Week 11 Project Planning
Week 11 Project Planning
CRI1C3
Proses Perangkat Lunak
Software Project
Planning
02 04
3
4
(1) Resource
Management Plan
Project Organizational
Chart
What is
this?
6
What is
this?
7
Resource Histogram
Resource Resource
Loading Levelling
Project Planning
• Business Requirements
• business and project objectives
• business rules for the performing organization
• guiding principles of the organization
• Stakeholder requirements; impacts
• Impacts to other organizational areas
• Impacts to other entities inside or outside the performing
organization
• Stakeholder communication and reporting requirements
Requirements documentation
18
• Solution requirements
• Functional and non-functional requirements
• Technology and standard compliance requirements
• Support and training requirements
• Quality requirements
• Reporting requirements
• Project requirements
• Levels of service, performance, safety, compliance
• Acceptance criteria
• Transition requirements
• Requirements assumptions, dependencies, and constraints
Create WBS
19
GOAL
Activity
Task #1 Task #2 Task #3 Task #4 … Task #n
Uses for the WBS
21
• Planning tool:
• The WBS gives the project team a detailed representation of the
project as a collection of activities that must be completed in order
for the project to be completed
• At the lowest level of WBS, we will estimate effort, elapsed time,
and resource requirements, build schedule of when work will be
completed, and estimate deliverable dates and project completion
• Project status reporting tool:
• The WBS is used as structure for reporting project status
• The WBS defines milestone events that can be reported to senior
management and to the customer
WBS completeness criteria
23
THANK YOU
31
32
32