Chapter Four
Chapter Four
3
…Cont’d
Planning requires an intimate knowledge of
construction methods combined with the ability
to visualize distinct work elements and to
establish their mutual interdependencies.
Construction planning is a fundamental and
challenging activity in the management and
execution of construction projects.
A good construction plan is the basis for
developing the budget and the schedule for
works.
4
…Cont’d
Construction planning consists of the following
basic steps
Choice of technology and method of construction,
Definition of work tasks,
Creating logical relationship among individual tasks
Estimation of the required resources and durations for
individual tasks
5
Project schedule
The approved Master schedule, called
the schedule baseline, is a component of
the overall project plan.
It provides the basis for measuring and
reporting schedule performance.
In PPA, the general conditions of
contract Clause 29-32 has clear
stipulation on project schedule(program),
Time Control (PPA)
Clause 27.1
The Contractor shall submit the work program showing
the general methods, arrangements, order, and timing
for all the activities in the Works within the time stated
in special condition of contract
Clause 27.2
The work program shall be updated based on the
progress of the work including any changes
Clause 27.3
The contractor is responsible for updating the
work program within the time stated in SCC
…Cont’d
Clause 27.4
The Engineer’s approval of the Program shall not
alter the Contractor’s obligations,
The Contractor may revise the Program and submit it
to the Engineer again at any time.
A revised Program shall show the effect of Variations
and Compensation Events.
Clause 28, Extension of the intended
completion date
Clause 28.1
The Engineer shall extend the Intended Completion
Date if a Compensation Event occurs or a Variation
are issued 8
…Cont’d
Clause 28.2
The Engineer shall decide whether and by
how much to extend the Intended
Completion Date within 21 days after recipt
of the time extention claim.
If the Contractor has failed to give early
warning of a delay or has failed to cooperate
in dealing with a delay, the delay by this
failure shall not be considered in assessing
the new Intended Completion Date.
9
…Cont’d
Clause 29, (Acceleration)
Clause 29.1 and 29.2
When the Employer wants the Contractor to
finish before the Intended Completion Date, the
Engineer will obtain priced proposals for
achieving the necessary acceleration from the
Contractor
If the Employer accepts these proposals,
1. the Intended Completion Date will be
adjusted accordingly and confirmed by both
the Employer and the Contractor.
2. The new proposal will be incorporated in the
Contract Price and it will be treated as a
Variation. 10
…Cont’d
Clause 30, (Delays ordered by the Engineer)
Clause 30.1
The Engineer may instruct the Contractor to delay the
start or progress of any activity within the Works.
Clause 31, ( Management Meetings)
Clause 31.1
Either the Engineer or the Contractor may require the
other to attend a Management meeting,
Clause 31.2
The Engineer shall record the business of management
meetings and provide copies of the record to those
attending the meeting and to the Employer 11
…Cont’d
Clause 32, (Early Warning)
Clause 32.1
The Contractor shall warn the Engineer at the earliest
opportunity of specific likely future events or
circumstances that may adversely affect the quality of
the work, increase the Contract Price or delay the
execution of the Works.
The Engineer may require the Contractor to provide an
estimate of the expected effect of the future event or
circumstance on the Contract Price and Completion Date
Clause 32.2
The Contractor shall cooperate with the Engineer in
making and considering proposals for how the effect of
such an event or circumstance can be 12
Performance reports
Site Diary
Progress report
Schedule
21
THANK YOU