Estimation & Costing - Final
Estimation & Costing - Final
2. It is used for framing the tenders for the works and to check contractor’s work during
and after the its execution for the purpose of making payments to the contractor.
3. Requirements of controlled materials, such as cement and steel can be estimated for
making applications to the controlling authorities.
4 = Good judgment with regard to different localities, different jobs and different workmen.
1. Cost per square foot of covered area (plinth area) is the most commonly adopted
criterion for preparing rough cost estimate for most of the residential buildings.
2. For public buildings, cost. Per person (cost per capita) is used. For example,
4. For water tank/reservoir, cost may be worked out on the basis of capacity in
gallons of water stored.
5. For roads and railways, cost may be found out per mile/kilometer of
length.
• The quantities for each item may be estimated and shown in the
pattern which is called "Bill of quantities."
• At the end, a total of all items of the work are made to get the total estimated
cost.
• The rates are usually as per Schedule of Rates for the locality plus a premium to
allow for rise in labor and material rates over and above the schedule of rates.
• A percentage, usually 5% is also provided on the total estimated cost for the
work to allow for the possible contingencies due to unforeseen items or
expenditure or other causes, besides 2% establishment charges.
DETAILED ESTIMATE
Besides drawings and details of measurements and calculation of quantities (Bill of Quantities), the
following documents are also usually submitted with the detailed estimate for obtaining Technical
Sanction:
A report explaining History, necessity, scope and main features of the project, its design, and estimate,
etc
Specifications lying down the nature and class of work and material to be used in various parts of the
work.
The abstract of cost (priced Bill of Quantities) showing the total quantities under each sub-head, rate
per unit of measurement, and cost.
Calculation sheets showing calculations for important parts of the structure. In fact, in
estimating the art and skill lies only in the computation of details without any omissions, of all parts of
the building or work.
1- CONTRACTOR ESTIMATE
It is made by the contractor for determining the price or
prices to be bid.
• Junctions of walls, corners and the meeting points of walls require special
attention.
• First of all, find the length of the foundation trench of the long wall “out-to-out” in the same manner
as explained above.
• The length of the foundation concrete is the same.
• For the length of the first footing or first step of the brick wall, subtract two offsets (2x6"=12") in
foundation concrete from the length of the trench or concrete.
• For the second footing subtract from the length of the 1st footing two offsets (2x2.25"= 4.5"), for 3rd
footing subtract from the length of the 2nd footing 2 offsets (4.5") and in this way deal with the long
walls up to the super-structure.
Foundation
Trench
CENTRE LINE METHOD
• In this method, total length of centre lines of walls, long and short, has
to be found out.
• Find the total length of centre lines of walls of same type, having same
type of foundations and footings and then find the quantities by
multiplying the total centre length by the respective breadth and the
height.
• In this method, the length will remain the same for excavation in
foundations, for concrete in foundations, for all footings, and for
superstructure (with slight difference when there are cross walls or
number of junctions).
• This method is quicker but requires special attention and considerations
CENTRE LINE METHOD
• For rectangular, circular polygonal (hexagonal, octagonal etc)
buildings having no inter or cross walls, this method is quite simple.
• Thus in the case of a building with one partition wall or cross wall
having two junctions, deduct one breadth of the respective item of
work from the total centre length.
CENTRE LINE METHOD
• For buildings having different types of walls, each set of walls shall have to be dealt
separately.
• Find the total centre length of all walls of one type and proceed in the same manner as
described above. Similarly find the total centre length of walls of second type and deal this
separately, and so on.
• Suppose the outer walls (main walls) are of A type and inner cross walls are of B type.
• Then all A type walls shall be taken jointly first, and then all B type walls shall be taken
together separately.
• In such cases, no deduction of any kind need be made for A type walls, but when B type
walls are taken, for each junction deduction of half breadth of A type walls (main Walls)
CENTRE LINE METHOD
w w w.t r i ko n a . c o n s k i l l . i n
http://theconstructor.org/construction/estimating-costing/
approximate-construction-cost-estimation/6483 /
C O N S k
C O N S k