Module 2 Creating a Task-Based Schedule
Module 2 Creating a Task-Based Schedule
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 1
Manually Scheduled vs. Auto Scheduled Tasks
For new tasks, you can select the New Tasks button in the status bar at the bottom of
the project file window.
For existing tasks, you can select the appropriate command from the Tasks group on
the Task tab of the ribbon.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 2
The Task Entry Table (1 of 2)
The default Gantt Chart view contains the Task Entry table at the left, which is the
main area where you can view, enter, and modify your project’s tasks.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 3
The Task Entry Table (2 of 2)
Task Name Displays a brief description of the task and the work to be done.
Displays how long a task will take to complete. By default, Project displays the
Duration duration in days, but you can specify minutes, hours, weeks, or even months as the
unit of time.
Start Displays the date when the task is supposed to begin.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 4
The Task Information Dialog Box (1 of 2)
You can view and modify all of the information for the task from the six tabs within
the Task Information dialog box.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 5
The Task Information Dialog Box (2 of 2)
Tab Description
Where you can view and modify the task’s name, duration, schedule mode, start
General date and finish date. This information corresponds to the fields in the Task Entry
table.
Where you can view all of the task’s predecessors, including their task ID, name,
Predecessors
and type.
Where you can view, enter, or modify the resources assigned to the task, including
Resources the resource’s name, the assignment owner, the number of assignment units
allocated to the task, and the costs associated with the resource.
Where you can view, enter or modify supplemental information about the task,
including its deadline, any constraints that might affect the task, the task type, the
Advanced
calendars or work breakdown structure that the task is associated with, whether to
mark the task as a milestone, and more.
Where you can view, enter or modify any further information for the task that may
Notes
be useful, in the form of a text note.
Where you can view, enter or modify any custom data fields that have been
Custom Fields
created and associated with the task.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 6
Task Durations
In the Task Information dialog box, the Duration field shows the amount of time it
will take to complete the specific task.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 7
Dependencies (1 of 3)
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 8
Dependencies (2 of 3)
You have to finish priming your walls (Task A) before you can start
painting them (Task B).
Start-to-Start (SS) The predecessor task must begin before the successor task can begin.
You have to start printing a book (Task A) before you can start binding it
(Task B).
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 9
Dependencies (3 of 3)
You can’t finish rerouting traffic (Task A) until you finish working on the
road (Task B).
Start-to-Finish (SF) The predecessor task must begin before the successor task can end. In
this case, the predecessor task is later in time than the successor task.
The start of a movie (Task A) concludes the sale of tickets for it (Task B).
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 10
Task Constraints
The task constraint parameters, used to control the start and finish dates for a task,
are selected from the Advanced tab of the Task Information dialog box.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 11
Deadlines (1 of 2)
Setting a deadline gives you a visual indicator in the Gantt chart —in the form of a
small green arrow—that you can use to easily monitor your progress.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 12
Deadlines (1 of 2)
You can set a deadline for a task on the Advanced tab of the Task Information dialog
box, by selecting the appropriate date from the Deadline field.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 13
User-Controlled Scheduling
Instead, you can enter this information as text in order to create a schedule that is
more a documentation of estimations and assumptions, instead of a date-based plan.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 14
Estimated Durations
If you don’t know a task’s true duration, you can enter your best guess at how long it
will take and then select the Estimated check box. A duration that has been estimated
will be shown with a question mark.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 15
Warnings and Suggestions
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 16
Summary Tasks and Subtasks
Summary tasks are bold in Subtasks are indented in Summary tasks are bracketed
the task list. the task list. in the Gantt Chart.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 17
The Project Summary Task
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 18
Outline Numbers
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 19
Milestone Tasks
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 20
Task Notes
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 21
Schedule Options
Before you insert any new tasks into an existing task list, you should modify the schedule
options for the project to ensure that new tasks are properly scheduled.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 22
Insert Task Options
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 23
Inactive Tasks
An inactive task is a task that is no longer needed in the project plan, but does not affect
resource availability or the project schedule.
When you make a task inactive, the task stays in the task list but the text is greyed out
and crossed out in strikethrough format.
You can mark a task as inactive either in the Task Information dialog box or by selecting
the Inactivate command from the Schedule command group on the Task tab.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 24
The Update Project Dialog Box
If a delay occurs in your project and you need to reschedule tasks accordingly in your
project plan, you can specify the date after which work can resume in the in the
Reschedule uncompleted work to start after field in the Update Project dialog box.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 25
Split Tasks
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 26
The Move Command
To move a task forward or backward in the scheduled or reschedule a task when resources
are available, select the appropriate option from the Move command drop-down.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 27
Master Projects and Subprojects
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 28
Insert Subproject Options (1 of 2)
In the Insert Project dialog box, you will select the file that you want to insert as a
subproject and then choose how to link the subproject file and master project file.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 29
Insert Subproject Options (2 of 2)
Option Description
Establishes a two-way link between the subproject and the master project.
Link to project and Insert
Changes made in either file will be updated in the other file.
Establishes a one-way link between the subproject and the master project.
Link to project and Insert
Changes made in the subproject file will be updated in the master project file, but
Read-Only
changes made in the master project file will not be updated in the subproject file.
Does not establish a link between the subproject and master project. Instead, a
Insert copy of the subproject data is simply inserted into the master project file, and
changes made in either file will not be updated in the other file.
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 30
The Link Between Projects Dialog Box
Copyright © 2016
2015 Logical Operations, Inc. All rights reserved. 31