 Cost
Variance
Is the difference between the
cumulative earned value (CEV) of the
work performed and cumulative actual
cost (CAC).
CV = CEV – CAC
It shows the gaps between value of the
work performed and actual cost.
CV is expressed in terms of dollars.
53
5.3 Cost Performance
Analysis
5.3.2 Cost
Variance
CV as of week 8 in our example:
CV = $54,000 – $68,000
= – $14,000
Indicate value of work performed
through week 8 is $14,000 less than
the amount expended actually.
Data collected all be as current and
based on same reporting period.
54
5.4. Cost Forecasting
55
5.4. Cost Forecasting
63
6.1 Project
6.1 Project Team
Team
Low
Sense of team
Work performance 69
1.Clear
understanding
of project
objective
2. Clear
expectations
5. Result of each one’s
Orientation role &
responsibilities
6.3 Effective
Project Team
Characteristi
cs
3. High degree
4. High level of of
trust
cooperation
70
1. Unclear
Goals
2. Lack of
8. Turnover of project
team members
structure
3.Unclear role
6.4 Team &
7.Lack of
Effectiveness
commitment Barriers responsibilities
6. Poor 4.Poor
communication leadership
5.
Dysfunctional
Behavior
71
6.5 Nine
6.5 Nine Steps
Steps of
of Approach
Approach to
to problem
problem solving
solving
2.
• Restart process if analysis
pr
An
necessary • Brainstorm
ca
ob s
al
6. Evaluation
us
le
6.6
yz
• Prioritize
solution
in
Problem
g
Solving 3.
5. Implementing Generating • Brainstorm
• Project control Process
solution potential
• Maintain solution • Analyze
commitment potential helps
4. Selecting and and hinders
• Plan contingencies planning solution
• Build on each
other’s ideas
• Prioritize solution
• Resources/costs
• Clarity tasks/action plan
• Present proposals
73
7.Time Management
7.Time Management
74
7.Time Management
7.Time Management
75
7: Communications
76
7. Communication
7. Communication
79
7. Communication
7. Communication
80
8: Quality Management
81
8. Quality
8. Quality Management
Management
84
9. Project Monitoring and
Evaluation
85
9. 1 Project Cycle
86
9.2 Monitoring
9.2 Monitoring and
and controlling
controlling project
project
work
work
Monitoring and evaluation (M&E)
needs to be prepared and planned
from the beginning of the design, and
a specific budget allocated. The work
progress is continuously monitored
and appropriate adjustments are
made and recorded as variances from
the original plan. In any project, a
project manager spends most of the
time in this step.
The evaluation process it is often
conducted by an external person to
the project team (an evaluator) and
sometimes organised by the donor.
87
9.2 Monitoring
9.2 Monitoring and
and controlling
controlling
project work
project work and
and modify
modify as
as required
required
88
9.3 Project
9.3 Project Monitoring
Monitoring
To ensure that everything is going
according to plan.
Project Control Measuring Actual Progress
To ensure:
• Greater accountability in the use of
resources.
• Greater focus on the achievement
of results.
• A clearer basis for decision making.
• Promotion of institutional learning
and knowledge sharing.
90
9.5 Monitoring
Questions
Goal Measuring changes at Goal level requires a longer
time frame, and is therefore dealt with by evaluation
and not monitoring
92
9.7 Monitoring and Evaluation throughout the
lifespan of project
Flow of
benefits
Ex-post
evaluation
Final
evaluation
Mid-term
evaluation
Development
al Evaluation
Baselin
e
Continuous monitoring &
Periodic management
reviews
Time
Duration of project
93
9.7 A Continuous Process
Daily
Weekly
Bi-weekly
Monthly
Þ Depends on
(i) overall duration of the project
(ii) complexity of the project
Shorter the reporting period, the better
the chance of identifying problems.
95
9.9 A Differences between monitoring and evaluation.
For
Why? When? Who?
whom?
Check progress towards Continuous The project Project
planned objectives activity team management
(impact monitoring), Main
outputs and activities stakeholders
Monitoring (implementation
monitoring)
Take remedial action if
necessary
Contribute to progress
report
96
9.9 Monitoring vs. Evaluation
Monitoring Evaluation
Continuous: day-to-day Periodic: important milestones
98