Lesson 6 Earned Value Management (2)
Lesson 6 Earned Value Management (2)
A task has a
planned value
(PV) of $1000, and
actual costs (AC)
of $1000.
It appears this task
has perfect cost
performance, and
is in good shape to
finish on-budget
(Figure 1).
Figure 1
Example: (contd.)
However, if physical
progress is taken into
account, the results
may differ.
In Figure 2, the project
has spent $1000 in
actual costs, but is
behind schedule and
has only achieved
$750 of Earned Value.
This is called a cost
overrun, and this
project would have a
Cost Variance (CV) of
-$250.
Figure 2
Example: (contd.)
From this example, we can see that EVM
expands on the two-dimensional analysis–
“Has this project spent more or less money
than planned?”– by adding the third
dimension– “What did we get for the money
we spent?”
Building Blocks of Earned Value
Analysis
In addition to more accurate project status
assessment, EVM makes it easy for a project
manager to analyze both schedule and cost
performance in a variety of ways. Using a
limited set of basic task information, it is
possible not only to determine how a project
has been performing, but to predict future
performance trends as well.
Basis for Earned Value Analysis:
Budget at Completion (BAC) = Overall
approved budget for a task.
Actual Costs (AC) = Total amount spent on a
task up to the current date.
Percent Complete = Task progress, related as
either EV/BAC, or simply physical progress
shown by the fill of the task bar.
Once these three measurements have been established, the
following calculations can be performed:
Earned Value (EV) = BAC x Percent Complete. The
because the Earned Value is greater than the Actual Costs accrued:
Performance Indices:
Schedule Performance Index (SPI) = Earned
Value / Planned Value. Schedule variance related as a
ratio instead of a dollar amount. A ratio less than 1.0
indicates that work is being completed slower than
planned.
Cost Performance Index (CPI) = Earned Value /
Actual Costs. Cost variance related as a ratio instead
of a dollar amount. A ratio less than 1.0 indicates that
the value of the work that has been accomplished is
less than the amount of money spent.
In the schedule below, Project A has a CPI greater than 1.00.
This shows us that the project has been earning value faster
than it has been accruing costs:
However, Project A also has a SPI value that is less than 1.00.
Although Actual Costs are low, Task 1 is behind schedule, so
the project has not earned as much value as was planned.
Forecasting Future Performance Trends
The Schedule Performance and Cost Performance
Indices not only monitor current project performance,
they can also be used to predict future performance
trends.
To-Complete Performance Index (TCPI) = (BAC-EV) /
(BAC-AC). Indicates the CPI required throughout the
remainder of the project to stay within the stated budget.
Estimate at Completion (EAC) = AC + ((BAC-EV)/CPI).
A forecast of total costs that will be accrued by project
completion based on past cost performance trends.
Variance at Completion (VAC) = EAC – BAC. The
difference between the new Estimate at Completion and the
original Budget at Completion.
Getting Started with Earned Value
Management
Identify and Organize all Allocate the Budget and
Project Steps Schedule Tasks
What are the BCWS, ACWP, and BCWP (PV, AC, and EV)?
Answer
BCWS is $500,000.
ACWP is $486,000.
BCWP is $480,000.
From these figures we can see that the accomplishments of the
project as of today are somewhat less than what was planned for.
This is the difference between the earned value and the planned
value to date. The planned value is the BCWS and the earned value
is the BCWP. This means that we are $20,000 behind schedule.
We can also see that the actual cost is $14,000 less than the planned
expenditures to date. This means that we are somewhat under
budget. Unfortunately we are $14,000 under budget but also
$20,000 behind schedule. If we add the $20,000 of work that should
have been completed but was not, we find ourselves projecting a
$6,000 over budget condition. It could be that things are actually
worse than they appear at first glance. If the performance to date
continues, the amount over budget will probably be even higher at
the end of the project. This is usually considered a bad
EXAMPLE 1 (Q)
Provide an earned value analysis to evaluate the progress of the
sewer and water lines project. The original budget is RM147, 500
and the project is scheduled to be completed in 94 working days. A
status report after 10 working days into the project includes the
following information:
Activity 10, 100% complete as scheduled, actual cost=RM1, 500
BCWP=RM7, 600
ACWP=RM7, 700
BCWS=RM7, 600
BAC=RM147, 500
The BCWS and BCWP shown above are the same values as