Revision
Revision
MODELS
INVENTORY AND
WAREHOUSE MANAGEMENT
BBMSCM320153
INVENTORY COSTS
Ordering cost - salaries and expenses of processing an order, Some times considering
Holding cost - usually a percentage of the value of the item assessed for keeping an item
in inventory (including finance costs, insurance, security costs, item assessed for keeping
an item in inventory, taxes, warehouse overhead, and other related variable expenses)
Backorder cost - costs associated with being out of stock when an item is demanded
Other costs
INVENTORY MODELS
questions:
time period.
EOQ
What is EOQ?
What is EOQ?
As demand for the inventoried item occurs, the inventory level drops.
When the inventory level drops to a critical point, the order point, the
The variable costs in this model a model are annual holding cost and
For the EOQ, annual holding and ordering costs are equal
MODEL I: BASIC EOQ - ASSUMPTIONS
Only one product is involved.
Annual demand (D), Carrying cost/Holding Cost (Ch ) and Ordering Cost/Set up Cost (Co ) can
ORDER QUANTITY MODEL (EOQ MODEL)
MODEL I: BASIC EOQ - FORMULAS
Ch
cost) = (D/Q) Co
TOTAL COST
COST MINIMIZATION GOAL
MINIMUM TOTAL COST
The total cost curve reaches its minimum where the carrying and
Total annual stocking cost (TC) = annual carrying cost + annual ordering cost =
(Q/2) Ch + (D/Q) Co
D = annual demand
L = lead time
The annual carrying cost for this material is 40% of the acquisition cost,
Bart's Barometer Business (BBB) is a retail outlet which deals exclusively with
the year.
Reordering costs are $80 per order and holding costs are figured at 20% of the cost of the item.
BBB is open 300 days a year (6 days a week and closed two weeks in August). Lead time is 60
working days.
EXAMPLE 2: BART’S BAROMETER BUSINESS
Bart should reorder 90 barometers when his inventory position reaches 100
EXAMPLE 2: BART’S BAROMETER BUSINESS
Number of reorder times per year = (500/90) = 5.56 or once or once every
(300/5.56) (300/5.56) = 54 working days (about every 9 weeks).
EXAMPLE 2: BART’S BAROMETER BUSINESS
CLASSROOM EXERCISE TUTORIAL 1
An industrial machine tool manufacturer supplies replacement parts from its inventory.
Carrying costs are 25% percent per year, and part is valued in inventory at $100 each.
Calculate the economic order quantity and the optimal time between orders.
Assuming a 300-day work year, how many orders should be processed per year?
Formulas
p= daily production
Since we assume p will be larger than d, the daily inventory build up rate
• Thus
– Average Inventory = ½ (1 – d/p)Q
– If Annual per unit Holding Cost is Ch
– Then Annual Holding Cost = ½ (1-d/p)Q*Ch,
– If the annual Demand is D and set up cost is Co
– Annual Set up cost = D/Q C0
• Total Cost = ½ (1-d/p)QCh, + D/Q C0
MODEL II. ECONOMIC PRODUCTION LOT SIZE
• Suppose that production facility operates 250 days a year, then we can
get daily demand d ( d = D/250 )
• Now lets assume that Annual Production is P,
• Then P = 250p,
• Thus p = P/250
• Thus d/p = (D/250) / (P/250) = D/P
• Hence we can now write the TC Total Cost = ½ (1-D/P)Q Ch, + D/Q C
MODEL II. ECONOMIC PRODUCTION LOT SIZE
• Formulas
• Optimal production lot-size: Q *2 = 2DCo /[(1-D/P )Ch ]
• Number of production runs per year: D/Q *
• Time between set-ups (cycle time): Q */D years
• Total annual cost: [(1/2)(1-D/P )Q *Ch ] + [DCo /Q *]
(holding + ordering)
EXAMPLE 1: EOQ FOR PRODUCTION LOTS
Highland Electric Co. buys coal from Cedar Creek Coal Co. to generate
electricity. CCCC can supply coal at the rate of 3,500 tons per day for
$10.50 per ton. HEC uses the coal at a rate of 800 tons per day and
operates 365 days per year
EXAMPLE 1: EOQ FOR PRODUCTION LOTS
HEC’s annual carrying cost for coal is 20% of the acquisition cost, and
the ordering cost is $5,000.
