Ov 4
Ov 4
• Develop a WBS
• Create an Activity List
• Identify the Relationships between Activities
• Identify Resources
• Estimate Time
Project
Maps to
Stage 1 Stage 2 Stage 3 Deliverable project scope
statement
Work package
2.2.1.2.2
Activities
32 / 101 / 417
Function / Category / Program
(Consultant fees) (Special education)
(Professional expenditures)
• Describes the need, justification, requirements, and boundaries for the project.
• Components include:
• The detailed project scope statement.
• The WBS.
• The WBS dictionary.
Project Scope
Statement
WBS
WBS
Dictionary
Developing a WBS
• The amount of time that a particular task or work package will take to complete.
• The metrics used to express duration are in units of time such as days, weeks,
months, or years.
• Fixed duration is used to describe a task or work package that requires a set amount
of time to complete.
• Elapsed time the actual calendar time required for an activity from start to finish.
• The measure of labor that must be applied to the completion of a particular task or
work package.
• The metrics used to express effort are expressed in number of resource times the
duration of the work. For example, “person-hours,” “person-days,” and “person-
months.”
• Effort-driven is used to describe a task where the effort (or work) remains fixed
regardless of the number of resources used to complete the work.
3 hours of
engineering
Duration Labor
Project:
Annual Report
Deliverable 2.1:
Deliverable 1.1: Deliverable 3.1:
W-2 and W-3
Finance report Graphic design
wage filings
Work Package 3.1.1:
Cover design
Deliverable 2.2:
Deliverable 1.2: Deliverable 3.2:
Form 941
CPA review Copy edit
quarterly filing Work Package 3.1.2:
Interior layout
Deliverable 2.3:
Deliverable 1.3: Deliverable 3.3: Work Package 3.1.3:
Form 944
Auditor’s report Printing Board of Director’s
annual filing
photos
Work Package
More than 8
hours of effort Less than 80
hours of effort
Verb
Verb (Action)
(Action) Noun
Noun (Deliverable)
(Deliverable)
• A definitive list of activities that must be completed to produce the desired project
deliverables.
5
A milestone is a control point event in a
project with zero duration that triggers a
reporting requirement or requires 4
sponsor or customer approval before
proceeding with the project
3
Milestone 1 Milestone 2
Subproject 2
Mandatory
Discretionary
External
Internal
• The logical relationship between two activities that describes the sequence in which
the activities should be carried out.
• Each activity has start and finish dates.
• Precedence relationships are always assigned to activities based on the
dependencies of each activity:
• Predecessor activity drives the relationship, and most often, occurs first.
• Successor activity is driven by the relationship.
A No Lag B
10 Days 4 days
14 Days
A Lag = 4 days B
10 Days 4 days
18 Days
A B
No Lead
8 Days 6 days
14 Days
A
8 Days
Lead = 4 days
B
6 days
10 Days
A B
Start C E
D Finish
F G H I J
A B
Start C E
D Finish
F G H I J
Hammock
Design logo
GERT Network Diagram with Conditional Branch
Dig trench
Sponsor N
approval? o
Loop
Yes s N Install sump
Trench dry? o Pump trench
Demo for focus system
groups
Yes
Shared resources Used for multiple projects and must be managed as such.
• Delay some of the work until the resource can handled within
their schedule.
Assigned to an activity • Assign some of the work to another resource.
(overallocation) • Change the scope.
• Permit overallocation and compensate the resource with
overtime pay.
Project Resources
• Determine the resources necessary to complete each activity in the work packages.
• Determine the quantity of resources necessary to complete each activity.
• Refer to the resource calendars to identify the availability of each resource.
• Generate possible alternatives for unavailable resources.
• Analyze the scope statement to ensure that you identified all the resources.
• Consider organizational policies that could affect resource acquisition and usage.
• Identify and use expert judgment resources.
• Analyze the resources currently available.
• Use project management software to plan, organize and manage project schedules
and resources.
• The process of identifying and adding extra time that will serve as contingency or
management reserves to the duration estimates.
• Contingency reserves serve as buffers in recognition of scheduled risks or setbacks.
• Management reserves are buffers added to the project for unforeseen changes to
project scope and cost.
Example: Using three-point estimating for a marketing campaign project. The project manager
had these historical estimates:
• Optimistic time was one month.
• Most likely time was three months.
• Pessimistic time was 11 months.
He then estimated the project duration to be four months: [1+(4*3)+11]/6
Estimating Time
1. How do you think creating an activity list for projects will help ensure that
your project activities are tied to the project scope?