For Stringing Training
For Stringing Training
TRANSMISSION LINES
STRINGING - METHODS
• Basically there are three methods of stringing
– Manual Method
– Tension Method
– Helicopter method
STRINGING METHODS
• Manual Method:
– In this method, conductor is pulled along the
ground by means of a pulling vehicle. The
conductor drum shall be mounted on a drum
lifting jack.
– The major drawback is that surface condition of
the conductor will get damaged
Tension stringing method
• This method is used to keep conductor surface safe during stringing process.
In this method, the conductor is kept under tension during the stringing
process to keep the conductor clear of the ground.
• A pulling line is initially pulled into the travelers which is then used to
pull the conductor from the reel stands using specially designed tensioners
and pullers.
• There are basically two types of pulling machines used in the construction of
transmission lines being strung under tension. These are defined as bullwheel and
drum/reel-type.
• Pullers should be equipped with load-indicating and load-limiting devices.
• Tensioners should be equipped with tension indicating devices. The capacities of the
puller and tensioner should be based on the conductor, span length, terrain, and
clearances required above obstructions.
• Sag tensions should never be exceeded during stringing. Required capacity for
both puller and tensioner can be calculated as mentioned in IEE 524.
• Positive braking systems are required for pullers and tensioners to
maintain conductor tension when pulling is stopped.
• The pulling and braking systems should operate smoothly and should not cause any
sudden jerking or bouncing of the conductor
TENSION STRINGING – TOOLS AND PLANTS
Details
• □ Essential parameter
Maximum Tension(kN):30
Continuous Tension(kN):25
Maximum speed (km/h):5
Bullwheel bottom of groove dia
meter(mm):Φ1200
Number of grooves:5
Maximum pullback (kN):20
Maximum suitable conductor di
ameter (mm): Φ32,
Engine power /speed
(kW/rpm)
:11/2200
Dimensions (mm): 3560
×1600
×2220
Weight(kg):1700
Features of Tensioner (YK-YZ30A)
• Essential parameter
• Maximum linepull (kN):30
• Continuous linepull (kN):25
• Maximum linespeed (km/h):5
• Bullwheel bottom of
groove diameter(mm) :Φ300
• Bullwheel grooves
number : 7
• Maximum suitable
steelrope
diameter (mm): Φ13
• Maximum through
connector diameter (mm):
Φ40
• Engine power
/speed
(kW/rpm):31/2200
• Dimensions(mm):320
0×1600×2000
•
Features of (YK-YQ30):
• 1. Infinitely variable speed and line control ,the pull in the
rope can be read on the line pull gauge .
• 2. The max pull for conductor –stringing operation can preset
,automatic overpull protection system .
• 3. Spring applied –hydraulic release brake acts automatically in
case of hydraulic failure ensure to safety .
• 4. Attached reel winder with automatically level wind .load
and unload conveniently .
• □ main component :
• 1.Chinese famous diesel engine.
• 2. Main pump:SAUER –SUNDSTRAND pump .main motor :
SAI techniques product .
• 3. Radiator:AKG
• 4.Hydraulic instrument:WIKA
• 5.Mating with model GSP950 drum
Stringing tools
Engine-winch-
hydraulic-
compression die machine- diesel-5-
compressor
sets ton-capacity
machine-motorised
Equalizer- Eye-type-four- Four-Sheave-
pulley sheave pulley pulley
hydraulic-cond-cutter- kitto-
clamp open-type-
two-cup-up-to-40mm-
single sheave-
dia- acsr
pulley
OPGW-Cable- patta
Comealong clamp
pulley-
blocks
pilot wire
reel
sag sagging- single-rope- snatch-
scope pulley pulley pulley
Turn-buckle-3t-
turn-table- 10t
snatch-
swivel-joint with- breaking
type- steel-
&
pulley
HELICOPTER METHOD
?
During stringing what should be strung first…
Swive
Tensione Pulle l
r r
• OPGW Cable with optical fiber are similar to those used for installation of the standard
ground wire cable special care should be taken to avoid any damage to the fibers by
observing the minimum bending radius at all times
• Therefore, specific components and machinery are used for the OPGW cable: pullers,
tensioners, anti twisting counterweights, swivels, pulling grips, pulley-blocks, self-
gripping clamps, pulling ropes, pulling cables, etc
Survey of the line:
• The OPGW drum lengths are determined based on the following considerations:
position of the tension towers, tower access, distance between supports and crossing
with other lines, roads, railways, routes, services and other obstacles.
• The position of the splices depends on the maximum available length of OPGW, on the
position of the towers and the tower access.
Transport, loading, unloading and storage:
• The drums should always be transported in vertical position with the cable ends
fixed to prevent cable from slackening. All of the staves and/or safeguards should
be maintained until the drums are situated for immediate installation.
• After the transport, the drums should be inspected to verify that they have not
been damaged and that none of the staves and/or safeguards are broken.
• The drums should never, under any circumstances, be thrown from the lorry
during unloading, nor moved by uncontrolled rolling.
• Loading and unloading are performed so that the drum ream ins in vertical
position and the sides of the drum are not damaged.
• The drums can be moved by rolling a short distance ensuring that there are no
objects that may damage the staves. The direction in which the drum turns
should be the same as that in which the cable is wound during manufacture.
• The drum should not be stored on its side under any circumstances
whatsoever.
• The ends of the cable should be sealed to prevent water penetration.
• The drums should be stored on flooring that is strong enough to prevent
sinking.
•
Positioning the equipments
The drum must be located at a distance of 2 or 3 metres from the
tensioner. The lifting components usually used are hydraulic jacks
and a bar with the suitable dimensions inserted in the central
opening of the drum. The drum must be located at a height of 10
to 15 cm from the ground.