What is the economical production lot size?
What is HEC’s maximum inventory level for coal?
EXAMPLE 1: EOQ FOR PRODUCTION LOTS
EXAMPLE 1: EOQ FOR PRODUCTION LOTS
EXAMPLE 1: EOQ FOR PRODUCTION LOTS
EXAMPLE 2: NON-SLIP TILE CO
Non-Slip Tile Company (NST) has been using production runs of 100,000 tiles, 10
times per year to meet the demand of 1,000,000 tiles annually. The set-up cost is
$5,000 per run and holding cost is estimated at 10% of the manufacturing cost of
$1 per tile. The production capacity of the machine is 500,000 tiles per month.
The factory is open 365 days per year.
Total Annual Variable Cost
Optimal Production Lot Size
Number of Production Runs Per Year
Idle Time Between Production Runs
EXAMPLE 2: NON-SLIP TILE CO
21.1 days.
Thus, the machine is idle for 126.3 - 21.1 = 105.2 days between runs.
EXAMPLE 2: NON-SLIP TILE CO
Maximum Inventory
Current Policy
Optimal Policy
Would you recommend changing the current production lot size from the monthly 500 unit
production runs to EPQ? Why or why not? If yes, is there any savings of your recommendation,
if so what is it?
TUTORIAL_2
• A five days lead time is schedule and set up a production run and 250
working days
Find the recommended production lot size
Total annual cost
Re-order point
Cycle length
MODEL III. EOQ WITH PLANNED SHORTAGES
Shortage or stock-out is a demand that cannot be supplied.
However, there are situations shortage is desirable from economic point of view
- If the value of the of the inventory per unit is high, and hence holding is high
This model consider back-order cost
Assumptions
– Planned shortages are permitted (backordered demand units are withdrawn from a replenishment order
MODEL III. EOQ WITH PLANNED SHORTAGES
With the EOQ with planned shortages model, a replenishment order does not
arrive at or before the inventory position drops to zero.
Shortages occur until a predetermined backorder quantity is reached; at
which time the replenishment order arrives.
The variable costs in this model are annual holding, backorder, and ordering.
For the optimal order and backorder quantity combination, the sum of the
annual holding and backordering costs equals the annual ordering cost.
INVENTORY LEVELS FOR PLANNED SHORTAGES MODEL
MODEL III. EOQ WITH PLANNED SHORTAGES
Average
Inventory =
Since Q units are order each cycle, the length of a cycle (T)
must be
Average Backorders =
So, when we let the maximum No of backorders reach an amount of S
at a daily rate of d, the length of the backorder portion of the
inventory cycle is
Average Backorders =
MODEL III. EOQ WITH PLANNED SHORTAGES
Ordering cost: $Co per order.
The company is considering the possibility of allowing some backorders to occur for
the product. The backorder cost is estimated to be $30 per unit per year. Working
Days per year is 250.
What is Q* and S*.
MODEL III. EOQ WITH PLANNED SHORTAGES - EXAMPLE
Annual Cost
MODEL IV: EOQ
WITH QUANTITY
DISCOUNTS/
MODEL IV: EOQ WITH QUANTITY DISCOUNTS
This model's variable costs are annual holding, ordering and purchase
costs.
For the optimal order quantity, the annual holding and ordering costs are
Assumptions
Purchase Cost is $C1 per item if the quantity ordered is between 0 and x1 , $C2 if the
Formulas
– Q*2=1000
– Q*3=2500
Step 3 – For each order quantity computer the total annual cost. The Q yielding the
EOQ with Quantity Discounts Model Nick's Camera Shop carries Zodiac instant
print film. The film normally costs Nick $3.20 per roll, and he sells it for $5.25.
Zodiac film has a shelf life of 18 months. Nick's average sales are 21 rolls per
week. His annual inventory holding cost rate is 25% and it costs Nick $20 to place
an order with Zodiac. If Zodiac offers a 7% discount on orders of 400 rolls or
more, a 10% discount for 900 rolls or more, and a 15% discount for 2000 rolls or
more, determine Nick's optimal order quantity.
Thank you..