L8 Pac
L8 Pac
• Resources include:
People: How many people with what skills? the amount of
time they are available on a day-to-day basis.
Tooling-Any fixtures or equipment .
Machine or equipment capacity and any scheduled downtime.
Materials-what components and/or other material are needed
to complete the order.
GENERAL PAC INFORMATION AND DATA 8.1
• Due date
• Shortest processing time (SPT).
• Total slack.
• Slack per operation.
• First come, first serve.
• Critical ratio. time remaining until due divided by the
work remaining.
EXAMPLE 8.1
Suppose a work center has the following six jobs awaiting
processing (they are listed in the order in which they arrived
at the work station):
Example 8.1
• Due date
• Total slack
•Critical ratio
Scheduling in MRP and "Pull" Production Environments
• Two approach:
backward scheduling
forward scheduling
Example
Current time day 214
One shift 7 hours
Quantity required 100
Capacity available
Example
• Forward scheduling