Puller and tensioner
Either the puller and the tensioner must be placed at a minimum
distance from the tower equal or greater than 2 times the height of
the tower. The tensioner as well as the puller should be placed
aligned with the conductors. The maximum acceptable deviation
angle is 30º. (a < 30 º see Figure)
If it is not possible to achieve this angle, the puller and/or the tensioner
are placed close to the following tower, using an additional pulling cable
of the required length.
90º or less retracking of the optic cable is not allowed.
The tensioner as well as the puller should be positioned at a
minimum distance equivalent to twice the height of the support to
which the cable is fastened.
Positioning the equipments
The tensioner must be equipped with a dynamometer (i). Its reels must be
protected with material that does not damage the outer layer of the OPGW cable.
The puller must also be equipped with a dynamometer with automatic
disconnection in case of over tension on the cable.
The pulling cable should be joined to the OPGW cable by a swivel and a
pulling grip
• The minimum diameter of the reels (where the OPGW is to be coiled) used during
the installation should be at least 80 times the diameter of the OPGW cable, with
no need of exceeding 1500mm. For example, the tensioner reels for a 15mm
cable should have a diameter of approximately 1.2 meters.
In the tensioner, the first groove the cable will pass through must be
perpendicular to the axis of the drum. A double armour OPGW in the tensioner it
will enter from the left and leave from the right for right-hand lay sense (and from
the right and leave from the left for left-hand lay sense).
Ground connection of the OPGW
the breaking device and the puller have to be suitably connected to the
ground by a system of moveable rollers
• Before commencing of stringing, the angle towers where the stringing is to be started
have to be provided with guy supports for all the phases.
What are the precautions which should be taken at the time of guying?
• The guys used generally are 20 mm steel wire rope. The guys are attached to the
tower at the tip of the cross arm , to the strain plates with suitable D-shackles.
• The guys are anchored in the ground at an angle of 45 deg. or less from the
horizontal, attached to dead end anchors .
• The guy wire is attached to the dead end anchor wire with the help of turn
buckles of
10 tons capacity.
• In 400 KV lines V-type insulator strings are used on all suspension A-O and A-5 towers (up to a
deviation of 5 degrees). Double tension insulator strings are used at all B-30, C-60 and DE type
Tension towers.
• The number of insulator units to be used on various types of strings are vary.
• Double suspension insulator strings are used in 132 KV & 220 KV lines on Suspension towers of
River and Power line Crossings only.
• Double Tension insulator strings are used in 132 KV & 220 KV lines on Tension towers of
Railway, River and Power Line Crossings only
What are the precautions which should be taken at the time of insulator hoisting?
INSULATOR HOISTING:
PRECAUTIONS:
• After opening of the crates, insulators shall be laid in series, on wooden
planks below the suspension points.
• The insulators shall be cleaned with water and wiped dry with cloth free from
grease and oil.
• Insulators shall be checked for any chipping or crack and shall be replaced
with new one.
• The no. of insulators required for string shall be joined and R clips in the
clevis shall be expanded to avoid slippage of the pin.
• The hardware of the string on the tower side is assembled and joined
to the
first insulator by ball eye.
• The bottom insulator is joined to the twin moose roller. The neoprene rubber
cushion on the outer rollers shall be checked for any cracks/wearing out and
shall be changed if required.
• A single sheave pulley is fixed to the cross arm very near to the suspension
hanger. A 20 mm polypropylene rope is passed through the pulley.
• Both the end of the rope is brought to the ground. One end of the rope is
firmly tied below the 3rd or 4th insulator. The complete string with roller is
lifted up by pulling the rope through a pulley attached to one of the tower
legs by using tractor/manually.
• After reaching the top the string is attached to the suspension hanger and
string is released slowly to hang free.
Precautions shall be taken for hosting of insulator strings:
C.C. GRADING
RING RING
PAYING OUT OF PILOT WIRE:
• A pilot wire is used to pull the conductor. The pilot wire is
initially laid through the centre wheel of the roller.
• A 12 mm dia pilot wire is generally used for pulling of twin
moose conductor.
• The pilot wire can be laid length by length and joined with pilot
wire connectors or it can be pulled from one side of the section
after each drum is paid out.
• At power line crossings, the pilot wire is laid from both sides
and free ends are joined after obtaining the shutdown of
power line.
• Scaffolding shall be provided for P&T and road crossing before
paying out of the pilot wire.
POSITION OF TENSIONER AND PULLER:
• The paying out of conductor is done generally between two
tension towers.
• The puller machine can be positioned behind the tension
tower on one side and the tensioner in front of the tension
tower on the other side.
• Both the machine should be securely anchored.
• Reel winder shall be positioned at a convenient distance
behind the puller.
• The distance of the drums from the tensioner shall be at
least 25 to 30 mtrs.
Puller and tensioner operating characteristics :
• Semicircular grooves with depths in the order of 0.5 or more times the conductor
diameter and with flare angles in the order of 5° to 15° from the vertical generally
have been found to be satisfactory for stringing.
• The number of grooves in the bull wheel must be sufficient to prevent the outer
layer of wires of multilayer conductors from slipping over underlying layers.
• In order to avoid loosening of outer layer of strands as it passes on bull
wheel, for normal conductors having a right-hand direction of lay for the outer
wires, bull wheels should be arranged so that, when facing in the direction of pull,
the conductor will enter the bull wheel on the left and pull off from the right side
and will enter the bull wheel on the right and pull off from the left side for
normal conductor with outer layer having left had direction of lay.
• The material and finish of the grooves must be such as not to damage the surface
of the conductor.
PAYING OUT OF CONDUCTOR: