GROUP C - Flashcard Games
GROUP C - Flashcard Games
Risk
assessment / Escalate
Risk Risk Accept the Known Risk
Risk Risk grading: the Risk
mitigation transfer Risk
high medium
low
Project Project
Project RAID
management Initiate Sponsor PM Owner
charter
lifecycle
EEF 2PG
OPA
Project (Enterprise (Policy,
(Organizatio Plan SoP
Strong Matrix Management environme Procedure,
nal Project
Policy ntal governanc
Asset)
factors): e
internal-
external
Benefit
Form/ Knowledge Project
realization plan Assumptio
Short term Long term Register/ Portal Success
(subsidiary n
Log
plan)
Day 1 (Page 5)
EV =
Risk Progressive Formal and AC =
Control Chart RACI Earned
severity elaboration verified Actual cost
value
Day 1 (Page 6)
EVM =
earned Simple
PV = Planned Validation Risk avoid
Process group value Overtime Structure
value scope
manageme
nt
Negative Parkinson’s
Hybrid structure Positive risk Agile
risk Law
Day 2 (24/2/24)
Central
Project Accidental
Digital Resource 5 Levels of
Supportive PMO Enterprise PMO Manageme Project
PMO Calendar Maturity
nt Support Manager
System
Sales
Program Resource Manageme Accidental PMO
Controlling PMO Management Agile PMO Optimizatio nt Office PMO Roadmap
Office n [PMP
Aspire]
Day 2 (Page 2)
Project
Develop Predictive Incrementa
Manageme
PMO Strategy PMO Roadmap Competenc Artifacts Approach l Approach
nt
ies
Approach
Vanilla Agile /
Proof of Supporting Plan Driven
Health Check PMO ROI Implement Adaptive
Concept Functions Approach
ation Approach
Day 2 (Page 4)
Minimum Emotional
4 Agile Knowledge viable Scope Technical
War Room bank
Manifesto Work Projects document impact impact
account
(MVD)
Minimum Self
12 Agile Cave & viable Schedule Positive
Co-locate organized
Principle Common product impact motivation
team
(MVP)
Requireme
nt Negative
Industrial Co Working Lean Cost Autonomy
prioritizatio motivation
Projects Space Coffee impact
n/
MoSCoW
Day 2 (Page 5)
Dynamic
system Scrum
Technical Lean- Scrum life Scrum
Agile framework developme retrospecti
excellence Kanban cycle planning ve
nt method
(DSDM)
Day 2 (Page 6)
SMART(Spe
cific,
Voice of Measurable,
Backlog Milestone / Product Process Signed
Customer Achievable,
refinement Sprint owner Groups Charter Realistic,
(VOC)
Time
bound)
ITTO (input
Velocity / Pareto
Shippable Scrum Kanban - tools & EPIC
Productivity chart
delivery master board techniques
rate
- output)
Team DOD(Defini
Developme efficiency / Expert Pareto
Shared resource Scrum roles tion of
nt team Productivit judgement Principle
Done)
y
Day 3 (01/03/2024)
Team leads
PMP
High Level Core team
Knowledge process(49 Kick off members (Project
Process group ・ Detail Manageme
area(10) ) meeting Key
Level stakeholders nt Plan)
All team
members
Communic
Baseline Subsidiary plan Scope time Cost ation
Quality
Stakeholde
Review Approver Version LEED ISO CMMI
r register
Collect
Monitoring Validate Control Scope requireme Interview
Gold plating
control scope(UAT) scope Creep nt
KII(Key Requireme
Group nt
Focus group informant Facilitated MosCow
Q&A interviews)
deception priotization
discussion Workshop
SME taking technique
Description
Conversati Confirmati Of
100 points 3Cs Card Prototype
on on Deliverable
s
Day 3 (Page 4)
Acceptance
Assumptions Constrains Exclutions
criteria
Day 4 (02/023/2024)
Breakdown
Transition Schedule activity:
Quality Stakeholder Define Activity
requireme Manageme Rolling
requirement requirement Activities attributes
nt nt wave
planning
Law of
Preferential Internal External diminishin
Sequence Mandatory Lead vs
dependenc dependenc dependenc g return
activities dependency Lag
y y y (Optimum
Level)
Day 4 (Page 2)
Planning
PERT (Project Vanilla
poker Uncertainit
3 points evaluation and wimpleme Fibonacci Complexity
(relative y
estimation review ntation (as- series
sizing
technique) is)
technique)
Functional Schedule
T-shirt sizing (S, Bottom up Develop Critical
Efforts point network
M, L, XL …) technique Schedule Path
estimation diagram
Day 4 (Page 3)
Compression
Cost Determine Activity
Project max technique (Fast Float / Estimate
manageme budget estimate
duration tracking, Slack cost
nt
Crashing)
EVM =
TCO = EAC = earned
Angel
total cost Phase gate estimate at value
Fixed cost Variable cost project
of review completion manageme
manager
ownership nt
Day 4 (Page 4)
EV =
BAC = budget PV = planned AC= actual
earned Kill point
at completion value cost
value
Day 5 (09-03-2024)
Six SIgma,
TQM,
Stack Quality Value
Confermance to Fitness for COntinuou
Quality Mgt holder mgt Stream
req Use s
satisfaction approach Mapping
Improveme
nt
Design of X
Flow (Design of Communic
Mind mapping Checklist Use case Data Model Experimen ation MGT
Diagram
t)
Push
Communic Project
Pull Political &
Encode - Interperso ation status Risk MGT
Interactive cultural
decode nal Skills requireme reporting
communication awareness
nt analysis
s
Knowledge
area base Risk
Implement Identify risk risk PESTLE TECOP VUCA
Exposure
identificati
on
Decision Positive
Risk and Stakeholde
Risk Impact Tree
Risk Ranking Response negative r
Categorization Scoring Regression
Plan risk
Analysis
Stakeholde
r Change
Identify Power Interest 7 Hat Stakeholde Engageme Request
MANCOM nt Impact
Stakeholders Grid Theory r Cube
Assessmen Analysis
t Matrix
Day 6 (10-03-2024)
Resource Man
Technical Schedule Cost Manageme Machine
Scope Impact Business Impact
Impact Impact Impact nt Material
NLP (Neuro
COntrolling
Emotional Linguisitic Fact Based Amiable Kinesthetic Mirroring
Subconscious
Intelligence Programmi Analytica Character
Mind
ng)
Stages of
Point Based
Team Norming Performing
Social Skills Performance Forming Storming
Developme
Assessment
nt
Compromis
Smoothing e Withdrawal
Team Charter/ Conflict / (Negotiatin (Avoiding)
Forcing
Adjourning Team Resolution Accommod g) (Lose /
(Win/Lose)
Agreement Technique ating (neutral / Lose)
(lose/lose) neutral)
Confrontation RFP
Procurement
(Collaboration / Source Procureme RFP VS (Request
SOW Procureme
Problem Selection nt Tender RFQ for
(Statement Of nt Method
Solving) (Win / Criteria Method Proposal)
Work)
Win)
Day 6 (Page 3)
RFI Cost
(Request Time &
RFQ R(equest EOI (Expression Financial Fixed Price Reimbursa
For Material
For Quotation) of Interest) Model Contract ble
Informatio Contract
Contract
n)
Chapter:
Chapter:
Chapter:
Chapter:
Chapter: