Cem Unit-2
Cem Unit-2
Unit I
Need of construction management
Objectives
Elements of project management
Construction in India
Unique Features of construction project
Types of construction projects
Stages in construction
agencies involved and their methods of execution
Project Delivery Methods
Construction Team. Organisation – principles and types.
Contents
Stages of project planning: pre-tender planning, construction
planning, detailed construction planning
Types of Project plans Time plan, man power plan, material plan,
construction equipment plan; Work break-down structure-
Methodologies of WBS; estimating durations, sequence of activities,
activity utility data;
Techniques of planning Bar charts, Networks: basic terminology,
types of precedence relationships, preparation of CPM networks:
activity on link and activity on node representation, computation of
float values, critical and semi critical paths, calendaring networks.
PERT- Assumptions underlying PERT analysis, determining three time
estimates, analysis, slack computations, calculation of probability of
completion.
Types in Project planning
Planning by owner
Pre-Tender planning
Contract planning
Planning by owner
Appoint an engineer to investigate and plan the project
for them
Prepare approximate estimate and determine capital
required.
In case of govt. projects detailed plans, estimates are
prepared by Govt. Agencies.
After the approval contracts are invited to bid for the
completion of project.
Pre-Tender planning
The planning undertaken by the contractor after receipt
of tender notice and before submitting the bid is called
pre tendering.
The planning involves the following steps
Careful study of tender documents.
To workout quantities of material required
To determine the availability of resources.
Examine the mode of execution of work.
Decide amount of Bid and Submit the tender document
Contract planning
After acceptance of tender the contractor needs further
planning
Studying the alternate method of construction
Material required ? Where to procure ? Their comparative cost ?
Recruitment and selection of human resources
Working out the detail requirement of equipment machinery
Arranging repair and maintenance facility to equipment and
machinery.
Planning for the location and other details of camp office,
service roads and layouts of site.
Transportation for labours.
To study interdependency of works and decide their proper
sequence.
Finalising the work program.
Types of project plans
Time plan
Man power plan
Material plan
Equipment plan
Time Plan
Masonry in foundation
Pointing
Coping
Work Breakdown
Guidelines for work breakdown
If the duration of an activity< project duration/1000 then level
of detail is too great
If the duration of an activity> project duration/10 then level of detail
is too shallow
The division into activities should take into account the complexity of
job (eg. Concreting), men & machine involvement
If the network is intended to be presented to top management keep minimum
details, for supervisory personnel full detail network should be presented
Bill of quantities for the work gives a fair idea of the activities to be
considered
A work breakdown structure (WBS) in construction is a
hierarchical way of organizing a building project. The WBS is
a single document that divides the project deliverables into
manageable chunks known as work packages.
Project managers create a visual representation of the
construction WBS; the image resembles a family tree or an
organization chart. At the very top of the diagram, the
finished building (or parent) appears. Each layer beneath
the parent breaks the project down into children.
Typical WBS for a
building work Building
Lean concrete in
Site clearance Plinth beams Interiors Exteriors Roof treatment
foundation
Masonry in
Excavation Columns Plastering
foundation
Anti-termite
DPC Beams and slabs Flooring
treatment
Painting
Bar chart / Gantt chart
Henry Gantt developed this technique around 1900
Conventional method of scheduling used in construction industry
Bar chart consists of two coordinate axes
Time is denoted on X-axis and on y-axis jobs/activities to be
performed
Each job is depicted in the form of a horizontal line or bar and the
length of a bar indicates duration of the job/activity
Some jobs may be taken up Concurrently thus bars for the same
may
run parallel to each other
The level of detail of the activities and the unit of time is determined
by the intended use (eg. management meeting or executives
meeting)
Development of Bar chart
Breakdown
Decide
Assign
Represent
Example of preparing bar chart for
equipment foundation
S.No. Activities Time (days)
1 Layout and excavation for foundation 5
2 Placing lean concrete (mud mat) 1
3 Fabricate shuttering 3
4 Cutting and bending of reinforcement 4
5 Reinforcement fixing 2
6 Shuttering 1
7 Concrete pouring 1
Bar chart 1 in MS
Project
Example-1
Example-2
Example-3
Exercise-1
Solution:
Limitations of bar charts
1. Interdependencies of activities
– Bar chart does not show clearly the interdependencies
among
the various
2. Project activities
progress
– A conventional bar chart does not show the progress of work,
it can be made useful by modifying with coloring/hatching to
show progress
3. Quantities of items of work
– The bar chart depicts the time schedule for various activities
but it does not indicate the quantities. It may be improved by
showing quantities of work against individual items
4. Critical activities
– Bar chart does not indicate critical activities requiring
careful
attention
Lack of Degree of details
Review of project progress
Bar chart 2 in MS
Project
Mild stone chart
It is the modification over the original Gantt chart
Mild stones are key events of main activity
These are the specific points in time which mark the
completion of certain portions of the main activity
These points are easily identified over the main bar
The beginning and end of the sub activities are
termed as mild stones
Represented by either circle or by square
Controlling become easy
Still has deficiency in showing interdependencies
Mild stone chart to Network
diagram
Project Mangement by Network
Network : A Network is a graphical and logical model or plan lists out the
sequence of various operations ( with interdependencies) which are
required to be performed
Activity : Any portions of the project which consumes time and resources
Activity is donated by arrow
B) Merge Events
Interrelationship of events
Parallel activities
Serial activities
Dummy activity
It is a type of operation in the network which neither requires any
time nor any resources, but merely a device to identify a dependence
among operations.
It is a connecting link for control purposes
It is represented with dashed arrow.
Uses of dummies
Grammatical purpose
Logical purpose
Example : Dummy activities
Function of Dummies
1. Arrows are not vectors. They are never used to indicate duration
(or time) through its length. All arrows should be of nearly equal size
wherever possible, i.e. wide variation is length of arrows should be
avoided. Length should be chosen to suit drafting requirements.
2. Orientation or angle between arrows should be chosen to suit
drafting convenience. The angle between arrows leaving or joining
nodes, should be as large as possible so that more space is available
for the addition of other relevant information in the diagram.
3. As far as possible, straight arrows should be used. Curved arrows
are not preferred.
4.Arrows should not cross each other
Representation of activities
Numbering of events
It is essential to number the events or node points.
The activities joining the nodes can better be identified on the network by
the event numbers or node numbers at the tail and head of the activity.
The event numbering should be scientifically done so that they reflect their
logical sequence. In a big network, the problem of numbering can be
simplified if the rules devised by D.R. Fulkerson are followed.
The sequential numbering to the events may be assigned in the following
steps :
There is a single initial event in a network diagram. This initial event will
have arrows coming out of it and none entering it. Number this initial event
as 1.
2. Neglect all the arrows emerging out of the initial event numbered 1.
Doing so will apparently provide one or more new initial events.
3. Number these apparently produced new initial events as 2, 3, 4 etc.
4. Again neglect all emerging arrows from these numbered events ; this will
create few more initial events.
5. Follow step 3.
How to draw network diagram
Generally CPM used for the repetitive type projects, or for the
projects for which fairly accurate estimate of time for
completion of each activity can be made
And for which cost estimate can be made with fair degree of
accuracy
How ever it is not suitable for research and development
projects
Advantages of CPM Network in execution of
projects
Calendar-wise construction schedule of activities useful to draw
schedule of men, machinery and material
Inter-relationship and sequence of various activities are clear
from network
Procurement of various resources can be done according to the
schedule
Realistic time to complete the project can be ascertained by
going into the details of time and activity sequence
During execution of the work the productivity constants can be
revised
In the event of the program getting upset due to some
unforeseen reasons, a revised CPM chart can be prepared and
prompt action can be taken to avoid further loss of resources
The network scheduling ensures the optimum use of the men,
machines and material
Activity time estimate
Deterministic approach : followed by CPM Planners
Probabilistic approach : followed by PERT planners
Optimistic time
Likely time
Pessimistic time
Earliest event time (TE):
Earliest time at which an event can occure
Example on Earliest occurrence
time
Solution
Latest allowable occurrence time (Latest event time) :
The latest time by which an event must occur to keep the
project on schedule
Denoted by TL
Previous Example : Determine
Latest allowable time
Solution:
Start and finish times of activity
Steps to be followed
Optimistic time
Pessimistic time
Most likely time
EXPECTED TIME
Three time estimates used in PERT are
1. Optimistic Time Estimate (To): shortest possible time under ideal conditions
2. Most likely Time Estimate (Tm): time for completing activity under normal
conditions
3. Pessimistic Time Estimate (Tp): Maximum time required to complete activity
under extremely adverse conditions in which everything goes wrong